MONTHYEARML24255A3252024-09-12012 September 2024 University of Utah - Withdrawal of Requested Licensing Action Re Exemption from Select Requirements of 10 CFR Part 55 (1) ML24250A1042024-09-0505 September 2024 University of Utah Supplemental Information Responses for Exemption Request ML24220A0212024-08-22022 August 2024 University of Utah - Supplemental Information Needed for Acceptance of the Application for an Exemption Request Re Requalification and License Activities Exemption ML24235A5422024-08-22022 August 2024 University of Utah, Exemption Request Withdraw ML24108A0972024-04-22022 April 2024 University of Utah - Change of Facility Backup Project Manager IR 05000407/20232012024-01-16016 January 2024 University of Utah - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000407/2023201 ML24003A2932024-01-0404 January 2024 University of Utah - Change of Facility Project Manager ML23243B0642023-09-19019 September 2023 Utah Issuance of Amendment No. 10 to Facility License No. R-126 and Technical Specifications for the University of Utah Triga Nuclear Reactor Re Administrative Changes ML23082A1182023-03-27027 March 2023 Examination Report No 50-407/OL-23-01 University of Utah ML23082A1192023-03-27027 March 2023 Examination Results Letter No. 50-407/OL-23-01, University of Utah IR 05000407/20222012022-10-0707 October 2022 University of Utah - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000407/2022201 IR 05000407/20222022022-08-29029 August 2022 University of Utah - Nuclear Regulatory Commission Security Inspection Report No. 05000407/2022202 ML22118A3812022-04-28028 April 2022 Examination Results Letter No. 50-407/OL-22-01, University of Utah ML22118A3802022-04-28028 April 2022 Examination Report Letter No. 50-407/OL-22-01, University of Utah ML22014A2752022-01-24024 January 2022 Examination Confirmation Letter No. 50-407/OL-22-01, University of Utah ML21245A2372021-10-20020 October 2021 University of Utah - Nuclear Regulatory Commission Routine Inspection ML21238A0242021-07-30030 July 2021 Univ of Utah, Submittal of Annual Operating Report 1 July 2020 Through 30 June 2021 ML21176A0842021-07-16016 July 2021 Examination Confirmation Letter No. 50-407/OL-21-01, University of Utah ML21173A3112021-06-24024 June 2021 University of Utah - Acknowledgement of Response to Notice of Violation (NRC Inspection Report No. 05000407/2020201) ML21203A0312021-06-0707 June 2021 University of Utah - Reply to a Notice of Violation ML20304A2162021-05-0707 May 2021 University of Utah - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000407/2020201 and Notice of Violation - Cover Letter and Enclosure ML21103A3422021-04-13013 April 2021 Examination Confirmation Letter No. 50-407/OL-21-01, University of Utah ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20111A1132020-04-0202 April 2020 University of Utah Triga Reactor (UUTR) Technical Specifications (T.S.) 6.7.2.1.5 to Operating License R-126, Docket No. 50-407 This Written Report Identifies a Component Malfunction That Affects T.S. 3.2.1.2 IR 05000407/20192022019-09-18018 September 2019 University of Utah - U.S. Nuclear Regulatory Commission Routine Inspection Report 05000407/2019202 ML19261A6762019-09-18018 September 2019 Examination Confirmation Letter No. 50-407/OL 20-01, University of Utah Triga Reactor ML19228A0822019-07-30030 July 2019 University of Utah, Annual Operating Report for July 2018 to June 2019 IR 05000407/20192012019-04-0101 April 2019 University of Utah - U.S. Nuclear Regulatory Commission Security Inspection Report No. 50-407/2019-201 ML18257A0742018-09-0909 September 2018 Univ. of Utah - Submittal of Annual Operating Report for the Period of 1 July 2017 Through 30 June 2018 ML18213A0222018-08-0101 August 2018 Examination Confrimation Letter No. 50-407/OL-18-02, University of Utah ML18094A7952018-04-13013 April 2018 Examination Report No. 50-407/OL-18-01, University of Utah ML17248A0292017-08-25025 August 2017 Notification of Interim Level 2 Change at the Utah Nuclear Engineering Program ML17199T4332017-07-27027 July 2017 University of Utah - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 50-407/2017-201 ML17209A7382017-07-12012 July 2017 Submittal of Annual Operating Report for the University of Utah Triga Nuclear Reactor for the Period of July 1, 2016 Through June 30, 2017 ML17136A0122017-05-17017 May 2017 Examination Report No. 50-407-OL 17-01, University of Utah ML17067A3912017-04-12012 April 2017 Non-Power Reactor Closeout of Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools University of Utah Triga Nuclear Reactor, Docket No. 50-407 ML17090A4202017-03-15015 March 2017 1 of the University of Utah Physical Security Plan ML17073A0882017-03-0808 March 2017 Update of Contact for University of Utah Vice President for Research ML17025A3662017-03-0101 March 2017 Examination Confirmation Letter 50-407/OL-17-01, University of Utah IR 05000407/20162022016-08-30030 August 2016 University of Utah - NRC Routine Inspection Report No. 50-407/2016-202 ML16223A7602016-07-29029 July 2016 University of Utah, Submittal of Annual Operating Report for 7/1/2015 Through 6/30/2016 ML16176A1772016-06-13013 June 2016 University of Utah, Response to Generic Letter 2016-01: Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools IR 05000407/20162012016-05-13013 May 2016 University of Utah Nuclear Regulatory Commission Security-Related Inspection Report No. 50-407/2016-201 (Non-Public Letter) ML16141A1182016-05-0606 May 2016 Notification of Interim Level 2 Adjustment at the Utah Engineering Program 2016 June - 2019 June ML15222A2502015-07-27027 July 2015 University of Utah - Annual Operating Report for the Period of July 1, 2014 Through June 30, 2015 ML14290A4862015-06-0303 June 2015 Y020140127 - Withdrawal of Order EA-05-007, Order Imposing Additional Security Measures ML14231B3182014-08-27027 August 2014 University of Utah Correction to Page No. 3 of Facility Operating License No. R-126 (TAC No. M79601) ML14216A3462014-07-23023 July 2014 University of Utah, Submittal of Annual Operating Report for the Period of 1 July 2013 Through 30 June 2014 ML14191A6832014-07-16016 July 2014 Examination Notification Letter No. 50-407/OL-14-01, University of Utah ML14139A5582014-05-27027 May 2014 University of Utah - Change of Facility Project Manager 2024-09-05
[Table view] |
Text
THEU UNIVERSITY OF UTAH Utah Nuclear Engineering Program 50 S. Central Campus Drive, Suite 2298 Salt Lake City, Utah 84112 801-581-4188 Fax 801-585-5477 May 6, 2016 U.S. Nuclear Regulatory Commission Document Control Desk Mail Stop 012-G 13 One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738
Subject:
Notification oflnterim Level 2 adjustment at the Utah Nuclear Engineering Program 2016 June -2019 June This letter is to provide notification that myself, Dr. Tatjana Jevremovic, Director of the Nuclear Engineering Program at the University of Utah (Level 2), have accepted a position at the International Atomic Energy Agency (IAEA) beginning June* 1, 2016. Ryan C. Schow will serve as the Interim Level 2 for the University of Utah 100 kW TRIG A Reactor (License No. R-126, Docket No. 50-407).
Mr. Schow satisfies the American National Standard ANSI/ANS and the University of Utah TRIGA Reactor Technical Specifications.
Mr. Schow is* currently the Reactor Supervisor for the University of Utah TRIG A Reactor.
He has performed as the Reactor Supervisor since June 2013. Mr. Schow will continue to perform as the Reactor Supervisor along with the addition of the Utah Nuclear Engineering Facility Manager responsibilities at the Level 2. Dr. Jevremovic will be available and readily in contact for consulting and review through a secure network connection using Devon Way software communications during her service at the IAEA. Contact information for Ryan C. Schow is given below: Ryan C. Schow Joseph Merrill Engineering Building 50 S CentralcCampus Drive, Room 1206 801-581-4188 ryan.c.schow@utah.edu I declare under penalty of perjury that the foregoing is true and correct.
cf; Tatjana Je emovic, Ph.D. Chair Pro essor and Director of Utah Nuclear Engineering Program and Nuc ear Facilities cc: Xiaosong Yin, NRC ngmeering THEU UNIVERSITY OF UTAH Utah Nuclear Engineering Program 50 S. Central Campus Drive, Suite 2298 Salt Lake City, Utah 84112 801-581-4188 Fax 801-585-5477 May 6, 2016 U.S. Nuclear Regulatory Commission Document Control Desk Mail Stop 012-G 13 One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738
Subject:
Notification oflnterim Level 2 adjustment at the Utah Nuclear Engineering Program 2016 June -2019 June This letter is to provide notification that myself, Dr. Tatjana Jevremovic, Director of the Nuclear Engineering Program at the University of Utah (Level 2), have accepted a position at the International Atomic Energy Agency (IAEA) beginning June* 1, 2016. Ryan C. Schow will serve as the Interim Level 2 for the University of Utah 100 kW TRIG A Reactor (License No. R-126, Docket No. 50-407).
Mr. Schow satisfies the American National Standard ANSI/ANS and the University of Utah TRIGA Reactor Technical Specifications.
Mr. Schow is* currently the Reactor Supervisor for the University of Utah TRIG A Reactor.
He has performed as the Reactor Supervisor since June 2013. Mr. Schow will continue to perform as the Reactor Supervisor along with the addition of the Utah Nuclear Engineering Facility Manager responsibilities at the Level 2. Dr. Jevremovic will be available and readily in contact for consulting and review through a secure network connection using Devon Way software communications during her service at the IAEA. Contact information for Ryan C. Schow is given below: Ryan C. Schow Joseph Merrill Engineering Building 50 S CentralcCampus Drive, Room 1206 801-581-4188 ryan.c.schow@utah.edu I declare under penalty of perjury that the foregoing is true and correct.
cf; Tatjana Je emovic, Ph.D. Chair Pro essor and Director of Utah Nuclear Engineering Program and Nuc ear Facilities cc: Xiaosong Yin, NRC ngmeering