05000285/FIN-2009007-02
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Perform Vendor and Industry Recommended Testing on Safety-Related and Risk Significant 4160 and 480 V Circuit Breakers |
Description | The team identified an unresolved item associated with inadequate maintenance procedures for 4160 and 480 V safety-related breakers. The team determined that maintenance procedures used to ensure that 4160 and 480 V safetyrelated breakers were being maintained and overhauled in a timely manner were inadequate. The licensee had no engineering analysis or technical basis to justify the deviation from vendor/Electric Power Research Institute guidance. At the end of the inspection, the licensee identified approximately 20 breakers that had failed over the last15 years and the team was waiting for additional information to determine if the failures were related to the inadequate maintenance. The team identified that the licensee was not performing the maintenance on the breakers as recommended by the vendor or Electric Power Research Institute guidelines. The licensee had completed a review of its breaker maintenance programs in November 2007 and modified it based on Electric Power Research Institute Documents TR-106857-V2 and TR-106857-V3, which are preventive maintenance program bases for low and medium voltage switchgear. The licensee only implemented portions of the recommended maintenance program, and had no engineering analysis or technical basis to justify the changes. Additionally, the guidance states in part that, this program assumes breakers are in nominally good condition to begin with. Breakers that have not been serviced for a very long time may need an overhaul or have a detailed inspection performed before this program is applied. The licensee had not been performing the entire vendor or Electric Power Research Institute recommended tests, inspections, and refurbishments on the breakers since installation. The team reviewed the licensee\'s circuit breaker maintenance procedures and records. The team determined that the licensee had not refurbished Asea Brown Boveri 4160 or General Electric 480 V safety-related and risk significant non-safety-related circuit breakers within the vendor specified 10-year maximum overhaul periodicity or the Electric Power Research Institute guidance of 12 years and had no engineering basis or evaluation to justify the deviation. The team compared the Electric Power Research Institute guidance and vendor-recommended maintenance requirements against the licensee\'s maintenance procedures and found that the licensee was not performing some of the recommended activities or had extended the periodicity of some inspections beyond even the Electric Power Research Institute recommended guidelines. The Fort Calhoun Station program for medium and low voltage switchgear and circuit breakers did not include most of the recommended testing and trending. Specifically, no testing of the operation of the 125-V DC control circuitry was performed at the voltages postulated to exist at the device terminals during design basis events. Contemporary industry standards and Electric Power Research Institute guidance recommend reduced control voltage testing as part of breaker maintenance. Vendor overhaul procedures include reduced control voltage testing on the as-found and as-left control circuit. While there is not an explicit requirement to perform reduced voltage testing on breaker control circuitry, the Electric Power Research Institute guidance recommends reduced voltage testing on breaker control circuitry in order to have reasonable assurance of reliable operation of control circuitry at the postulated minimum control voltage. Additional recommended testing per the preventative maintenance program basis DocumentsTR-106857-V2 and TR-106857-V3 that were not being performed included: Thermography inspections of the breakers and switchgear at recommended periodicity and trending, and: Measurement of the electrical resistance of coils and relays, trended over time to detect progressive failure of winding insulation and give an indication of the condition of these electrical devices. As a result, the team requested the basis for not performing all of the recommended maintenance activities. The licensee was unable to produce an engineering evaluation that allowed the use of the Electric Power Research Institute guidance versus the vendor guidance. Additionally, the team found that the licensee failed to update their in-use guidance when operating experience or new vendor information were issued. Because the licensee was unable to produce documentation demonstrating recommended maintenance had been performed at the appropriate intervals or which qualified the practice of extending the maintenance and refurbishment intervals, the team was concerned about the reliability of the safety-related and safety significant breakers that had not been overhauled within 10 years.n The licensee stated that the 10-year vendor requirement was based on breakers manufactured and lubricated with petroleum-based grease and that their Asea Brown Boveri circuit breakers were lubricated with synthetic-based grease, Anderol 757, which does not dry out as fast and extends the useful life of the lubrication. The licensee cited a May 11, 1995, letter from Asea Brown Boveri/Combustion Engineering that implied grease hardening was not an issue with Anderol 757 lubricant. The team identified operating experience which showed that other licensees had experienced grease hardening in Asea Brown Boveri breakers that contained the Anderol 757.Following the10 CFR Part 21 report issued by D. C. Cook on March 3, 1989, Asea Brown Boveri established the 10 year overhaul frequency. This report was issued after two Asea Brown Boveri 4160 V breakers failed to close because of hardened grease in their operating mechanism. Additional operating experience from Perry supported that grease hardening can occur in less than ten years, pertaining to the 4160 V C residual heat removal (RHR) pump breaker. It stated in part, Various anomalies were identified during the process of disassembling the breaker, and the lubricant within the operating mechanism appears to be hardened. Based on the breaker serial number it was determined that this breaker would have used the synthetic lubricate. This provided further evidence that synthetic grease can degrade in less than 10 years. Asea Brown Boveri breaker historical industry data showed that the lubrication in the operating mechanism tended to harden within 10 years and that this condition can cause sluggish breaker operation. The issue was entered into the licensees corrective action program- 14 V Enclosure and was being evaluated under Condition Report 2009-2306. This issue is unresolved pending review of the causes of the breaker failures as related to the improperly performed maintenance (Unresolved Item 05000285/2009007-02) |
Site: | Fort Calhoun ![]() |
---|---|
Report | IR 05000285/2009007 Section 4OA2 |
Date counted | Jun 30, 2009 (2009Q2) |
Type: | URI: |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | J Kirkland G Werner M Vasquez P Goldbergl Ricketsonj Kirkland D Stearns G George J Clark D Graves I Anchondo W Schaup T Buchanan R Hickok N Greene J Wingebach |
INPO aspect | |
' | |
Finding - Fort Calhoun - IR 05000285/2009007 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Fort Calhoun) @ 2009Q2
Self-Identified List (Fort Calhoun)
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||