05000530/LER-2015-002, Condition Prohibited by Technical Specification 3.0.4 Due to an Inoperable Atmospheric Dump Valve (ADV)

From kanterella
Jump to navigation Jump to search
LER-2015-002, Condition Prohibited by Technical Specification 3.0.4 Due to an Inoperable Atmospheric Dump Valve (ADV)
Palo Verde Nuclear Generating Station (Pvngs) Unit 3
Event date: 05-01-2015
Report date: 06-26-2015
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
5302015002R00 - NRC Website

All times are Mountain Standard Time and approximate unless otherwise indicated.

1. REPORTING REQUIREMENT(S):

This Licensee Event Report (LER) is being submitted pursuant to 10 CFR 50.73(a)(2)(i)(b) as a condition prohibited by Technical Specification (TS) Limiting Condition for Operation (LCO) 3.0.4, due to entry into a Mode or other specified condition in the applicability for LCO 3.7.4, Atmospheric Dump Valves, while the LCO was not met.

The condition was discovered in Palo Verde Nuclear Generating Station (PVNGS) Unit 3 during planned testing of atmospheric dump valve SGB-HV-178 (ADV-178).

Mode 3 on May 1, 2015. On May 2, 2015, when the plant conditions needed to perform ADV stroking with steam were achieved, testing of ADV-178 was performed which determined the ADV would not stroke more than approximately 13 percent open and the ADV was declared inoperable.

2. DESCRIPTION OF STRUCTURE(S), SYSTEM(S) AND COMPONENT(S):

The PVNGS design includes two steam generators (SGs) (EIIS: AB), each with two main steam lines (EIIS: SB) and an ADV (EIIS: SB) for each of the four main steam lines. Each ADV line consists of one normally closed ADV and an associated, normally open, block valve. The ADV block valves permit testing and maintenance of the ADVs while a unit is at power.

The ADVs (Control Components International, Model B3G9-10-12P8-31NA51) are main steam isolation valves (MSIVs) (EIIS: SB) and are used to remove reactor decay heat via the SGs by venting steam in the event that the main condenser (EIIS: SG) becomes unavailable, including a loss of electrical power. The ADVs have the capacity to achieve and maintain safe shutdown conditions following design basis accidents involving a loss of offsite power and/or closure of the MSIVs. Each ADV is sized to accommodate plant cooldown in the event of a steam line break or SG tube rupture which may render one SG unavailable for heat removal.

The ADV (Figure 1) is an angled flow control valve designed with a rising internal plug that exposes flow passages in a disk stack as the plug is moved up through the valve stroke length. The disk stack consists of a number of circular disks which form a cylinder when stacked. Each disk is machined with labyrinth flow passages. As the valve is opened the plug rises up within the disk stack cylinder and steam flow passes from the valve inlet through the exposed labyrinth flow passages in the disk stack into the bore area and then to the outlet port on the valve body. The position of the plug within the disk stack bore determines flow by exposing more or less disk passages of the disk stack as the valve is positioned. This configuration permits relatively linear changes in steam flow rate relative to valve position.

The ADV is held closed by a combination of spring pressure and steam pressure (in the valve bonnet area) acting on the upper surface of the plug. An internal pilot valve is installed in the upper part of the plug which allows for depressurization of the valve bonnet area during valve opening. To limit steam leakage into the bonnet area of the valve, a set of sealing rings is installed in the upper part of the bore area between the plug and the valve body.

Each ADV is normally remotely operated using a pneumatic valve actuator in remote shutdown panels. The valves may also be positioned by a local manual operator. The pneumatic valve actuator is normally supplied from the plant instrument air system and is provided with a backup supply of pressurized nitrogen that, on a loss of pressure in the normal instrument air supply, automatically supplies nitrogen to operate the ADVs.

TS LCO 3.7.4 requires that four ADV lines shall be operable when the unit is in Modes 1, 2, and 3, or Mode 4 when the SG is being relied upon for heat removal. With one required ADV inoperable, the ADV must be restored to operable status within 7 days or the unit must be placed in Mode 3 within 6 hours and then must be in Mode 4 without reliance on the SG for heat removal within 24 hours.

3. INITIAL PLANT CONDITIONS:

On May 2, 2015, PVNGS Unit 3 was in Mode 3 with plant startup in progress following completion of refueling activities. Reactor coolant system temperature and pressure were being increased in preparation for planned equipment testing at normal operating temperature and pressure. There were no other systems, structures or components out

4. EVENT DESCRIPTION:

At 0258 on May 1, 2015, following completion of refueling activities, PVNGS Unit 3 refueling outage, on April 10, 2015, with Unit 3 in a cold shutdown condition, maintenance personnel started a planned activity to rebuild the valve internals for ADV-178. This maintenance activity was completed, the ADV was reassembled and testing was performed and completed with the unit in a cold shutdown condition with no issues or problems identified. However, additional testing of the four ADVs which required normal hot standby steam pressure conditions was performed when the plant entered Mode 3.

On May 2, 2015, when plant conditions needed to perform ADV stroking with steam were achieved, the additional testing of ADV-178 was initiated. The testing consisted of a 30 percent partial stroke test with steam flow (block valve open). At 1739 on May 2, 2015, the testing determined that ADV-178 would not stroke open greater than approximately 13 percent and Operations personnel declared the valve inoperable and entered TS LCO 3.7.4 Condition A. Engineering and maintenance personnel then conducted a series of troubleshooting activities to identify the cause of the problem.

On May 6, 2015, ADV-178 was isolated and disassembled to allow inspection of the valve internals. This inspection identified that internal sealing rings had been improperly installed during the valve maintenance performed in April during the refueling outage.

Therefore, when Unit 3 entered Mode 4 on May 1, 2015, the valve was inoperable. The valve was reassembled in the proper configuration and post maintenance testing, including the 30 percent partial stroke test with steam flow, was successfully completed.

At 0853 on May 7, 2015, ADV-178 was declared operable and Unit 3 exited TS LCO 3.7.4 Condition A.

5. ASSESSMENT OF SAFETY CONSEQUENCES:

This event did not result in a potential transient more severe than those analyzed in the Updated Final Safety Analysis Report (UFSAR) or result in the release of radioactive materials to the environment. There were no actual safety consequences as a result of this event and the event did not adversely affect the health and safety of the public.

The safety function of the ADVs is to provide a safety grade method for cooling the unit to shutdown cooling entry conditions, should the preferred heat sink not be available, as discussed in the PVNGS UFSAR, Section 10.3. During the period while ADV-178 was inoperable with Unit 3 in a condition which required four operable ADVs, the three remaining operable ADVs were capable of performing the safety function. Therefore, the event did not result in potential safety consequences beyond those analyzed in the UFSAR. The safety significance associated with the subject condition was very associated with the subject condition was very small. The Incremental Conditional Core Damage Probability (ICCDP) and Incremental Conditional Large Early Release Probability (ICLERP) associated with the period of unavailability of ADV-178 were estimated to be 1.3E-8 and 1.2E-9, respectively, using the PVNGS at-power probabilistic risk assessment model developed for 10 CFR 50.65(a)(4) risk Regulatory Guide 1.174, An Approach for using Probabilistic Risk Assessment in Risk Informed Decisions on Plant Specific Changes to the Licensing Basis.

The condition would not have prevented the fulfillment of the safety function; and the condition did not result in a safety system functional failure as defined by 10 CFR 50.73(a)(2)(v).

6. CAUSE OF THE EVENT:

The event resulted from improperly installed sealing rings on the valve internals which created excessive friction between internal valve components when the valve was stroked with steam pressure applied.

The causes of the event were determined to be human error by maintenance personnel during re-assembly of valve internals and inadequacies with the procedure used to perform the valve maintenance.

7. CORRECTIVE ACTIONS:

To correct the problem with improperly installed sealing rings, ADV-178 was dis-assembled and a new valve plug and new sealing rings were installed in their proper configuration. Post maintenance testing was successfully completed to verify valve function.

To prevent recurrence, corrective actions will revise work instructions to provide detailed guidance for valve re-assembly and to require verifications of proper re-assembly.

Any additional corrective actions taken as a result of this event will be implemented in accordance with the PVNGS corrective action program. If information is subsequently developed that would significantly affect a reader's understanding or perception of this event, a supplement to this LER will be submitted.

8. PREVIOUS SIMILAR EVENTS:

A similar event was reported in LER 50-529/2012-003-00 which resulted when testing in Mode 3 following refueling activities identified an inoperable steam supply valve for the steam driven auxiliary feedwater pump. The corrective actions taken as a result of the event reported in LER 50-529/2012-003-00, were to revise valve specific work instructions and would not have prevented the event discussed in this LER (50-530/2015-002-00).


gItC

E=2UPSTREAM rFLUID STREAM CHAMBER.

ABOVE PLUG SEALING RMG VALVE BODY VALVE.

DISC PLUG :P41.'N' STACK 312 1.

- TO RELEF CHAMBER Figure 1 STEM PILOT VALVE