Semantic search
Jump to navigation
Jump to search
Issue date | Title | |
---|---|---|
IR 05000454/2023002 | 3 August 2023 | Integrated Inspection Report 05000454/2023002 and 05000455/2023002 |
IR 05000454/2022004 | 1 February 2023 | Integrated Inspection Report 05000454/2022004 and 05000455/2022004 |
RS-22-057, Constellation Radiological Emergency Plan Addendum Revision | 21 April 2022 | Constellation Radiological Emergency Plan Addendum Revision |
RS-20-130, License Amendment Request - Proposed Changes to Byron Emergency Plan for Post-Shutdown and Permanently Defueled Condition | 2 November 2020 | License Amendment Request - Proposed Changes to Byron Emergency Plan for Post-Shutdown and Permanently Defueled Condition |
ML20141L636 | 10 July 2020 | Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2 |
ML19331A725 | 14 February 2020 | Issuance of Amendments Revising Emergency Action Levels |
ML19269C098 | 24 September 2019 | 54018-CALC-01, Byron Station: Evaluation of Risk Significance of Permanent ILRT Extension. |
ML19269C094 | 24 September 2019 | 54017-CALC-01, Braidwood Station: Evaluation of Risk Significance of Permanent ILRT Extension. |
RS-18-142, Application to Revise Braidwood Station and Byron Station Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended. | 13 December 2018 | Application to Revise Braidwood Station and Byron Station Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended. |
ML18264A092 | 22 October 2018 | Issuance of Amendment Nos. 198, 198, 204, and 204, Respectively, Regarding Adoption of Title 10 of the Code of Federal Regulations Section 50.69 CAC Nos. MG0201, MG0202, MG0203, and MG0204; EPID-L 2017-LLA-0285) |
RS-18-102, License Amendment Request for a One-Time Extension to Technical Specification 3.8.1, AC Sources-Operating, Required Action A.2 | 10 August 2018 | License Amendment Request for a One-Time Extension to Technical Specification 3.8.1, AC Sources-Operating, Required Action A.2 |
RS-17-170, Company Emergency Plan Annex and Addendum Revisions | 19 December 2017 | Company Emergency Plan Annex and Addendum Revisions |
ML17346A679 | 14 November 2017 | Final After Action Report/Improvement Plan for the Byron Station Radiological Emergency Preparedness Exercise Held on September 26, 2017 |
ML17271A178 | 21 September 2017 | Radiological Emergency Plan Annex and Addendum Revisions |
RS-17-123, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors. | 1 September 2017 | Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors. |
IR 05000454/2017001 | 4 May 2017 | NRC Integrated Inspection Report 05000454/2017001; 05000455/2017001 and Exercise of Enforcement Discretion |
IR 05000454/2016004 | 24 January 2017 | NRC Integrated Inspection Report 05000454/2016004; 05000455/2016004; 07200068/2016001 and Emergency Preparedness Annual Inspection Report 05000454/2016501; 05000455/2016501 |
ML16334A504 | 19 December 2016 | Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 |
RS-16-248, Redacted Braidwood Nuclear Stations, Revision 16 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics - Braidwood | 15 December 2016 | Redacted Braidwood Nuclear Stations, Revision 16 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics - Braidwood |
IR 05000454/2016002 | 26 July 2016 | NRC Integrated Inspection Report 05000454/2016002; 05000455/2016002 and Exercise of Enforcement Discretion (EA-16-125) |
RS-16-088, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | 15 July 2016 | Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) |
RA-16-049, Response to Request for Additional Information Regarding Requests to Withhold Emergency Preparedness Documents from Public Disclosure | 26 May 2016 | Response to Request for Additional Information Regarding Requests to Withhold Emergency Preparedness Documents from Public Disclosure |
IR 05000454/2016001 | 25 April 2016 | NRC Integrated Inspection Report 05000454/2016001; 05000455/2016001, January 1, 2016 Through March 31, 2016 |
RS-16-060, EP-AA-1002, Addendum 3, Revision 1, Emergency Action Levels for Byron Station. | 14 March 2016 | EP-AA-1002, Addendum 3, Revision 1, Emergency Action Levels for Byron Station. |
IR 05000454/2015004 | 27 January 2016 | IR 05000454/2015004, 05000455/2015004; 10/01/2015 - 12/31/2015; Byron Station, Units 1 and 2; Inservice Inspection Activities, Post Maintenance Testing, and Outage Activities |
RS-15-209, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | 28 August 2015 | Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) |
IR 05000454/2015002 | 22 July 2015 | IR 05000454/2015002, 05000455/2015002, 07200068/20150001; on 04/01/2015 - 06/30/2015; Byron Station, Units 1 and 2; Routine Integrated Inspection Report |
RA-15-019, Attachment 3 - EP-AA-1002, Revised Radiological Emergency Plan Annex Information for Byron Station | 3 March 2015 | Attachment 3 - EP-AA-1002, Revised Radiological Emergency Plan Annex Information for Byron Station |
ML15071A128 | 3 March 2015 | Attachment 3 - EP-AA-1002, Revised Radiological Emergency Plan Annex Information for Byron Station |
RA-15-019, Attachment 1 - Response to the Request for Additional Information - License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors | 2 March 2015 | Attachment 1 - Response to the Request for Additional Information - License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors |
ML15071A119 | 2 March 2015 | Attachment 1 - Response to the Request for Additional Information - License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors |
IR 05000454/2014003 | 25 July 2014 | IR 05000454-14-003, 05000455-14-003; 04/01/2014-06/30/2014; Byron Station, Units 1 & 2; Routine Integrated Inspection |
ML14198A559 | 24 July 2014 | Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 |
NEI 99-01, Byron, Units 1 and 2, Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3A, 3B, Cover - by 3-74 | 30 May 2014 | Byron, Units 1 and 2, Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3A, 3B, Cover - by 3-74 |
NEI 99-01, Byron, Units 1 and 2, Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3B, 3C, by 3-75 - by 3-157 | 30 May 2014 | Byron, Units 1 and 2, Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3B, 3C, by 3-75 - by 3-157 |
RA-14-032, Byron, Units 1 and 2, Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3B, 3C, by 3-75 - by 3-157 | 30 May 2014 | Byron, Units 1 and 2, Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3B, 3C, by 3-75 - by 3-157 |
RA-14-032, Byron, Units 1 and 2, Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3A, 3B, Cover - by 3-74 | 30 May 2014 | Byron, Units 1 and 2, Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3A, 3B, Cover - by 3-74 |
ML14164A060 | 30 May 2014 | Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3A, 3B, Cover - by 3-74 |
ML14164A061 | 30 May 2014 | Attachment 3, Discussion of Revision to the Radiological Emergency Plan Annex, EP-AA-1002, NEI 99-01, Rev. 6, Development of Emergency Action Levels for Non-Passive Reactors, Enclosures 3B, 3C, by 3-75 - by 3-157 |
IR 05000454/2014002 | 7 May 2014 | IR 05000454-14-002, 05000455-14-002 and 07200068-14-001; 01/01/2014 - 03/31/2014; Byron Station, Units 1 & 2; Fire Protection |
ML14079A423 | 12 March 2014 | Enclosure 1, Byron Nuclear Generating Station, Flood Hazard Reevaluation Report, Revision 0 |
ML14007A083 | 19 December 2013 | Response to NRC Request for Additional Information, Dated November 21, 2013, Related to the Byron and Braidwood Stations, Units 1 and 2 License Renewal Application, Byron Station Applicant'S Environmental Report. Part 2 of 15 |
ML13225A595 | 17 December 2013 | Interim Staff Evaluation Related to Integrated Plan in Response to Order EA-12-049(Mitigation Strategies) |
ML13338A642 | 9 December 2013 | Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Byron Station, Units 1 and 2, TAC Nos.: MF0893 and MF0894 |
IR 05000455/2013003 | 1 August 2013 | IR 05000455-13-003 & 05000455-13-003; Exelon Generation Company, LLC; 04/01/2013 - 06/30/2013; Byron Station, Units 1 and 2, NRC Integrated Inspection Report |
IR 05000454/2013003 | 1 August 2013 | IR 05000455-13-003 & 05000455-13-003; Exelon Generation Company, LLC; 04/01/2013 - 06/30/2013; Byron Station, Units 1 and 2, NRC Integrated Inspection Report |
ML13162A370 | 31 May 2013 | Applicant'S Environmental Report Operating License Renewal Stage, Byron Station, Units 1 and 2. Appendix F |
ML13155A423 | 29 May 2013 | Environmental Report, Part 2 |
RS-13-145, Byron, Units 1 and 2 - Environmental Report, Part 2 | 29 May 2013 | Byron, Units 1 and 2 - Environmental Report, Part 2 |
RS-13-018, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | 28 February 2013 | Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) |