CNL-14-134, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Order Number EA-12-049) for Watts Bar Nucle
| ML14248A517 | |
| Person / Time | |
|---|---|
| Site: | Watts Bar |
| Issue date: | 08/28/2014 |
| From: | James Shea Tennessee Valley Authority |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| CNL-14-134, EA-12-049, TAC MF0950, TAC MF1177 L44 140828 006 | |
| Download: ML14248A517 (10) | |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-134 August 28, 2014 10 CFR 2.202 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391
Subject:
Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Watts Bar Nuclear Plant (TAC Nos. MF0950 and MF1177)
References:
- 1. Letter from TVA to NRC, Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Watts Bar Nuclear Plant, dated February 28, 2013 (ML13067A030)
- 2. Letter from TVA to NRC, First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Watts Bar Nuclear Plant, dated August 28, 2013 (ML13247A288)
- 3. Letter from NRC to TVA, Watts Bar Nuclear Plant, Units 1 and 2 - Interim Staff Evaluation Relating to Overall Intergraded Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC Nos. MF0950 and MF1177), dated December 20, 2013 (ML13343A025)
L44 140828 006
U.S. Nuclear Regulatory Commission Page 2 August 28, 2014
- 4. Letter from TVA to NRC, Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Watts Bar Nuclear Plant (TAC Nos. MF0950 and MF1177), dated February 7, 2014 (ML14062A050)
- 5. Letter from TVA to NRC, Response to NRC Staff Audit Question Clarification for Watts Bar Nuclear Plant, Units 1 and 2 Mitigation Strategies Integrated Plan, Phase 2 Electrical Strategy (TAC Nos. MF0950 and MF1177, dated March 28, 2014 On February 28, 2013, the Tennessee Valley Authority (TVA) submitted an Overall Integrated Plan (OIP) in response to the March 12, 2012, Commission Order modifying licenses with regards to requirements for mitigation strategies for beyond-design-basis external events, Order number EA-12-049, for the Watts Bar Nuclear Plant (WBN), Units 1 and 2 (Reference 1). On August 28, 2013, TVA provided the first six-month status report to the OIP (Reference 2).
The OIP submitted in Reference 1 employed a strategy using reactor coolant pump (RCP) low leakage seals. TVA revised its strategy to use the existing conventional RCP seals.
This change in RCP seals required a revision to the OIP submitted by Reference 1. These changes were presented and discussed with the Nuclear Regulatory Commission (NRC) through the mitigation strategies audit process. Based on a review of TVAs plan, including the six-month update, and information obtained through the mitigation strategies audit process, the NRC concluded in its Interim Staff Evaluation that the plan, when properly implemented, will meet the requirements of Order EA-12-049 at WBN, Units 1 and 2 (Reference 3). The Interim Staff Evaluation included two open items. Open item 3.2.1.6.A required revision to the Sequence of Events due to use of the conventional RCP seals, for reanalysis by the NRC. On February 7, 2014, TVA provided the revised OIP (Reference 4) which included the required revision to the Sequence of Events. Reference 4 also served as the second six-month status report.
The second open item, 3.2.4.8.A, required resolution for justification regarding use of pre-staged diesel generators. TVA provided the justification regarding use of pre-staged diesel generators on March 28, 2014 (Reference 5).
The purpose of this letter is to provide the third six-month status report to the OIP.
Specifically, the Enclosure of this letter provides the third six-month status report. This status report updates the status to the OIP Open Items table. The remaining OIP open items 4, 9, 10, 12, and 13 are closed. OIP Attachment 2, Milestone Schedule, has been updated and revised as noted in the revised target completion date column.
U.S. Nuclear Regulatory Commission Page 3 August 28, 2014 If you have any questions regarding this report, please contact Kevin Casey at (423) 751-8523.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2014.
Respectfully, J. W. Shea Vice President, Nuclear Licensing
Enclosure:
Tennessee Valley Authority Watts Bar Nuclear Plants Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events cc (Enclosure):
NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRR JLD Director - NRC Headquarters NRC Regional Administrator - Region II NRR Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant NRR Mitigation Strategies Director - NRC Mitigation Strategies Directorate J. W. Shea Digitally signed by J. W. Shea DN: cn=J. W. Shea, o=Tennessee Valley Authority, ou=Nuclear Licensing, email=jwshea@tva.gov, c=US Date: 2014.08.28 19:33:02 -04'00'
ENCLOSURE TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT THIRD SIX-MONTH STATUS REPORT FOR THE IMPLEMENTATION OF ORDER EA-12-049, ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS
Page 2 of 7 ENCLOSURE Introduction Tennessee Valley Authority (TVA) developed an Overall Integrated Plan (Reference 1 in Reference section of this enclosure) for Watts Bar Nuclear Plant (WBN), Units 1 and 2, documenting the diverse and flexible strategies (FLEX), in response to Reference 2. TVA provided a revised OIP on February 7, 2014 (Reference 3). This attachment provides an update of milestone accomplishments since submittal of the revised OIP (Reference 3),
including any changes to the compliance method or schedule.
Milestone Accomplishments The following milestone(s) have been completed since submittal of the revised OIP (Reference 3), and are current as of July 31, 2014.
Unit 1 Implementation Outage (FLEX mechanical and electrical connections)
Unit 2 Design Engineering Milestone Schedule Status The following provides an update to Attachment 2 of the OIP. The activity status of each item is provided, as well as any change to the expected completion date. The dates are planning dates subject to change as design and implementation details are developed.
Page 3 of 7 Milestone Target Completion Date Activity Status Revised Target Completion Date Submit 60 Day Status Report Oct 2012 Complete Submit Overall Integrated Plan Feb 2013 Complete Submit 6 Month Updates:
Update 1 Aug 2013 Complete Update 2 Feb 2014 Complete Update 3 Aug 2014 Complete FLEX Strategy Evaluation June 2013 Complete Walk-throughs or Demonstrations Sep 2014 In Progress Perform Staffing Analysis Jun 2014 Complete Modifications:
Modifications Evaluation Apr 2013 Complete Unit 1 N-1 Walkdown Apr 2013 Complete Unit 1 Design Engineering Oct 2013 Complete Unit 1 Implementation Outage May 2014 Complete Unit 2 Construction Walkdown Apr 2013 Complete Unit 2 Design Engineering Feb 2014 Complete Unit 2 Implementation (Startup)
Aug 2014 On Track Sep 2014 Storage Storage Design Engineering Complete Storage Implementation Aug 2014 On Track Sep 2014 On-Site FLEX Equipment Procure Feb 2014 On Track Sep 2014 Off-Site FLEX Equipment Develop Strategies with RRC Jun 2014 On Track Sep 2014 Install Off-site Delivery Station Apr 2014 On Track Sep 2014 Procedures:
PWROG issues NSSS-specific guidelines Jun 2013 Complete Create Site-Specific FSIs Apr 2014 On Track Sep 2014 Create Maintenance Procedures Apr 2014 On Track Sep 2014 Training:
Develop Training Plan Apr 2014 Complete Training Complete Jul 2014 On Track Sep 2014 Unit 1 FLEX Implementation Aug 2014 On Track Sep 2014 Unit 2 FLEX Implementation Aug 2014 On Track Sep 2014 Full Site FLEX Implementation Aug 2014 Not Started Mar 20151 Submit Completion Report Aug 2014 Not Started Mar 20151 1 - Full site FLEX implementation is tied to 30 days prior to U2 Operating License to allow for completion of pre-operational testing of U2 components.
Page 4 of 7 Changes to Compliance Method There have been no changes to the compliance methods since submittal of the revised OIP in Reference 3.
Need for Relief and Basis for the Relief Watts Bar expects to comply with the order implementation date and no relief is required at this time.
Open Items from Overall Integrated Plan and NRC Evaluation The following table provides a summary of the open items documented in the OIP or the NRC Evaluation and the status of each item.
Open Item Number Description Status 1
The current Condensate Storage Tank (CST) is a non-seismic tank that is not missile protected. The site is currently pursuing two options; the qualification and hardening of the existing CST or the construction of a new seismically qualified and missile protected CST. One of these options must be completed before the volume of the CST can be credited.
Closed A new qualified Auxiliary Feedwater Supply Tank (AFWST) will be used instead of using the Condensate Storage Tank (CST) for FLEX.
2 Liquefaction of haul routes for FLEX will be analyzed.
Closed Reference WBN White Paper (EDMS 24900-100-KOR-CY00-00001) 3 No detailed analysis has been provided regarding initial FLEX fuel supplies to determine a need time for access to 7 day tank supplies or resupply of the 7 day tanks. It is assumed that each FLEX component is stored with a minimum supply of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of fuel at constant operation. This assumption will need to be assessed once all FLEX equipment has been purchased and equipment specifications are known.
Closed Fuel consumption spreadsheet completed to show that fuel supply of equipment will last seven days.
4 No need time has been identified for action to protect containment. This includes actions to mitigate pressurization of containment due to steaming when reactor coolant system (RCS) vent paths have been established or actions to mitigate temperature effects associated with equipment survivability. An evaluation will be provided to prove indefinite containment coping.
Closed Reference LTR-ISENG-14-1, Rev 0
Page 5 of 7 Open Item Number Description Status 5
The Phase 3 equipment staging area has not been determined.
Closed Areas are identified and will be included with the SAFER National Response Center playbook 6
A strategy for clearing and removing debris will be determined.
Closed Debris removal equipment is identified and storage determined.
7 A thorough analysis of the makeup flow rate requirements and other equipment characteristics will be finalized during the detailed design phase of FLEX.
Closed Detailed FLEX Operating Conditions and pump sizing has been completed Reference CN-SEE-II-13-26, Rev 1 8
The need time for spent fuel pool (SFP) cooling actions (deployment of hose, venting, and alignment of makeup) was determined using worst case heat loads. This item will continue to be assessed and later action times may be acceptable. Note that the timing for this step during an outage is different, but resources will be available to complete the required actions.
Closed Reference CN-SEE-II-12-40, Rev 3 9
Functional requirements for each of the Phase 3 strategies, equipment and components will be completed at a later time and will be provided in the six month updates to the February 28, 2013 submittal.
Closed Reference WBN SAFER National Response Center Playbook 10 Containment temperature instrumentation is only available until flood waters enter the technical support center (TSC) inverter or station battery rooms. A method to monitor containment temperature, post-flood, will be developed.
Closed Reference LTR-ISENG-14-1, Rev 0 11 The heating, ventilation and air conditioning (HVAC) analysis is preliminary, and has not been finalized.
Closed Reference Calculation MDQ0003602012000272 12 Verify ability to deploy FLEX equipment to provide core cooling in Modes 5 and 6 with steam generators (SGs) unavailable.
Closed Reference NPG-SPP-07.2.11, Rev 5
Page 6 of 7 Open Item Number Description Status 13 An evaluation of the impact of FLEX response actions on design basis flood mode preparations will be performed. This evaluation will include the potential for extended preparation time for FLEX.
Changes which affect the Integrated Plan will be included in the six month update.
Closed TVAs River Systems Operation (RSO) will notify the WBN control room if Watts Bar Hydro instantaneous flow rate reaches 170,000 cfs, which approximates the 25 year flood frequency based upon observed historical flow data. This notification will provide for initiation and completion of preparatory FLEX equipment deployment and mitigation strategy implementation prior to conditions that might trigger a Stage 1 Flood Warning from RSO.
14 Further analysis will be performed to determine the required timeline for implementing the 3 MWe diesel generators (DGs) as an alternate power source for the loads supplied by the 225 kva 480 Vac DGs.
Closed The 3 MWe DGs are available within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. A line will be added to 225 kva timing to state that if 225s not available, then 3 MWe to be started.
15 The CETs are only available until water enters the auxiliary instrument room. A method to monitor CET, post flood, will be evaluated and developed, if required.
Closed CETs will not be required for flood event.
16 Strategies to address extreme cold conditions on the refueling water storage tank (RWST) and/or boric acid tanks (BATs), including potential need to reenergize heaters have not been finalized.
Closed Reference Westinghouse LTR-SEE-11-14-44, Rev 0 17 Establish a contract with the Strategic Alliance for FLEX Emergency Response (SAFER) team in accordance with the requirements of Section 12 of NEI 12-06.
Closed Agreement with SAFER National Response Center is in place.
18 Manual station blackout (SBO) load shedding time in References 4 and 5, Section 8.3.2.1.1, will be revised from 30 minutes to 45 minutes as supported by the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> extended loss of alternating current power (ELAP) battery calculations.
Closed Reference TVA EDQ00023620070003 Rev 28 and EPMMA041592 Rev 20
Page 7 of 7 Potential NRC Evaluation Impacts There are no potential impacts or Open Items to the NRC Evaluation identified at this time.
References The following references support the updates to the OIP described in this enclosure.
- 1. Letter from TVA to NRC, Watts Bars Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28, 2013.
- 2. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012.
- 3. Letter from TVA to NRC, Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 12 049) for Watts Bar Nuclear Plant (TAC Nos. MF0950 and MF1177), dated February 7, 2014 (ML14062A050)
- 4. Letter from TVA to NRC, Response to NRC Staff Audit Question Clarification for Watts Bar Nuclear Plant, Units 1 and 2 Mitigation Strategies Integrated Plan, Phase 2 Electrical Strategy (TAC Nos. MF0950 and MF1177), dated March 28, 2014