Title | Failure to Follow Site Procurement Procedure for EDG Temperature Control Valve Elements |
Description | The inspectors identified a Green NCV of 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings because Entergy personnel did not implement the requirements of procedure SAO-270, Procurement Program, for the procurement of safety related temperature control valve (TCV) elements for the emergency diesel generators (EDGs). Specifically, Entergy did not perform a technical evaluation as required for the TCV elements which resulted in the purchase and installation of incorrect TCV elements on the 21 and 22 EDGs between 2002 and 2003. The inspectors determined that this finding was more than minor because it was associated with the human performance attribute of the Mitigating Systems cornerstone and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors evaluated this finding using the Phase 1 analysis in IMC 0609, Appendix A, Determining the Significance of Reactor Inspection Findings for At- Power Situations. The inspectors determined that this finding was of very low safety significance (Green) because the installation of incorrect TCV elements represented a design deficiency that was confirmed not to result in a loss of operability of the EDGs. Specifically, engineering analysis verified past EDG operability was maintained based on analysis that assumed the highest observed service water temperature over the past three years. Entergy entered this issue into the corrective action program and installed the correct TCV elements in 21 and 22 EDGs. |
Site: | Indian Point ![]() |
---|---|
Report | IR 05000247/2008003 Section 1R15 |
Date counted | Jun 30, 2008 (2008Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.15 |
Inspectors (proximate) | A Koonce A Patel C Hott F Arner H Gray J Noggle J Richmond M Gray M Marshfield P Cataldo R Mckinley S Barr S Smith |
INPO aspect | |
' | |