11-29-2016 | On September 29, 2016, at Arkansas Nuclear One, Unit 1 (ANO-1), during refueling outage 1R26 with both trains of Decay Heat Removal ( DHR) in service, a 0.125 gpm leak was identified in the DHR system at a one-inch drain line.
This leak was on a section of cross-connect piping shared by both trains of the DHR system. The consequence of the leak was that both trains of the DHR system were declared inoperable.
The leakage was due to a fatigue crack caused by vibration of the drain line due to a pipe support that was not designed for system vibration.
Other systems and components in ANO-1 and ANO, Unit 2 (ANO-2) exposed to elevated system vibration were evaluated with respect to this condition. As a result of this evaluation, socket welds on other drains and vents in the ANO-1 DHR system were cut out and replaced, and pipe supports were modified where needed to withstand system vibration. |
---|
|
---|
Category:Letter
MONTHYEARML24295A1202024-10-21021 October 2024 Relief Request ANO2-RR-24-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 71 IR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 IR 05000313/20244042024-08-29029 August 2024 Cybersecurity Inspection Report 05000313/2024404 and 05000368/2024404 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 ML24128A2472024-05-0808 May 2024 Project Manager Assignment ML24017A2982024-04-18018 April 2024 Summary of Regulatory Audit Regarding the License Amendment Request to Revise Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information IR 05000313/20243012024-04-16016 April 2024 NRC Examination Report 05000313/2024301 ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML24102A1342024-03-12012 March 2024 AN1-2024-03 Post Exam Submittal IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 ML24012A0502024-02-0202 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0054 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 – Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle 2024-09-09
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR1CAN072402, Source Range Nuclear Instrument Failure Resulting in Condition Prohibited by Technical Specifications2024-07-0101 July 2024 Source Range Nuclear Instrument Failure Resulting in Condition Prohibited by Technical Specifications ML20135G7222020-05-14014 May 2020 Final ASP Analysis - ANO 1 (LER 313-96-005) 05000313/LER-2017-0022017-07-26026 July 2017 High Pressure Injection Pump Inoperable for Greater Than Technical Specification Completion Time, LER 17-002-00 for Arkansas Nuclear One, Unit 1, Regarding High Pressure Injection Pump Inoperable for Greater Than Technical Specification Completion Time 05000368/LER-2017-0022017-06-26026 June 2017 Automatic Start of an Emergency Diesel Generator Due to the Momentary Loss of Offsite Power due to Severe Weather, LER 17-002-00 for Arkansas Nuclear One, Unit 2, Regarding Automatic Start of an Emergency Diesel Generator Due to the Momentary Loss of Offsite Power due to Severe Weather 05000313/LER-2017-0012017-06-26026 June 2017 Automatic Start of an Emergency Diesel Generator Due to the Loss of Offsite Power due to Severe Weather, LER 17-001-00 for Arkansas Nuclear One, Unit 1, Regarding Automatic Start of an Emergency Diesel Generator Due to the Loss of Offsite Power due to Severe Weather 05000313/LER-2016-0032017-06-0909 June 2017 Tornado Missile Vulnerabilities Resulting in Unanalyzed Condition, LER 16-003-01 for Arkansas Nuclear One, Unit 1 Regarding Tornado Missile Vulnerabilities Resulting in Unanalyzed Condition 05000368/LER-2017-0012017-05-30030 May 2017 Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions, LER 17-001-00 for Arkansas Nuclear One, Unit 2, Regarding Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions 05000313/LER-2016-0042016-11-29029 November 2016 Decay Heat Removal System Socket Weld Leak due to a Vibration-Induced Fatigue Crack, LER 16-004-00 for Arkansas Nuclear One, Unit 1, Regarding Decay Heat Removal System Socket Weld Leak Due to a Vibration-Induced Fatigue Crack 05000368/LER-2016-0012016-11-15015 November 2016 Failure of One Emergency Diesel Generator and Subsequent Required Shutdown of Arkansas Nuclear One, Unit 2, LER 16-001-00 for Arkansas Nuclear One, Unit 2, Regarding Failure of One Emergency Diesel Generator and Subsequent Required Shutdown 05000313/LER-2016-0022016-08-11011 August 2016 Tornado Missile Vulnerability Resulting in Condition Prohibited By Technical Specifications, LER 16-002-00 for Arkansas Nuclear One, Unit 1, Regarding Tornado Missile Vulnerability Resulting in Condition Prohibited By Technical Specifications 05000313/LER-2016-0012016-05-18018 May 2016 Non-Functional External Penetration Flood Seals, LER 16-001-00 for Arkansas Nuclear One, Unit 1, Regarding Non-Functional External Penetration Flood Seals 05000313/LER-2015-0012016-02-12012 February 2016 Manual Reactor Trio Due to Oscillations in the Feedwater System, LER 15-001-00 for Arkansas Nuclear One, Unit 1, Regarding Manual Reactor Trip Due to Oscillations in the Feedwater System 2CAN051405, LER 14-01-00 for Arkansas Nuclear One, Unit 2 Regarding Operation of Switchgear Rooms Ventilation Prohibited by Technical Specifications2014-05-15015 May 2014 LER 14-01-00 for Arkansas Nuclear One, Unit 2 Regarding Operation of Switchgear Rooms Ventilation Prohibited by Technical Specifications 0CAN050202, LER 02-S01-00 for Arkansas Nuclear One Units 1 and 2, Compensatory Measures Were Removed While a Security Perimeter Intrusion Detection Microwave Field Remained Disarmed2002-05-10010 May 2002 LER 02-S01-00 for Arkansas Nuclear One Units 1 and 2, Compensatory Measures Were Removed While a Security Perimeter Intrusion Detection Microwave Field Remained Disarmed 2024-07-01
[Table view] |
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the A. Plant Status At the time this condition was identified, ANO-1 was shut down and in a refueling outage with the core fully loaded.
No structures, systems, or components were out of service at the time of this event that contributed to this event.
B. Event Description
At approximately 20:47 on September 29, 2016, the ANO-1 Control Room received a report of a leak in the ANO-1 Reactor Building (RB). Investigation revealed a 0.125 gpm leak in a class 1 pipe from a socket weld [VTV] where the drain pipe connects to the main DHR system injection line. This leak was on a section of cross-connect piping shared by both trains of the DHR system.
Operations closed RB penetrations providing direct access from the RB atmosphere to the outside atmosphere in accordance with required actions of DHR Technical Specification (TS) 3.9.5.
To reduce the potential for propagation of the weld crack, Operations maintained DHR flow at less than 2000 gpm and monitored data from vibration probes affixed to the affected piping to maintain low vibration levels.
To remove the reliance on the DHR system, actions were taken to defuel the reactor vessel, which was accomplished at 12:00 on Thursday, October 6, 2016. The leak remained less than or equal to 0.125 gpm from the time of discovery until the piping was removed from service for repair.
C. Background — System Design The DHR /Low Pressure Injection (LPI) [BP] pumps have three major functions. The first is to remove decay heat from the fuel and Reactor Coolant System (RCS) once the plant is shut down and cooled down. To do this, the DHR pump takes suction from the RCS, discharges through a cooler which is cooled by Service Water, and injects the cooled water back into the RCS. A second function is to provide required net positive suction head from the RB Sump to the High Pressure Injection (HP1) pumps in the event of an intermediate size loss-of-coolant accident (LOCA). The third function is LPI of borated water from the Borated Water Storage Tank or RB Sump into the RCS in the event of a large-break LOCA or after cooling down and depressurizing sufficiently following an intermediate break LOCA.
D. Event Cause This condition was self-revealing. The direct cause of the leak was a fatigue crack caused by vibration of the drain.
ANO's corrective actions for previous DHR/LPI system drain line socket weld cracks did not either adequately address worst case operating conditions or eliminate the source of the vibration. In addition, the DHR operating procedure contained inadequate administrative barriers to minimize DHR system vibration. Furthermore, previous corrective actions did not ensure that Operations training programs were updated regarding the basis for limiting DHR system flow to minimize system vibration.
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the 50-000313 Extent of Condition The socket welds on other drains and vents in the ANO-1 DHR system were evaluated which resulted in cut out and replacement of other vents and drains. The drain line socket welds were replaced with enhanced welds. The tie-back supports for DH-1037 and DH-1450 were designed using as-measured vibration spectra to provide hardening against system vibration. The evaluation of other systems and components identified no additional corrective actions for vibration-induced damage.
E. Corrective Actions
The corrective actions taken and planned are:
- The cracked socket weld was repaired. The tie-back drain line support was redesigned and replaced. This hardens the system against vibration-induced fatigue cracking and component damage.
- The DHR system piping and supports inside the RB were inspected for damage. No other damage was identified. The stresses on the DHR system one-inch drain line isolation valves inside the RB were calculated using as-measured response spectra to ensure acceptable performance. The socket welds for several other drain valves were cut out and replaced using enhanced welds.
- Post-modification testing of the drain valve and support modifications confirmed that the corrective actions would result in acceptable vibration of the drain lines during high system flow rates.
- The DHR operating procedure is planned to be revised to provide specific administrative guidance to minimize DHR system vibration, consistent with results of post-modification testing.
F. Safety Significant Evaluation For the function of the DHR system, the effect of the one-inch drain line completely separating from the eight-inch Core Flood Tank injection line is estimated to be a leak of 98 gpm with the backpressure that would exist at 4,000 gpm of DHR system flow. When the leak was discovered, both DHR pumps were in service. The second DHR pump was secured and the remaining pump flow was throttled back to approximately 2000 gpm (2000 gpm is adequate for core cooling at all expected decay heat levels). The maximum flow that can be provided by a DHR/LPI pump is 3547 gpm per CALC-92-E-0077-08. Therefore, the potential loss of approximately 175 gpm through the leak path would not have prevented either DHR train from providing adequate core cooling.
For the function of piggyback operation (suction from RB Sump through LPI Pump to HPI pump) the HPI pump has a maximum flowrate of approximately 525 gpm. Considering the aforementioned LPI flow capability, complete separation of the one-inch drain line would not have prevented the HPI pump from performing its specified safety function.
In the LPI mode of operation following a trip from full power, the mechanism which caused the flow-induced vibration fatigue failure would not have occurred until RCS pressure had lowered to approximately 30 psig. This is because venturi cavitation does not occur until the pressure downstream of the venturis reaches approximately 30 psig. The extent-of-condition review identified three drains that were susceptible to this vibration-induced fatigue failure. The total loss of the three drains equates to an area of about 1.56 sq. inches, which is bounded by supporting LOCA calculations. A review of the associated pump curves indicated that there is more than enough margin to account for the losses through the drain lines assuming these two failed during a LOCA.
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the Arkansas Nuclear One, Unit 1 50-000313 The significance of the leak is lessened by the fact that the leak is located inside the RB and any leaks are fully recoverable by aligning the suction of the DHR/LPI pump to the RB Sump.
Summary:
The actual consequences as stated in the problem statement were that both trains of DHR were declared inoperable. There were no other actual consequences to general safety of the public, nuclear safety, industrial safety, and radiological safety for this event.
The potential consequences to general safety of the public, nuclear safety, industrial safety, and radiological safety of this event are reduced flow to the core in the event of a large-break LOCA. However, adequate flow remains available to ensure the reactor can be maintained in a safe shutdown condition.
Based on the above, the significance of this condition is low.
G. Basis for Reportability 10 CFR 50.73(a)(2)(v)(B): Any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to remove residual heat.
10 CFR 50.73(a)(2)(v)(D): Any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to mitigate the consequences of an accident.
At the time of discovery, both trains of the DHR system were in service. Based on the location of the leak both trains of DHR were declared inoperable. With both trains being declared inoperable the associated safety function could not be met. In accordance with the NUREG-1022 guidelines, at the time of discovery ANO-1 made the 8-hour notification under EN 52271 and this LER is required.
H. Additional Information
10 CFR 50.73(b)(5) states that this report shall contain reference to "any previous similar events at the same plant that are known to the licensee." NU REG 1022 reporting guidance states that term "previous occurrences" should include previous events or conditions that involved the same underlying concern or reason as this event, such as the same root cause, failure, or sequence of events.
A review of the ANO corrective action program and LERs for the previous three years was performed. No relevant LER were similar to the failure mode.
|
---|
|
|
| | Reporting criterion |
---|
05000368/LER-2016-001 | Failure of One Emergency Diesel Generator and Subsequent Required Shutdown of Arkansas Nuclear One, Unit 2 LER 16-001-00 for Arkansas Nuclear One, Unit 2, Regarding Failure of One Emergency Diesel Generator and Subsequent Required Shutdown | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000313/LER-2016-001 | Non-Functional External Penetration Flood Seals LER 16-001-00 for Arkansas Nuclear One, Unit 1, Regarding Non-Functional External Penetration Flood Seals | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | 05000313/LER-2016-002 | Tornado Missile Vulnerability Resulting in Condition Prohibited By Technical Specifications LER 16-002-00 for Arkansas Nuclear One, Unit 1, Regarding Tornado Missile Vulnerability Resulting in Condition Prohibited By Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000313/LER-2016-003 | Tornado Missile Vulnerabilities Resulting in Unanalyzed Condition LER 16-003-01 for Arkansas Nuclear One, Unit 1 Regarding Tornado Missile Vulnerabilities Resulting in Unanalyzed Condition | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000313/LER-2016-004 | Decay Heat Removal System Socket Weld Leak due to a Vibration-Induced Fatigue Crack LER 16-004-00 for Arkansas Nuclear One, Unit 1, Regarding Decay Heat Removal System Socket Weld Leak Due to a Vibration-Induced Fatigue Crack | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident |
|