ENS 47884
ENS Event | |
---|---|
13:41 Mar 2, 2012 | |
Title | Potential Degradation of Reactor Containment Electrical Penetration Seals |
Event Description | During a review of environmental qualification records for reactor containment building electrical penetrations, six penetrations were identified that may not provide an adequate seal during worst case (Design Basis Accident (DBA)) conditions as required. These penetrations are through wall from the containment into the auxiliary building. The conditions that could cause degradation of the electrical penetration seals are not applicable to this operating mode. The station is currently in a refueling mode. This event was identified on March 2, 2012. The reportability was confirmed on May 1, 2012 at 1502 CDT.
The current penetration configuration has existed since the plant was built. The area of concern is that the Teflon connections may degrade under conditions of high radiation and high temperature during a DBA event. The licensee is investigating the extent of the condition and repair techniques. The licensee notified the NRC Resident Inspector.
On review of CR 2012-01947 by a new Project Manager, who was brought in as a subject matter expert on HELB/EEQ, and issue was identified with the 530 primary containment electrical penetration feed-throughs used for non-CQE devices. The CR [Condition Report] correctly notes that under the original accident testing, the Teflon seals failed, and water was noted leaking from these penetrations. On further review, the following was noted: Due to the design of the penetration feed-throughs, when the inboard Teflon seal fails (as it is expected to, due to high level of radioactivity in the primary containment, following a Loss of Coolant Accident (LOCA)), the atmosphere of the primary containment will be introduced to the penetration assembly, first through the failed seal or seals, and then through the weep hole between the inboard and outboard seals of the feed-through. This will put the same high level of radioactivity in direct contact with the outboard seals, resulting in the failure of its Teflon Seal. This would result in approximately 530 breaches of the Primary Containment during post LOCA conditions. The existing vendor analysis does not assume any contribution to the outboard seal exposure from the mixing of containment atmosphere with the penetration air after the failure of the inboard seal. This is probable, as each feed-through has a weep hole. Once the inboard seal fails, the penetration will be filled with containment atmosphere to equalize the pressure, which will bring the associated noble gas and Iodine fraction in proportion, into the penetration. The licensee notified the NRC Resident Inspector. Notified R4DO (Clark)
During the extent of condition review for CR 2012-01655 and 2012-01947 additional penetration feed-through assemblies were identified that are subject to the same failure mechanism. These penetrations are associated with the containment sump recirculation isolation valves, and also associated with the personnel air lock. The licensee notified the NRC Resident Inspector. Notified R4DO (Walker). |
Where | |
---|---|
Fort Calhoun Nebraska (NRC Region 4) | |
Reporting | |
10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition | |
LER: | 05000285/LER-2012-002 |
Time - Person (Reporting Time:+1445.08 h60.212 days <br />8.602 weeks <br />1.979 months <br />) | |
Opened: | Erick Matzke 17:46 May 1, 2012 |
NRC Officer: | Mark Abramovitz |
Last Updated: | Jul 17, 2012 |
47884 - NRC Website | |
Unit 1 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Cold Shutdown (0 %) |
After | Cold Shutdown (0 %) |
WEEKMONTHYEARENS 522012016-08-25T20:23:00025 August 2016 20:23:00
[Table view]10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition Involving Potential Tornado Missile Damage ENS 519172016-05-10T16:38:00010 May 2016 16:38:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Containment Cooling Water System Inoperable Due to Unanalyzed Condition ENS 514872015-10-21T18:50:00021 October 2015 18:50:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition Due to Pressurizer Heater Bank Potential Circuit Failure Vulnerability ENS 508002015-02-09T23:30:0009 February 2015 23:30:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Safety Injection Tank Level Results in an Unanalyzed Condition ENS 494782013-10-28T17:30:00028 October 2013 17:30:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Postulated Event Could Result in a Hot Short That Could Adversely Impact Safe Shutdown Equipment ENS 493782013-09-23T18:40:00023 September 2013 18:40:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition - Epoxy Floor Coatings Do Not Meet Design Basis Requirements in Two Rooms ENS 493242013-09-05T13:31:0005 September 2013 13:31:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Potential Low Pressure Safety Injection Pump Run Out Condition ENS 491192013-06-14T16:00:00014 June 2013 16:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Invalid Conditions Discovered Due to Exclusion of Small Bore Piping from Analysis ENS 491122013-06-13T13:05:00013 June 2013 13:05:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition ENS 490502013-05-17T05:00:00017 May 2013 05:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Embedment Depth for Seismic Anchors Inadequate ENS 488062013-03-04T20:00:0004 March 2013 20:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition Due to Mechanical Seal Material Design ENS 487872013-02-27T02:12:00027 February 2013 02:12:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Relay Backing Plate Fasteners Discovered to Be at Less than Specified Torque ENS 487812013-02-24T23:00:00024 February 2013 23:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Inverters Potentially Inoperable During Emergency Diesel Generator Operation ENS 487302013-02-07T20:30:0007 February 2013 20:30:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition Due to Possible Run-Out of High Pressure Safety Injection Pump ENS 480942012-07-11T21:03:00011 July 2012 21:03:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Analysis of Internal Containment Support Beam Exceeds Load Combination Limit ENS 479922012-06-04T20:14:0004 June 2012 20:14:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Reactor Coolant System in a Degraded Condition Due to an Instrument Rack Seismic Design Issue ENS 479002012-05-04T15:00:0004 May 2012 15:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Containment Equipment Not Analyzed for Environmental Conditions of Record ENS 478922012-05-02T16:55:0002 May 2012 16:55:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Potential Unanalyzed Condition with Containment Pressure Instruments ENS 478622012-04-25T14:00:00025 April 2012 14:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Conditions Resulting from a Non-Conservative Error in Calculations ENS 478842012-03-02T13:41:0002 March 2012 13:41:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Potential Degradation of Reactor Containment Electrical Penetration Seals ENS 476582012-02-10T06:00:00010 February 2012 06:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition - Guidance Not Adequate to Mitigate a Design Basis Flood ENS 478482011-10-06T18:44:0006 October 2011 18:44:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Waste Disposal System Class One Seismic Support Inoperable ENS 470882011-07-22T13:30:00022 July 2011 13:30:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Fire Supression Pumps Inoperable ENS 469652011-06-16T17:30:00016 June 2011 17:30:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Additional Penetration Identified for Mitigation During Walkdown ENS 462972010-09-30T21:16:00030 September 2010 21:16:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition Due to Potential Flooding Via Condensate Drain Lines ENS 458282010-04-08T21:22:0008 April 2010 21:22:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition, 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Technical Specification Required Shutdown Due to Inoperable Steam Generator Inlet Isolation Valve ENS 454672009-10-26T15:50:00026 October 2009 15:50:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Pressurizer and Feedwater Storage Tank Level Indications Do Not Meet Appendix R Requirements ENS 429432006-10-28T22:09:00028 October 2006 22:09:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition ENS 429022006-10-12T22:30:00012 October 2006 22:30:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Steam Generator Instrumentation Nonconformance ENS 428962006-10-10T20:00:00010 October 2006 20:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Containment Spray Valve Mispositioned 2016-08-25T20:23:00 | |