ENS 46722
ENS Event | |
---|---|
04:00 Apr 4, 2011 | |
Title | Press Release Concerning Additional Containment Delamination |
Event Description | Progress Energy Florida, Inc. has notified the Florida Public Service Commission (FPSC) that the Crystal River Unit 3 (CR-3) Nuclear Plant will remain out of service while the company conducts a thorough engineering analysis and review of a new delamination. Options to return the plant to service will be analyzed after the report is complete. The company cannot estimate a return to service date for CR-3 at this time.
In mid-March, final retensioning of tendons within the CR-3 containment building was suspended while engineers investigated evidence of an additional delamination (or separation) resulting from the tendon retensioning work. The initial damage occurred in late 2009 in the concrete at the periphery of the containment building while creating an opening in the structure to facilitate the replacement of the steam generators inside. The unit was already shut down for refueling and maintenance at the time the damage was found. The plant has been shut down since September 2009 and there continues to be no threat to public health and safety. Progress Energy continues to coordinate repair and restart plans with Nuclear Regulatory Commission officials. The licensee notified the NRC Resident Inspector. |
Where | |
---|---|
Crystal River Florida (NRC Region 2) | |
Reporting | |
Other Unspec Reqmnt | |
Time - Person (Reporting Time:+13.58 h0.566 days <br />0.0808 weeks <br />0.0186 months <br />) | |
Opened: | C. Mckim 17:35 Apr 4, 2011 |
NRC Officer: | Pete Snyder |
Last Updated: | Apr 4, 2011 |
46722 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 46722\u003C/a\u003E - \u003Ca href=\"/Crystal_River\" title=\"Crystal River\"\u003ECrystal River\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EPress Release Concerning Additional Containment Delamination\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 46722 - Crystal River\n","link":"","lat":28.959783333333334,"lon":-82.69345555555556,"icon":"/w/images/7/75/Duke_Energy_icon.png"}],"imageoverlays":null} | |
Unit 3 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Cold Shutdown (0 %) |
After | Cold Shutdown (0 %) |
WEEKMONTHYEARENS 529572017-09-09T15:09:0009 September 2017 15:09:00
[Table view]Other Unspec Reqmnt Hurricane Warning Issued Affecting Site within 36 Hours ENS 467222011-04-04T04:00:0004 April 2011 04:00:00 Other Unspec Reqmnt Press Release Concerning Additional Containment Delamination ENS 466732011-03-14T18:11:00014 March 2011 18:11:00 Other Unspec Reqmnt Additional Delaminated Containment Concrete Discovered ENS 454162009-10-07T23:30:0007 October 2009 23:30:00 Other Unspec Reqmnt Discovery of a Containment Separation ENS 437062007-10-10T17:12:00010 October 2007 17:12:00 Information Only, Other Unspec Reqmnt, 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Pressurizer Porv Opened Momentarily with Rcs Discharge of Approximately 10 Gallons 2017-09-09T15:09:00 | |