Finding | |
---|---|
Title | Licensee-Identified Violation |
Description | TS 3.7.1 requires that all main steam safety valves (MSSVs) shall be operable, which, in part, is specifically met if as-found lift setpoints are within applicable acceptance criteria during in-service testing. Contrary to this requirement, on March 10, 2009, during performance of MSSV testing, Entergy personnel identified that MS-45-1 and 48-3 exceeded as-found lift setpoints. Entergy subsequently performed satisfactory adjustments and as-left testing to ensure operability was restored. Entergy documented this issue in the corrective action program for resolution under condition report CR-IP3-2009-00716. In addition, Entergy personnel analyzed the past operability and associated impact on the safety analysis with two MSSVs potentially lifting at greater than allowable setpoints. Although two MSSVs were determined to be inoperable for an unknown duration, and potentially longer than the allowed outage time listed in Unit 3 technical specifications, the inspectors determined that this finding is of very low safety significance because it did not increase the probability or consequences of any anticipated operational occurrence or accidents covered by the safety analysis. |
Site: | Indian Point |
---|---|
Report | IR 05000286/2010002 Section 4OA7 |
Date counted | Mar 31, 2010 (2010Q1) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Licensee-identified |
Inspection Procedure: | |
Inspectors (proximate) | E Keighley J Noggle M Gray M Halter P Cataldo S Barr |
INPO aspect | |
' | |
Finding - Indian Point - IR 05000286/2010002 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Indian Point) @ 2010Q1
Self-Identified List (Indian Point)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||