05000277/FIN-2012002-03
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Untimely Corrective Actions Resulted in Spent Fuel Pool Boraflex Degradation Exceeding Design Limits |
Description | The inspectors identified a PD that was determined to be a finding of very low safety significance (Green) involving a NCV of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for the failure by PBAPS to take timely corrective action to correct a condition adverse to quality and the inability to comply with Design Technical Specification (TS) 4.3.1.1.b which requires, in part, that spent fuel pool (SFP) storage racks are designed and maintained with keff less than or equal to 0.95. Specifically, although PBAPS was aware of degradation of neutron absorbing material (Boraflex) within the SFP storage racks since at least 1996, PBAPS did not take effective measures to adequately monitor or manage the degradation to assure sufficient margin to criticality was maintained. Rather, in 2010, PBAPS deferred corrective actions in the SFPs until 2014 based on an operability determination (OD) that concluded sufficient margin would exist until that time. However, the NRC concluded that the OD did not accurately project the rate of boron degradation, and used several non-conservative assumptions. In June 2011, after addressing the errors in the OD, PBAPS declared 117 spent fuel bundle rack storage cells inoperable since the estimated Boraflex degradation indicated that PBAPS had exceeded design TS 4.3.1.1.b. The PD was more than minor because it was similar to IMC 0612, Appendix E, Examples of Minor Issues, Example 3.j, which considers that an issue is more than minor if an engineering calculation error results in a condition where there is now a reasonable doubt on the operability of a system or component, or if significant programmatic deficiencies were identified with the issue that could lead to more significant errors if uncorrected. Using IMC 0609, Attachment 4, Phase 1 Initial Screening and Characterization of Findings, the inspectors attempted to evaluate the risk significance of this issue. Applying the guidance in Table 3b, the inspectors made the assumption that the risk associated with this PD most appropriately impacted the Initiating Events cornerstone. A Region I Senior Reactor Analyst (SRA) determined that there were no probabilistic risk assessment tools currently available to adequately assess the risk of a SFP criticality event. Consequently, the inspectors followed the guidance in the Phase 1 SDP screening worksheet, Table 3b, Step 6, which states, in part, that where the SDP guidance is not adequate to provide reasonable estimates of a findings significance, use IMC 0609, Appendix M, SDP Using Qualitative Criteria. Using Appendix M, the inspectors identified criteria and associated considerations that supported the overall qualitative risk assessment. On April 3, 2012, a Significance and Enforcement Review Panel (SERP) was conducted involving staff from Region I, the Office of Nuclear Reactor Regulation, and the Office of Enforcement to discuss the significance of this event. The SERP determined the PD and subsequent consequences resulted in a condition of very low safety significance (Green), based on an assessment using Appendix M attributes. This finding was also determined to have a cross-cutting aspect in the area of Problem Identification and Resolution - Evaluation P.1(c). Specifically, Exelon did not properly evaluate a condition adverse to quality for operability in that the 2010 OD did not accurately predict the rate of Boraflex degradation and whether the issue challenged current SFP operability. |
Site: | Peach Bottom ![]() |
---|---|
Report | IR 05000277/2012002 Section 4OA2 |
Date counted | Mar 31, 2012 (2012Q1) |
Type: | NCV: Green |
cornerstone | Initiating Events |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | J Furia A Rosebrook S Hansell A Ziedonis P Krohn |
CCA | P.2, Evaluation |
INPO aspect | PI.2 |
' | |
Finding - Peach Bottom - IR 05000277/2012002 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Peach Bottom) @ 2012Q1
Self-Identified List (Peach Bottom)
| ||||||||||||||||||||||||||||||||||||||||||||||||||||