NRC Generic Letter 91-18, Information to Licensees Regarding Two NRC Inspection Manual Sections on Resolution of Degraded and Nonconforming Conditions and on Operability

From kanterella
Jump to navigation Jump to search

text

October 8, 1997

NRC GENERIC LETTER NO. 91-18, REVISION 1: INFORMATION TO LICENSEES REGARDING NRC INSPECTION MANUAL SECTION ON RESOLUTION OF DEGRADED AND NONCONFORMING CONDITIONS

Addressees

All holders of operating licenses for nuclear power and non-power reactors,

including those power reactor licensees who have permanently ceased

operations, and all holders of non-power reactor licenses whose license no

longer authorizes operation.

Purpose

The U.S. Nuclear Regulatory Commission (NRC) is issuing this generic letter to

inform licensees of the issuance of a revised section of Part 9900, "Technical

Guidance," of the NRC Inspection Manual. The revised section is entitled

"Resolution of Degraded and Nonconforming Conditions." The revisions to this

section of Part 9900 more explicitly discuss the role of the 10 CFR 50.59

evaluation process in the resolution of degraded and nonconforming conditions.

The Part 9900 guidance on operability forwarded by Generic Letter (GL) 91-18

has not been revised. This letter is provided for information only; no

specific action or written response is required.

Background

The previous version of NRC Inspection Manual, Part 9900, "Technical

Guidance," on the Resolution of Degraded and Nonconforming Conditions, was

issued for information in GL 91-18, on November 7, 1991. This guidance

provided a process for licensees to develop a basis to continue operation or

to place the plant in a safe condition and to take prompt corrective action.

It contained a number of provisions that relate to the role of 10 CFR 50.59

and the basis for continued operation of a facility.

Section 4.3.2, "Changing the Current Licensing Basis To Satisfy an Appendix B

Corrective Action," stated:

A licensee may change the design of its plant as described in the

FSAR in accordance with 10 CFR 50.59, at any time. Whenever such

changes are sufficient to resolve a degraded or nonconforming

condition involving an SSC [system, structure, or component] that

is subject both to Appendix B and 50.59, they may be used in lieu

of restoring the affected equipment to its original design. However, whenever such a change involves a unreviewed safety

question (USQ) or change in a technical specification (TS), the licensee

must obtain a license amendment in accordance with 10 CFR 50.90 prior to

operating (emphasis added) the plant with the degraded or nonconforming

condition...

Section 4.5.1, "Justification for Continued Operation (JCO) Background,"

stated:

The license authorizes the licensee to operate the plant in

accordance with the regulations, license conditions, and the TS.

If an SSC is degraded or nonconforming but operable, the license

provides authorization to operate and the licensee does not need

further justification. The licensee must, however, promptly

identify and correct the condition adverse to safety or quality in

accordance with 10 CFR Part 50, Appendix B, Criterion XVI.

A footnote to the flow chart attached to the Part 9900 guidance stated:

50.59 may be used to make a change in a facility, as described in

the SAR, which would resolve the condition adverse to safety or

quality so that the degraded and nonconforming condition no longer

exists. Delay or partial correction of conditions adverse to

safety or quality is considered a change in facility or procedures

and subject to 50.59 review.

The NRC Inspection Manual Part 9900 guidance, "10 CFR 50.59 - Interim Guidance

on the Requirements Related to Changes to Facilities, Procedures, and Tests

(or Experiments)," issued in April 1996, specifically refers to the Part 9900

attached to GL 91-18 for guidance concerning 10 CFR 50.59 in the resolution of

degraded and nonconforming conditions.

As part of its reevaluation of the 10 CFR 50.59 process, the staff recognized

that the guidance in GL 91-18 was not complete, and may in some respects be

inconsistent. Therefore, the staff developed additional guidance on the

application of 10 CFR 50.59 to the resolution of degraded and nonconforming

conditions. The staff's proposed guidance was published for public comment,

as part of draft NUREG-1606, "Proposed Regulatory Guidance Related to

Implementation of 10 CFR 50.59 (Changes, Tests, or Experiments)," on May 7,

1997 (62 FR 24947).

Description of Circumstances

The proposed guidance published for comment on May 7, 1997, discussed the

application of 10 CFR 50.59 to implementation of compensatory measures, how

"delay" should be interpreted, and how the guidance about obtaining a license

amendment operating the facility with a condition involving a USQ should be

interpreted. In this proposed guidance, the staff stated that implementation

of compensatory measures required a 10 CFR 50.59 evaluation with respect to

the condition described in the final safety analysis report (FSAR) and that

the staff would consider delay to have occurred when a licensee has not

implemented corrective action at the first available opportunity (considering

need for analysis or parts, or the need to be in cold shutdown to complete the

action), in any event not to exceed the next refueling outage. Finally, the

staff proposed that when a licensee determined that resolution of a nonconforming condition involved a USQ, the license amendment should be issued

before the plant resumed operation from any shutdown (the NRC would not

require a plant to shut down in such circumstances provided that SSCs required

for operation were operable). Over the last several months, a number of

nonconforming conditions have been identified at operating plants through

licensee reviews and NRC inspections. Based on staff experience in dealing

with these situations, the staff has concluded that a revision to the

Part 9900 guidance, "Resolution of Degraded and Nonconforming Conditions," was

appropriate.

Many of the comments received in response to the Federal Register notice

stated that the position that should be applied is more consistent with the

discussion in Section 4.5.1 of the existing Part 9900 guidance, that is, if

SSCs are operable but degraded, the license provides authority for continued

operation, and existence of a USQ, by itself, should not be an impediment to a

plant's ability to resume operation.

Commenters noted that the policy of not requiring plant shutdown but

preventing plant restart was arbitrary, and had no basis in safety.

Commenters also suggested that delay in implementation of corrective action is

a matter for enforcement of 10 CFR Part 50, Appendix B, and not for requiring

a 10 CFR 50.59 evaluation. The commenters also stated that requiring a 10 CFR 50.59 evaluation of compensatory measures against the condition described in

the safety analysis report (SAR) would essentially preclude licensee

implementation of compensating actions that enhance safety when degraded or

nonconforming conditions are found.

On the basis of the staff's continuing review of the issues associated with

nonconforming conditions and with interpretations of 10 CFR 50.59

requirements, and of the public comments that were received in response to the

Federal Register notice, the staff determined that it would be beneficial at

this time to issue a revision to this Inspection Manual Chapter 9900 guidance,

even before other aspects of potential guidance are resolved, because of the

impacts on plant operation. Therefore, through this generic letter, the NRC

is notifying addressees of the issuance of the attached NRC Inspection Manual

guidance.

Discussion

As discussed in more detail in the attached guidance, the staff now concludes

that the need to obtain NRC approval for the final resolution of a degraded or

nonconforming condition does not affect the licensee's authority to continue

operation (or restart from a shutdown), provided that necessary equipment is

operable and the degraded equipment is not in conflict with any technical

specification. Thus, Section 4.3.2 has been revised, and other conforming

changes made, to note this change in staff guidance.

On July 21, 1997, the Nuclear Energy Institute (NEI) submitted to the NRC a

guidance document, NEI 96-07 [Final Draft], "Guidelines for 10 CFR 50.59

Safety Evaluations." Part of this guidance relates to applicability of 10 CFR 50.59 to degraded and nonconforming conditions.

The specific guidance is:

In the case of a nonconforming condition, there are three potential scenarios for addressing the condition:

  • If the condition is accepted "as-is" resulting in something different than described in the SAR or is modified to something different than described in the SAR, then the condition should be considered a change and subjected to a 10 CFR 50.59 safety evaluation unless another regulation applies (i.e., 10 CFR 50.55a).
  • If the licensee intends to restore the SSC back to its previous condition (as described in the SAR), then this corrective action should be performed in accordance with 10 CFR Part 50, Appendix B (i.e., in a timely manner commensurate with safety), and a 10 CFR 50.59 safety evaluation is not required.
  • If an interim compensatory action is taken to address the condition and involves a procedure change or temporary modification, a 10 CFR 50.59 review should be conducted and may result in a safety evaluation. The intent is to determine whether the compensatory action itself (not the degraded condition) impacts other aspects of the facility described in the SAR.

The staff finds this industry guidance acceptable with respect to the need for

a 10 CFR 50.59 safety evaluation for degraded and nonconforming conditions.

Therefore, the revised Part 9900 Inspection Manual guidance references this

industry guidance.

As noted in the Part 9900 guidance, the NRC will take enforcement action if it

determines that licensee corrective action (which may include submittal of a

license amendment request) is not prompt, or that operability determinations

are not sound. Enforcement action may also be taken for the circumstances

that led to the existence of the degraded or nonconforming condition.

This generic letter was not published for public comment because the issues

covered by the revision were previously published for public comment in

May 1997, and the staff's guidance is responsive to the comments received.

This generic letter requires no specific action or response. If you have any

questions about this matter, please contact the technical contact listed

below.

signed by

Jack W. Roe, Acting Director

Division of Reactor Program Management

Office of Nuclear Reactor Regulation

Technical contact: Eileen M. McKenna, NRR

301-415-2189

Email: emm@nrc.gov

Attachments:

1. Inspection Manual Part 9900 Guidance, "Resolution of Degraded and Nonconforming Conditions"
2. List of Recently Issued NRC Generic Letters.

Attachment 1

GL 91-18, Revision 1

October 8, 1997

Page 1 of 14

NRC INSPECTION MANUAL

OTSB PART 9900: TECHNICAL GUIDANCE STS30DEG.TG

RESOLUTION OF DEGRADED AND NONCONFORMING CONDITIONS

RESOLUTION OF

DEGRADED AND NONCONFORMING CONDITIONS

1.0 PURPOSE AND SCOPE:

To provide guidance to NRC inspectors on resolution of degraded and

nonconforming conditions affecting the following systems, structures, or

components (SSCs):

(i) Safety-related SSCs, which are those relied upon to remain functional

during and following design basis events (A) to ensure the integrity of

the reactor coolant pressure boundary, (B) to ensure the capability to

shut down the reactor and maintain it in a safe shutdown condition, or

(C) to ensure the capability to prevent or mitigate the consequences of

accidents that could result in potential offsite consequences comparable

to the 10 CFR Part 100 guidelines. Design basis events are defined the

same as in 10 CFR 50.49(b)(1).

(ii) All SSCs whose failure could prevent satisfactory accomplishment of any

of the required functions identified in (i) A, B, and C.

(iii) All SSCs relied on in the safety analyses or plant evaluations that are

a part of the plant's current licensing basis. Such analyses and

evaluations include those submitted to support license amendment

requests, exemption requests, or relief requests, and those submitted to

demonstrate compliance with the Commission's regulations such as fire

protection (10 CFR 50.48), environmental qualification (10 CFR 50.49),

pressurized thermal shock (10 CFR 50.61), anticipated transients without

scram (10 CFR 50.62), and station blackout (10 CFR 50.63).

(iv) Any SSCs subject to 10 CFR Part 50, Appendix B.

(v) Any SSCs subject to 10 CFR Part 50, Appendix A, Criterion 1.

(vi) Any SSCs explicitly subject to facility Technical Specifications (TS).

(vii) Any SSCs subject to facility TS through the definition of operability

(i.e., support SSCs outside TS).

(viii) Any SSCs described in the final safety analysis report (FSAR).

This guidance is directed toward NRC inspectors who are reviewing actions of

licensees that hold an operating license. Although this guidance generally

reflects existing staff practices, application to specific plants may constitute a backfit. Consequently,

significant differences in licensee practices should be discussed with NRC

management to ensure that the guidance is applied in a reasonable and

consistent manner for all licensees.

2.0 DEFINITIONS

2.1 Current Licensing Basis

Current licensing basis (CLB) is the set of NRC requirements applicable to a

specific plant, and a licensee's written commitments for assuring compliance

with and operation within applicable NRC requirements and the plant-specific

design basis (including all modifications and additions to such commitments

over the life of the license) that are docketed and in effect. The CLB

includes the NRC regulations contained in 10 CFR Parts 2, 19, 20, 21, 30, 40,

50, 51, 55, 72, 73, 100 and appendices thereto; orders; license conditions;

exemptions, and TS. It also includes the plant-specific design basis

information defined in 10 CFR 50.2 as documented in the most recent FSAR as

required by 10 CFR 50.71 and the licensee's commitments remaining in effect

that were made in docketed licensing correspondence such as licensee responses

to NRC bulletins, generic letters, and enforcement actions, as well as

licensee commitments documented in NRC safety evaluations or licensee event

reports.

2.2 Design Basis

Design basis is that body of plant-specific design bases information defined

by 10 CFR 50.2.

2.3 Degraded Condition

A condition of an SSC in which there has been any loss of quality or

functional capability.

2.4 Nonconforming Condition

A condition of an SSC in which there is failure to meet requirements or

licensee commitments. Some examples of nonconforming conditions include the

following:

1. There is failure to conform to one or more applicable codes or standards specified in the FSAR.
2. As-built equipment, or as-modified equipment, does not meet FSAR descriptions.
3. Operating experience or engineering reviews demonstrate a design inadequacy.
4. Documentation required by NRC requirements such as 10 CFR 50.49 is not available or deficient.

2.5 Full Qualification

Full qualification constitutes conforming to all aspects of the current

licensing basis, including codes and standards, design criteria, and

commitments.

3.0 BACKGROUND:

A nuclear power plant's SSCs are designed to meet NRC requirements, satisfy

the current licensing basis, and conform to specified codes and standards.

For degraded or nonconforming conditions of these SSCs, the licensee may be

required to take actions required by the TS. The provisions of Title 10 of

the "Code of Federal Regulations" (10 CFR), Part 50, Appendix B, Criteria XVI,

may apply requiring the licensee to identify promptly and correct conditions

adverse to safety or quality. Reporting may be required in accordance with

Sections 50.72, 50.73, and 50.9(b) of 10 CFR Part 50, 10 CFR Part 21, and the

TS. Collectively, these requirements may be viewed as a process for licensees

to develop a basis to continue operation or to place the plant in a safe

condition, and to take prompt corrective action. Changes to the facility in

accordance with 10 CFR 50.59 may be made as part of the corrective action

required by Appendix B. The process displayed by means of the attached chart

titled, "Resolution of Degraded and Nonconforming Conditions," recognizes

these and other provisions that a licensee may follow to restore or establish

acceptable conditions. These provisions are success paths that enable

licensees to continue safe operation of their facilities.

4.0 DISCUSSION OF NOTABLE PROVISIONS

4.1 Public Health and Safety

All success paths, whether specifically stated or not, are first directed to

ensuring public health and safety and second to restoring the SSCs to the

current licensing basis of the plant as an acceptable level of safety.

Identification of a degraded or nonconforming condition that may pose an

immediate threat to the public health and safety requires the plant to be

placed in a safe condition.

Technical Specifications (TS) address the safety systems and provide Limiting

Conditions for Operation (LCOs) and Allowed Outage Times (AOTs) required to

ensure public health and safety.

4.2 Operability Determinations

For guidance on operability see the Inspection Manual, Part 9900, "OPERABLE/

OPERABILITY: ENSURING THE FUNCTIONAL CAPABILITY OF A SYSTEM OR COMPONENT,"

and see the Inspection Manual, Part 9900, "STANDARD TECHNICAL SPECIFICATIONS

STS SECTION 1, OPERABILITY."

4.3 The Current Licensing Basis and 10 CFR 50, Appendix B

The design and operation of a nuclear plant is to be consistent with the

current licensing basis. Whenever degraded or nonconforming conditions of

SSCs subject to Appendix B are identified, Appendix B requires prompt

corrective action to correct or resolve the condition. The licensee must

establish a time frame for completion of corrective action. The timeliness of

this corrective action should be commensurate with the safety significance of

the issue. The time frame governing corrective action begins with the

discovery of the condition, not with the time when it is reported to the NRC.

In determining whether the licensee is making reasonable efforts to complete

corrective action promptly, NRC will consider whether corrective action was

taken at the first opportunity, as determined by safety significance (effects

on operability, significance of degradation) and by what is necessary to

implement the corrective action. Factors that might be included are the

amount of time required for design, review, approval, or procurement of the

repair/modification; availability of specialized equipment to perform the

repair; or the need to be in a hot or cold shutdown to implement the actions.

The NRC expects time frames longer than the next refueling outage to be

explicitly justified by the licensee as part of the deficiency tracking

documentation. If the licensee does not resolve the degraded or nonconforming

condition at the first available opportunity or does not appropriately justify

a longer completion schedule, the staff would conclude that corrective action

has not been timely and would consider taking enforcement action.

4.4 Discovery of an Existing But Previously Unanalyzed Condition or Accident

In the course of its activities, the licensee may discover a previously

unanalyzed condition or accident. Upon discovery of an existing but

previously unanalyzed condition that significantly compromises plant safety,

the licensee shall report that condition in accordance with 10 CFR 50.72 and

50.73, and put the plant in a safe condition.

For a previously unanalyzed condition or accident that is considered a

significant safety concern, but is not part of the design basis, the licensee

may subsequently be required to take additional action after consideration of

backfit issues (see Section 50.109(a)(5)).

4.5 Justification for Continued Operation (JCO)

4.5.1 Background

The license authorizes the licensee to operate the plant in accordance with

the regulations, license conditions, and the TS. If an SSC is degraded or

nonconforming but operable, the license establishes an acceptable basis to

continue to operate and the licensee does not need to take any further

actions. The licensee must, however, promptly identify and correct the

condition adverse to safety or quality in accordance with 10 CFR Part 50,

Appendix B, Criterion XVI..

The basis for this authority to continue to operate arises because the TS

contain the specific characteristics and conditions of operation necessary to

obviate the possibility of an abnormal situation or event giving rise to an

immediate threat to public health and safety. Thus, if the TS are satisfied,

and required equipment is operable, and the licensee is correcting the

degraded or nonconforming condition in a timely manner, continued plant

operation does not pose an undue risk to public health and safety.

Under certain defined and limited circumstances, the licensee may find that

strict compliance with the TS would cause an unnecessary plant action not in

the best interest of public health and safety. NRC review and action is

required prior to the licensee taking actions that are contrary to compliance

with the license conditions or TS unless an emergency situation is present

such that 10 CFR 50.54(x) and (y) is applied. A JCO, as defined herein for

general NRC purposes, is the licensee's technical basis for requesting NRC

responses to such action.

4.5.2 JCO Definition

A Justification for Continued Operation (JCO) is the licensee's technical

basis for requesting authorization to operate in a manner that is prohibited

(e.g., outside TS or license) absent such authorization. The preparation of

JCOs does not constitute authorization to continue operation.

4.5.3 Items for Consideration in a JCO

Some items which are appropriate for consideration in a licensee's development

of a JCO include:

  • Availability of redundant or backup equipment
  • Compensatory measures including limited administrative controls
  • Safety function and events protected against
  • Conservatism and margins, and
  • Probability of needing the safety function.
  • Probabilistic Risk Assessment (PRA) or Individual Plant Evaluation (IPE) results that determine how operating the facility in the manner proposed in the JCO will impact the core damage frequency..

4.5.4 Discussion of Industry-Type JCOs

Currently, some licensees refer to two other documents or processes as JCOs

that are not equivalent to and do not perform the same function as the

NRC-recognized JCO (as defined in 4.5.2). This is an acceptable industry

practice and to the extent the industry JCO fulfills other NRC requirements,

the JCOs will be selectively reviewed and audited accordingly.

In the first industry-type JCO, the licensee may consider the entire process

depicted in the attached chart as a single JCO that includes such things as

the basis for operability, PRA, corrective action elements, and alternative

operations.

In the second industry-type JCO, the licensee may consider the documentation

that is developed to support facility operation after the operability decision

has been made as a JCO. This documentation can cover any or all of the items

listed under "Interim Operation" on the attached chart.

Although the "JCO" is used differently by some licensees, the NRC concern is

that the operability decision is correct, documentation of licensee's actions

are appropriate, and submittals to the NRC are complete. The licensee's

documentation of the JCO is normally proceduralized through the existing plant

record system, which is auditable.

4.6 Reasonable Assurance of Safety

For SSCs that are not expressly subject to TS and that are determined to be

inoperable, the licensee should assess the reasonable assurance of safety. If

the assessment is successful, then the facility may continue to operate while

prompt corrective action is taken. Items to be considered for such an

assessment include the following:

  • Availability of redundant or backup equipment
  • Compensatory measures including limited administrative controls
  • Safety function and events protected against
  • Conservatism and margins, and
  • Probability of needing the safety function.
  • PRA or Individual Plant Evaluation (IPE) results that determine how operating the facility in the manner proposed in the JCO will impact the core damage frequency.

4.7 Evaluation of Compensatory Measures

In its evaluation of the impact of a degraded or nonconforming condition on

plant operation and on operability of SSCs, a licensee may decide to implement

a compensatory measure as an interim step to restore operability or to

otherwise enhance the capability of SSCs until the final corrective action is

complete. Reliance on a compensatory measure for operability should be an

important consideration in establishing the "reasonable time frame" to

complete the corrective action process. NRC would normally expect that

conditions that require interim compensatory measures to demonstrate

operability would be resolved more promptly than conditions that are not

dependent on compensatory measures to show operability, because such reliance suggests a greater degree of degradation. Similarly, if an

operability determination is based upon operator action, NRC would expect the

nonconforming condition to be resolved expeditiously.

On July 21, 1997, the Nuclear Energy Institute (NEI) submitted to the NRC a

guidance document, NEI 96-07 [Final Draft], "Guidelines for 10 CFR 50.59

Safety Evaluations." Part of this guidance relates to applicability of 10 CFR 50.59 to degraded and nonconforming conditions. With respect to the use of

compensatory measures, the guidance states:

. If an interim compensatory action is taken to address the condition

and involves a procedure change or temporary modification, a 10 CFR

50.59 review should be conducted and may result in a safety

evaluation. The intent is to determine whether the compensatory

action itself (not the degraded condition) impacts other aspects of

the facility described in the SAR.

The staff concludes that this is an acceptable approach for dealing with

compensatory actions within the context of a corrective action process.

In considering whether a compensatory measure may affect other aspects of the

facility, a licensee should pay particular attention to ancillary aspects of

the compensatory measure that may result from actions taken to directly

compensate for the degraded condition. As an example, suppose a licensee

plans to close a valve to isolate a leak. Although that action would

temporarily resolve the leak, it has the potential to affect flow distribution

to other components or systems, may complicate required operator responses, or

could have other effects that should be evaluated before the compensatory

measures are implemented. In accordance with 10 CFR 50.59, should the

evaluation determine that implementation of the compensatory action itself

would involve a TS change or an unreviewed safety question

(USQ), NRC approval, in accordance with 10 CFR 50.90 and 50.92, is required

prior to implementation of the compensatory action.

4.8 Final Corrective Action

The responsibility for corrective action rests squarely on the licensee. A

licensee's range of corrective action could include (1) full restoration to

the SAR-described condition, (2) NRC approval for a change to its licensing

basis to accept the as-found condition as is, or (3) some modification of the

facility other than restoration to the original FSAR condition. If

corrective action is taken so that the degraded or nonconforming condition is

restored to its original configuration, no 10 CFR 50.59 evaluation is

required. The 10 CFR 50.59 process is entered when the final resolution to

the degraded or nonconforming condition is to be different than the

established FSAR requirement. At this point, the licensee is planning (in a

prospective sense) to make a change to the facility or procedures as described

in the SAR. The proposed change is now subject to the evaluation process

established by 10 CFR 50.59. A change can be safe, but can still require NRC

approval. The proposed final resolution can be under staff review and not affect the continued operation of the plant,

because interim operation is being governed by the processes of the

operability determination and corrective action of Appendix B.

In two situations, the identification of a final resolution or final

corrective action would trigger a 10 CFR 50.59 evaluation, unless another

regulation applies (i.e., 10 CFR 50.55a): (1) when a licensee decides to

change its facility or procedures to something other than full restoration to

the FSAR-described condition, as the final corrective action, or (2) when a

licensee decides to change its licensing basis as described in the SAR to

accept the degraded or nonconforming condition as its revised licensing basis.

This guidance is consistent with the July 21, 1997, revision of NEI 96-07.

Change to Facility or Procedures

The first circumstance is if the licensee plans for its final resolution

of the degraded or nonconforming condition to include other change(s) to

the facility or procedures in order to cope with the (uncorrected,

including only partially corrected) nonconforming condition. Rather

than fully correcting the nonconforming condition, the licensee decides

to restore capability or margin by another change. In this case, the

licensee needs to evaluate the change from the SAR-described condition

to the final condition in which the licensee proposes to operate its

facility. If the 10 CFR 50.59 evaluation concludes that a change to the

TS or a USQ is involved, a license amendment must be requested, and the

corrective action process is not complete until the approval is

received, or other resolution occurs.

Change to Current Licensing Basis

The other situation is a final resolution in which the licensee proposes

to change the current licensing basis to accept the as-found

nonconforming condition. In this case, the 10 CFR 50.59 evaluation is

of the change from the SAR-described condition to the existing condition

in which the licensee plans to remain (i.e., the licensee will exit the

corrective action process by revising its licensing basis to document

acceptance of the condition). If the 10 CFR 50.59 evaluation concludes

that a change to the TS or a USQ is involved, a license amendment must

be requested, and the corrective action process is not complete until

the approval is received, or other resolution occurs. In order to

resolve the degraded or nonconforming condition without restoring the

affected equipment to its original design, a licensee may need to obtain

an exemption from 10 CFR Part 50 in accordance with 10 CFR 50.12, or

relief from a design code in accordance with 10 CFR 50.55a. The use of

10 CFR 50.59, 50.12, or 50.55a in fulfillment of Appendix B corrective

action requirements does not relieve the licensee of the responsibility

to determine the root cause, to examine other affected systems, or to

report the original condition, as appropriate..

In both of these situations, the need to obtain NRC approval for a change

(e.g., because it involves a USQ) does not affect the licensee's authority to

operate the plant. The licensee may make mode changes, restart from outages,

etc., provided that necessary equipment is operable and the degraded condition

is not in conflict with the TS or the license. The basis for this position

was previously discussed in Section 4.5.1.

ENFORCEMENT

If the licensee, without good cause, does not correct the nonconformance at

the first available opportunity, the staff concludes that the licensee has

failed to take prompt corrective action and, thus, is in violation of 10 CFR Part 50 Appendix B (Criterion XVI). When the NRC concludes that corrective

action to implement the final resolution of the degraded or nonconforming

condition is not prompt, or that the operability determination is not valid,

enforcement action (Notice of Violation, orders) will be taken. Enforcement

action may include restrictions on continued operation.

Implementation of complete corrective action within a reasonable time frame

does not mitigate the potential for taking enforcement action for the root

causes that initially created the degraded or nonconforming condition or for

violations of other regulatory requirements. The nonconforming condition may

have resulted from (1) earlier changes performed without a 10 CFR 50.59

evaluation or (2) inadequate reviews; or may be a de facto change for which

the facility never met the SAR description. The staff may determine that the

"change" from the FSAR-described condition to the discovered nonconforming

condition involved a USQ (or a TS change), and that enforcement action is

appropriate for the time frame up to time of discovery.

5.0 REFERENCE

See attached charts titled, "Resolution of Degraded and Nonconforming

Conditions."

END.The figures for Attachment 1 are currently not available.