MONTHYEARCNL-17-034, Application to Modify the Technical Specifications for Browns Ferry (TS-512), Sequoyah (TS-17-03), and Watts Bar (TS-17-20) to Resolve the Open Phase Issue Identified in NRC Bulletin 2012-01, Design Vulnerability in Electrical Power Syste2017-11-17017 November 2017 Application to Modify the Technical Specifications for Browns Ferry (TS-512), Sequoyah (TS-17-03), and Watts Bar (TS-17-20) to Resolve the Open Phase Issue Identified in NRC Bulletin 2012-01, Design Vulnerability in Electrical Power System. Project stage: Request ML17347A0252017-12-12012 December 2017 NRR E-mail Capture - TVA Nuclear Plants - Acceptance for Review - Application to Modify the TSs for TVA Plants to Resolve Bl 2012-01 Issues Project stage: Acceptance Review ML18213A3192018-08-17017 August 2018 Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant - Summary of Regulatory Audit to Support Review of License Amendment Request to Incorporate New Technical Specification for Unbalanced Voltage Relays Project stage: Approval CNL-18-130, Revised Application to Modify the Technical Specifications for Unbalanced Voltage Relays2018-11-19019 November 2018 Revised Application to Modify the Technical Specifications for Unbalanced Voltage Relays Project stage: Request CNL-19-023, Plants - Supplement to Application to Modify the Technical Specifications for the Browns Ferry Nuclear Plant (TS-512), Sequoyah Nuclear Plant (TS-17-03)and Watts Bar Nuclear Plant (TS-17-20) to ...2019-01-25025 January 2019 Plants - Supplement to Application to Modify the Technical Specifications for the Browns Ferry Nuclear Plant (TS-512), Sequoyah Nuclear Plant (TS-17-03)and Watts Bar Nuclear Plant (TS-17-20) to ... Project stage: Request ML18277A1102019-08-27027 August 2019 Units, 1 & 2 Issuance of Amendment Nos. 309, 332, 292, 345, 339, 128, and 31 Regarding Unbalanced Voltage Protection Project stage: Approval CNL-19-097, Non-Voluntary License Amendment Request to Correct Unbalanced Voltage Relay Instrumentation Values (TS-19-22)2019-10-23023 October 2019 Non-Voluntary License Amendment Request to Correct Unbalanced Voltage Relay Instrumentation Values (TS-19-22) Project stage: Request 2018-08-17
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A4762024-02-0101 February 2024 Final Report of a Part 21 Evaluation Associated with Starter Contactors for the BFN Unit 1 High Pressure Coolant Injection Suppression Pool Inboard Suction Valve ML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML24023A2802024-01-23023 January 2024 Final Report of a Deviation or Failure to Comply Associated with a Relay in the Reactor Core Isolation Cooling Condensate Pump ML24008A2462024-01-18018 January 2024 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24018A0142024-01-17017 January 2024 Engine Systems, Inc., Report No. 10CFR21-0137, Rev. 1, 56913-EN 56913 ML24016A3042024-01-16016 January 2024 Final Report of a Part 21 Evaluation Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 IR 05000327/20234422024-01-11011 January 2024 95001 Supplemental Inspection Report 05000327/2023442 and 05000328/2023442 and Follow-Up Assessment Letter ML24011A3162024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), August 2023 ML24011A3172024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), September 2023 ML24011A3182024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), October 2023 ML24011A3192024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), November 2023 ML24011A3202024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), December 2023 ML24010A2132024-01-10010 January 2024 CFR 21.21 Final Report Regarding Siemens Medium Voltage Circuit Breakers CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) ML24018A0952024-01-0404 January 2024 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0137, Rev. 0 ML24004A0332024-01-0303 January 2024 Interim Report of a Deviation or Failure to Comply Crompton Instruments Type 077 Ammeter ML24004A0402024-01-0303 January 2024 Response to NRCs November 8, 2023, Request for Additional Information - Related to Independent Spent Fuel Storage Installation ML23346A1382024-01-0303 January 2024 Regulatory Audit Summary Related to Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML24022A1732024-01-0303 January 2024 Receipt and Availability of the Subsequent License Renewal Application ML23319A1992024-01-0303 January 2024 Issuance of Amendment Nos. 333, 356, and 316 Regarding the Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves ML23355A2062023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20234412023-12-21021 December 2023 Plantfinal Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) IR 05000390/20234042023-12-14014 December 2023 Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 ML23348A3942023-12-14014 December 2023 Interim Part 21 Report of a Potential Deviation or Failure to Comply Associated with Starter Contactors for the High Pressure Coolant Injection Suppression Pool Inboard Suction Valve CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) ML23346A1222023-12-12012 December 2023 Annual Non-Radiological Environmental Operating Report - 2023 IR 05000259/20230102023-12-11011 December 2023 Commercial Grade Dedication Inspection Report 05000259/2023010 and 05000260/2023010 and 05000296/2023010 ML23293A0572023-12-0606 December 2023 Issuance of Amendment Nos. 163 and 70 Regarding Adoption of TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23335A0722023-12-0101 December 2023 Interim Report of a Deviation or Failure to Comply Associated with a Relay in the Unit 2 Reactor Core Isolation Cooling Condensate Pump ML23334A2492023-11-30030 November 2023 Site Emergency Plan Implementing Procedure Revision IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation CNL-23-070, Submittal of Fifth 10-Year Interval Inservice Testing Program Plan2023-11-29029 November 2023 Submittal of Fifth 10-Year Interval Inservice Testing Program Plan IR 05000327/20234202023-11-28028 November 2023 Security Baseline Inspection Report 05000327/2023420 and 05000328/2023420 CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23331A2532023-11-27027 November 2023 Summary Report for 10 CFR 50.9 Evaluations, Technical Specifications Bases Changes, Technical Requirement Manual Changes, and NRC Commitment Revisions ML23325A1102023-11-21021 November 2023 Anchor Darling Double Disc Gate Valve Commitment Revision ML23320A2542023-11-16016 November 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump IR 05000259/20230032023-11-13013 November 2023 Integrated Inspection Report 05000259/2023003, 05000260/2023003 and 05000296/2023003 IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation 2024-02-01
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 17, 2018 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 11 01 Market Street, LP 4A Chattanooga, TN 37402-2801
SUBJECT:
BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3; SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2; AND WATTS BAR NUCLEAR PLANT, UNITS 1 AND 2 -
SUMMARY
OF REGULATORY AUDIT TO SUPPORT REVIEW OF THE LICENSE AMENDMENT REQUEST TO INCORPORATE NEW TECHNICAL SPECIFICATION FOR UNBALANCED VOLTAGE RELAYS (EPID L-2017-LLA-0391)
Dear Mr. Shea:
By application dated November 17, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17324A349), Tennessee Valley Authority (TVA, the licensee), submitted a request for an amendment to Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 for the Browns Ferry Nuclear Plant, Units 1, 2, and 3; Renewed Facility Operating License Nos. DPR-77 and DPR-79 for the Sequoyah Nuclear Plant, Units 1 and 2; and Facility Operating License Nos. NPF-90 and NPF-96 for the Watts Bar Nuclear Plant, Units 1 and 2. This license amendment request (LAR), titled "Application to Modify the Technical Specifications for the Browns Ferry Nuclear Plant (TS-512), Sequoyah Nuclear Plant (TS-17-03) and Watts Bar Nuclear Plant (TS-17-20) to Resolve the Open Phase Issue Identified in NRC Bulletin 2012-01, 'Design Vulnerability in Electrical Power System',"
proposed addition of a new level of protection, "Unbalanced Voltage," to the Technical Specifications (TSs) for the loss of power instrumentation.
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the information provided by the licensee in the LAR and sent draft requests for additional information (RAls) to TVA on March 27, 2018. On March 29, 2018, NRC staff had a conference call with TVA staff to clarify the requested information. During the conference call, the licensee stated that the discussion in the LAR related to the issues identified in Bulletin 2012-01 was for informational purposes only and not intended to document the completion of actions for vulnerabilities discussed in Bulletin 2012-01.
Due to the complexity of the proposed new TSs, supporting calculations, proposed actions, design modifications, and computer-based modeling, the NRC staff determined the need for a regulatory audit to be conducted in accordance with the Office of Nuclear Reactor Regulation Office (NRR) Instruction LIC-111, "Regulatory Audits."
By letter dated April 20, 2018 (ADAMS Accession No. ML18103A018), the NRC staff issued its plan to conduct an audit in support of its review of the subject LAR. Subsequently, the NRC staff forwarded its revised draft RAls to TVA on April 23, 2018, for discussion during the audit.
J.Shea On May 1, 2018, and May 2, 2018, staff from NRR conducted the audit at the TVA corporate office in Chattanooga, Tennessee. The purpose of this regulatory audit was for the staff to obtain a better understanding of TVA's unique approach for resolving issues associated with Bulletin 2012-01 for TVA plants and bases for the proposed new TSs and the details on the clarifications required to evaluate the adequacy of proposed changes, and for TVA to provide better detailed responses to the RAls. During the audit, TVA staff clarified that while reviewing the consequences of an open phase condition (OPC), a vulnerability to unbalanced voltage (UV) conditions adverseiy impacting safety-related busses was identified at TVA plants. The UV conditions could exist due to several initiating events, including an OPC from the offsite or onsite power systems. The existing protective relay schemes comprising of loss of voltage and degraded voltage relays were not capable of detecting UV conditions. Therefore, TVA submitted this LAR to propose installation of unique UV relays. TVA staff also clarified that a separate document will be submitted to confirm actions taken to address vulnerabilities associated with OPCs discussed in Bulletin 2012-01.
Based on the discussions with the TVA staff and review of the documents during the audit, the NRC staff revised its draft RAls and issued the official RAls by letter dated May 21, 2018 (ADAMS Accession No. ML18115A379). The licensee's responses to the RAls were submitted to the NRC by letter dated June 18, 2018 (ADAMS Accession No. ML18169A404).
A list of audit participants is enclosed. If you have any questions, please contact me at (301) 415-1447 or Farideh.Saba@nrc.gov.
Sincerely, Farideh E. Saba, Senior Project Manager Plant Licensing 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391
Enclosure:
List of Audit Participants cc: Listserv
LIST OF AUDIT PARTICIPANTS Name Organization Jessie Quichocho U.S. Nuclear Regulatory Commission (NRC)
Gurcharan (Singh) Matharu NRC Robert Schaaf NRC Farideh Saba (partially)* NRC Pete Snyder* NRC Edward Schrull Tennessee Valley Authority (TVA)
Gordon Williams TVA Tammy Womack TVA Preston Cooper TVA Mike Durr (partially) TVA Ashley Taylor (partially) TVA Chase Hardeman (partially) TVA
J. Shea
SUBJECT:
BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3; SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2; AND WATTS BAR NUCLEAR PLANT, UNITS 1 AND 2 -
SUMMARY
OF REGULATORY AUDIT TO SUPPORT REVIEW OF THE LICENSE AMENDMENT REQUEST TO INCORPORATE NEW TECHNICAL SPECIFICATION FOR UNBALANCED VOLTAGE RELAYS (EPID L-2017-LLA-0391) DATED AUGUST 17, 2018 DISTRIBUTION:
PUBLIC RidsACRS_MailCTR Resource RidsNrrDorl Resource RidsNrrDorlLpl2-2 Resource RidsNrrPMBrownsFerry Resource RidsNrrDeEeob Resource RidsNrrDssStsb Resource RidsNrrPMSequoyah Resource RidsNrrLABClayton Resource RidsRgn2MailCenter Resource RidsNrrPMWattsBar Resource GMatharu, NRR PSnyder, NRR ADAMS A ccess1on No.: ML18213A319 *b1y e-ma1*1 OFFICE DORL/LPLI 1-2/PM DORL/LPLI 1-2/LA DE/EE OB/BC*
NAME FSaba BClayton (LRonewicz for) JQuichocho DATE 08/13/2018 08/08/2018 08/06/2018 OFFICE NRR/DORL/LPL2-2/BC(A) NRR/DORL/LPL2-2/PM NAME BVenkataraman FSaba DATE 08/13/2018 08/17/2018 OFFICIAL RECORD COPY