ML18248A248

From kanterella
Jump to navigation Jump to search
Requalification Program Inspection Notification Letter - 2018
ML18248A248
Person / Time
Site: Millstone Dominion icon.png
Issue date: 09/04/2018
From: Diane Jackson
Operations Branch I
To: Stoddard D
Dominion Energy
Jackson D
References
Download: ML18248A248 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD.

KING OF PRUSSIA, PA 19406-2713 September 4, 2018 Mr. Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Dominion Energy, Inc.

Innsbrook Technical Center 5000 Dominion Blvd.

Glen Allen, VA 23060-6711

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - MILLSTONE POWER STATION, UNIT NO. 2

Dear Mr. Stoddard:

In a telephone conversation on August 23, 2018, Mr. David Silk, Senior Operations Engineer, and Mr. Daniel Brown, Unit 2 Training Supervisor, made arrangements for the U.S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at Millstone Power Station, Unit 2. The inspection is planned for the week of December 3, 2018, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish: 1) an index or summary of condition reports written in the past 2 years in which licensed operator errors were determined to be the root or contributing cause; 2) an index or summary of condition reports written in the past 2 years on simulator performance problems; 3) an index or summary of simulator performance test results in the past 2 years; and 4) the examination schedule, sample plan, written examinations, and operating test scheduled for the week of the inspection to the NRC by the week of October 15, 2018. Mr. Brown has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions

D. Stoddard 2 for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S.

Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. David Silk at (610) 337-5372.

Sincerely,

/RA/

Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 50-336 License No. DPR-65 cc: Distribution via ListServ

ML18248A248 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRS/OB RI/DRS/OB NAME DSilk DEJackson DATE 08/24/2018 09/04/2018