Finding | |
|---|---|
| Title | Failure to Ensure Adequate Control of Foreign Material in Safet-Related Systems |
| Description | A self-revealed finding of very low safety significance and associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, was identified for the failure to ensure adequate control of foreign material in accordance with the requirements of procedure NP 8.4.10, Exclusion of Foreign Material from Plant Components and Systems. Specifically, on October 17, 2009, foreign material was discovered inside the 2SI-897B valve after the valve failed to properly stroke during the performance of procedure IT-215, SI Valves - Cold Shutdown. The licensee took prompt corrective actions to repair the valve and perform an extent-of-condition review. Additionally, upon entering the issue into its corrective action program, the licensee performed a causal evaluation to determine any additional corrective actions. The finding was more than minor because it was associated with the Barrier Integrity Cornerstone attribute of human performance and adversely affected the associated cornerstone objective of providing reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, due to the interference caused by the foreign material inside the 2SI-897B valve, the valve would not have been able to perform its safety function to close during the initiation of the post-LOCA (loss of coolant accident) sump-recirculation phase of safety injection. The inspectors determined the finding could be evaluated in accordance with IMC 0609, Significance Determination Process, Attachment 0609.04, Phase 1 - Initial Screening and Characterization of Findings, Table 4a, dated January 10, 2008. The finding was determined to be of very low safety significance because the issue did not represent a degradation of the radiological barrier function provided for the control room, the auxiliary building, or the spent fuel pool; represent a degradation of the barrier function of the control room against smoke or a toxic atmosphere; represent an actual open pathway in the physical integrity of reactor containment (valves, airlocks, containment isolation system (logic and instrumentation)), and heat removal components; or involve an actual reduction in function of hydrogen ignitors in the reactor containment. No cross-cutting aspect was identified because the foreign material was determined to have been introduced into the system in the past and was not considered indicative of current performance. (Section 1R15.1 |
| Site: | Point Beach |
|---|---|
| Report | IR 05000266/2009005 Section 1R15 |
| Date counted | Dec 31, 2009 (2009Q4) |
| Type: | NCV: Green |
| cornerstone | Barrier Integrity |
| Identified by: | Self-revealing |
| Inspection Procedure: | IP 71111.15 |
| Inspectors (proximate) | D Jones D Mcneil E Sanchez Santiago J Cassidy J Gilliam J Jandovitz M Kunowski M Thorpe Kavanaugh N Feliz Adorno R Edwards R Jickling R Ruiz S Burton |
| INPO aspect | |
| ' | |