ML21267A427

From kanterella
Jump to navigation Jump to search
Purdue Univ., Reply to Notice of Violation in NRC Special Inspection Report No. 05000182/2021202
ML21267A427
Person / Time
Site: Purdue University
Issue date: 09/21/2021
From: Miller T
Purdue University
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
IR 2021202
Download: ML21267A427 (2)


Text

PURDUE UNIVERSITY0 School of Nuclear Engineering September 21, 2021 U.S. Nuclear Regulatory Commission AT1N: Document Control Desk Director, Office of Nuclear Material Safety and Safeguards Washington, DC 20555-0001

SUBJECT:

Reply to Notice of Violation in NRC Special Inspection Report NO. 05000182/2021202 1.) Reason for the Violation In inspection report NO. 05000182/2021202, it was found that PUR-1, docket number 50-182, had committed a level IV violation by failing to report physical security plan changes to the NRC within 30 days as required by 10 CFR 50.54 (p)(2). This violation occurred during a period when renovations to the PUR-1 facility were taking place. Several entryways and rooms were modified during these renovations which resulted in changes to PUR-1 's physical security plan. These changes were implemented into the security plan however this revised security plan was riot mailed to the NRC by the facility's previous reactor supervisor. It is not known why the final changes to the security plan was not mailed to the NRC. The most likely reason is the individual forgot to mail it.

2.) Corrective Steps Taken and Results Achieved Currently the security plan is being reviewed for any other changes that need to be made before submitting the plan to the NRC. This process was delayed for a short period of time, after the notification of the failure to submit changes within 30 days, as the facility was waiting for the new reactor supervisor and facility director to receive their T &Rs so they would be able to contribute to and review the changes to the security plan before submitting the final plan.

3.) Corrective Steps to be Taken The final, up to date, physical security plan will be mailed to the NRC as required by 10 CFR 50.54 (p)(2) as soon as all facility members have reviewed and approved the updated version.

4.) Date When Full Compliance Will be Reached It is planned to submit the updated physical security plan by October 31 st 2021.

~-£!>!

Please feel free to contact me or any of us with questions or if you need further clarification.

Sincerely, }!J20

~ /1P-L-, ~ ;vii True Miller Reactor Supervisor School of Nuclear Engineering I 516 Northwestern Ave I West Lafayette, IN, 47906 I 765-494-5739Ine@purdue.eduIwww.purdue.edu/NE

N.E. Radiation Laboratory Coordinator School of Nuclear Engineering CC. Mung Chiang, Seungjin Kim, Stylianos Chatzidakis, David Storz Page 2 of2