05000220/FIN-2012004-03
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Inadequate Installation Instructions for Control Rod Blade Storage Rack |
Description | A self-revealing Green finding (FIN) was identified for NMPNS failure to provide adequate instructions for the installation of a control rod blade storage rack in the Unit 1 spent fuel pool. Specifically, certain critical steps were missing from the installation instructions and as a result, the rack was not properly installed, causing it to shift. The rack could have dropped, potentially resulting in damage to the spent fuel bundles stored beneath the rack. NMPNS immediate CAs were to halt further control rod blade moves and install temporary slings to hold up the rack. The rack was then re-leveled and the jacking pad was welded to the spent fuel pool curb. NMPNS entered this issue into its corrective action program as CR 2012-006547. This finding is more than minor because it would have the potential to lead to a more significant safety concern; e.g. spent fuel bundle damage and a radiological release. The inspectors evaluated the finding using Attachment 0609.04 of Inspection Manual Chapter (IMC) 0609, Significance Determination Process, Exhibit 3, Barrier Integrity Screening Questions, pertaining to spent fuel pools and determined this finding to be of very low safety significance (Green), because the finding did not adversely affect decay heat removal capabilities or pool water inventory, and did not result from fuel handling errors, dropped fuel assembly, dropped storage cask, or crane operations over the spent fuel pool that caused mechanical damage to fuel clad and a detectible release of radionuclides. The finding has a cross-cutting aspect in the area of work practices because NMPNS did not ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported. Specifically, NMPNS supervision did not ensure that critical assumptions contained in the control rod storage rack design analysis concerning the configuration of the Unit 1 spent fuel pool curb were translated into the installation instructions, and differences between Units 1 and 2 curbs noted during the installation were captured or evaluated by engineering, work control, or the CA process. |
Site: | Nine Mile Point |
---|---|
Report | IR 05000220/2012004 Section 1R18 |
Date counted | Sep 30, 2012 (2012Q3) |
Type: | Finding: Green |
cornerstone | Initiating Events |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71111.18 |
Inspectors (proximate) | L Scholl D Dempsey K Kolaczyk B Haagensen G Dentel J Krafty C Crisden B Dionne E Miller |
CCA | H.2, Field Presence |
INPO aspect | LA.2 |
' | |
Finding - Nine Mile Point - IR 05000220/2012004 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Nine Mile Point) @ 2012Q3
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||