| | Q | CCA | Title |
|---|
| 05000293/FIN-2011002-03 | 2011Q1 | | Need For Clarification on Condensate Storage Tank Suction Piping ASME Classification |
| 05000293/FIN-2011002-01 | 2011Q1 | | Application of TS 3.3.8.1 When Control Rod Position Indication is Lost |
| 05000293/FIN-2011008-02 | 2011Q1 | P.2 | Torus Air Temperature 10 CFR 50.65(a)(2) Performance Demonstration Not Met |
| 05000293/FIN-2011002-02 | 2011Q1 | P.2 | Inadequate Corrective Actions for RCIC Torus Suction Valve |
| 05000293/FIN-2011008-01 | 2011Q1 | P.1 | Failure to Follow Corrective Action Process for HPCI Diaphragm Degraded Condition |
| 05000293/FIN-2011011-01 | 2011Q2 | | Security |
| 05000293/FIN-2011004-02 | 2011Q3 | H.14 | Failure to Identify a Primary Containment System Maintenance Rule Functional Failure and Thereby Establish Monitoring Requirements for the System |
| 05000293/FIN-2011004-03 | 2011Q3 | H.5 | Failure to Accurately Assess Risk of Maintenance on Standby Gas and Secondary Containment |
| 05000293/FIN-2011012-01 | 2011Q3 | H.12 | Failure to Implement Conduct of Operations and Reactivity Control Procedures during Reactor Startup |
| 05000293/FIN-2011004-01 | 2011Q3 | | Failure to Verify the Adequacy of the Design for the \'C\' Salt Service Water Pump |
| 05000293/FIN-2011003-05 | 2011Q3 | H.14 | Failure to Enter Technical Specifications after Loss of Control Rod Indication |
| 05000293/FIN-2011003-04 | 2011Q3 | H.4 H.5 | Failure to Enter Technical Specifications for CHREAFS |
| 05000293/FIN-2011003-03 | 2011Q3 | H.13 | lnadequate Risk Assessment for Planned Maintenance and Testing on RCIC, SLC and ATS Systems |
| 05000293/FIN-2011003-02 | 2011Q3 | P.3 | Submerged Medium Voltage Cables |
| 05000293/FIN-2011003-01 | 2011Q3 | H.4 H.5 | Transient Combustible Loading in SLC Room in Excess of the Fire Hazards Analysis Limit |
| 05000293/FIN-2011005-05 | 2011Q4 | | Written NRC Biennial Written Examinations did not meet Qualitative Standards |
| 05000293/FIN-2011007-01 | 2011Q4 | | Inadequate Evaluation of the Adequacy of the 4160 Volt Emergency Bus 95% Voltage Alarm and Load Shed Relay Design |
| 05000293/FIN-2011007-02 | 2011Q4 | H.7 | Inadequate Test Control of Safety Related Batteries |
| 05000293/FIN-2011007-03 | 2011Q4 | | Inadequate Evaluation of the Affect of Non Class I Equipment Internal Flooding on Redundant Safety Related Equipment |
| 05000293/FIN-2011005-04 | 2011Q4 | | Entergy Incorrectly Credited Operators Proficiency Watch-Standing Experience and the Operators subsequently stood watch |
| 05000293/FIN-2011005-03 | 2011Q4 | | Entergy did not Notify the NRC within 30 days of discovering changes in Medical Conditions |
| 05000293/FIN-2011405-01 | 2011Q4 | P.5 | Security |
| 05000293/FIN-2011005-02 | 2011Q4 | | Entergy did not Provide Complete and Accurate Medical Information for Licensed Operator Renewal Applications |
| 05000293/FIN-2011005-01 | 2011Q4 | | Licensed Operators Stood Watch Without Being Medically Qualified |