ML17261B179
From kanterella
Revision as of 01:11, 21 March 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Letter Sequence Response to RAI | |
---|---|
TAC:MF1185, Control Room Habitability (Approved, Closed) TAC:MF1186, Control Room Habitability (Approved, Closed) TAC:MF1187, Control Room Habitability (Approved, Closed) | |
Initiation Administration Questions Answers | |
MONTHYEARML13092A3922013-03-27027 March 2013
[Table View]Transition to 10 CFR 50.48(c) - NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition - Transition Report Project stage: Request ML13092A3932013-03-27027 March 2013 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) (Technical Specification Change TS-480) Project stage: Request ML13087A4182013-04-0808 April 2013 National Fire Protection Association Standard 805 License Amendment Application Online Reference Portal Project stage: Other ML13128A0132013-05-0303 May 2013 Response to NRC Request for Confirmation of Terms and Conditions of Online Reference Portal, NFPA 805 License Amendment Application Project stage: Request ML13141A2912013-05-16016 May 2013 Response to NRC Request to Supplement License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Supplement ML13149A3642013-05-31031 May 2013 Acceptance Review Concerning LAR to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, Project stage: Acceptance Review ML13298A7022013-11-19019 November 2013 RAI Regarding LAR to Request Adopt National Fire Protection Association Standard 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (TAC Nos. MF1185 - MF1187) Project stage: RAI CNL-13-141, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants - Set 12013-12-20020 December 2013 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants - Set 1 Project stage: Response to RAI CNL-14-001, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plant2014-01-10010 January 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plant Project stage: Response to RAI CNL-14-006, Response to NRC Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for Browns Ferry Plant, Units 1, 22014-01-14014 January 2014 Response to NRC Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for Browns Ferry Plant, Units 1, 2 & Project stage: Response to RAI CNL-14-020, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants2014-02-13013 February 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI CNL-14-025, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants2014-03-14014 March 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI ML14154A4962014-05-30030 May 2014 Update to the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Request CNL-14-097, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants...2014-06-13013 June 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants... Project stage: Response to RAI CNL-14-116, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light Water Reactor2014-07-10010 July 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light Water Reactor Project stage: Response to RAI CNL-14-147, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants2014-08-29029 August 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI CNL-14-160, Update to the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2 and 32014-09-16016 September 2014 Update to the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Project stage: Request CNL-14-208, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Pl2014-12-17017 December 2014 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plan Project stage: Response to RAI CNL-15-054, Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants..2015-03-26026 March 2015 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants.. Project stage: Response to RAI ML15085A5522015-03-27027 March 2015 Response to NRC Request for Additional Information Regarding the License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Response to RAI ML15076A1852015-05-0808 May 2015 Audit Report to Support Proposed Amendment to Transition to the National Fire Protection Association Standard 805 Fire Protection Licensing Basis Project stage: Other CNL-15-074, Update to License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants2015-06-19019 June 2015 Update to License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants Project stage: Request ML15190A2342015-07-0909 July 2015 Record of Review of Internal Events and Fire PRA for NFPA 805 SE Section 3 4 (07-09-2015) Project stage: Request ML15243A5562015-08-20020 August 2015 NRR E-mail Capture - Browns Ferry, 1, 2, and 3 - Issuance of Amend Transition to a RISK-INFORMED, PERFORMANCE-BASED Fire Protection Program (TAC Nos. MF1185, MF1186, and MF1187) Project stage: Approval CNL-15-191, Update to License Amendment Request to Adopt NFPA 805 Performance- Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MF1185, MF1186, and M2015-09-0808 September 2015 Update to License Amendment Request to Adopt NFPA 805 Performance- Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MF1185, MF1186, and MF1 Project stage: Request CNL-15-224, Update to License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants - Revised Implementation Item 492015-10-20020 October 2015 Update to License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants - Revised Implementation Item 49 Project stage: Request ML15212A7962015-10-28028 October 2015 Issuance of Amendments to Transition to Fire Protection Program NFPA-805 Project stage: Approval CNL-15-253, Brown Ferry, Units 1, 2, and 3 - Change in Commitment Related to Interim Compensatory Measures to Reduce Fire Risk2016-01-0505 January 2016 Brown Ferry, Units 1, 2, and 3 - Change in Commitment Related to Interim Compensatory Measures to Reduce Fire Risk Project stage: Other CNL-16-059, Revision to NFPA 805 Interim Compensatory Measures Commitments Regarding Hot Work and Combustible Controls2016-05-10010 May 2016 Revision to NFPA 805 Interim Compensatory Measures Commitments Regarding Hot Work and Combustible Controls Project stage: Other CNL-16-165, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 34, Revised Proposed License Conditions and Technical Specification Change2016-10-31031 October 2016 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 34, Revised Proposed License Conditions and Technical Specification Change Project stage: Supplement CNL-17-024, Update to License Amendment Request to Revise NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor - Revision to Tables S-2 and S-32017-06-0707 June 2017 Update to License Amendment Request to Revise NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor - Revision to Tables S-2 and S-3 Project stage: Request CNL-17-109, Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Genera2017-09-18018 September 2017 Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generati Project stage: Response to RAI CNL-17-130, Update to Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection For..2017-10-23023 October 2017 Update to Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection For.. Project stage: Response to RAI 2014-08-29 |
ML17261B179 | |
Person / Time | |
---|---|
Site: | Browns Ferry |
Issue date: | 09/18/2017 |
From: | Shea J W Tennessee Valley Authority |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
CNL-17-109, TAC MF1185, TAC MF1186, TAC MF1187 | |
Download: ML17261B179 (42) | |
Similar Documents at Browns Ferry | |
---|---|
Category:Letter
MONTHYEARML24289A1232024-10-24024 October 2024
[Table view]Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 ML24239A3332024-09-0303 September 2024 Full Audit Plan IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request ML24219A0272024-08-0606 August 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000259/20244022024-08-0606 August 2024 Security Baseline Inspection Report 05000259/2024402 and 05000260/2024402 and 05000296/2024402 IR 05000259/20240022024-08-0202 August 2024 Brown Ferry Nuclear Plant – Integrated Inspection Report05000259/2024002 and 05000260/2024002 and 05000296/2024002 ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24183A4142024-07-10010 July 2024 – License Renewal Regulatory Limited Scope Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-SLE-0000) (Docket Numbers: 50-259, 50-260, and 50-296) 05000296/LER-2024-003, Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints2024-07-0808 July 2024 Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints 05000259/LER-2024-001-01, Inoperability of Unit 3 Diesel Generator Due to Relay Failure2024-07-0303 July 2024 Inoperability of Unit 3 Diesel Generator Due to Relay Failure ML24184A1142024-07-0202 July 2024 Site Emergency Plan Implementing Procedure Revision ML24183A3842024-07-0101 July 2024 Registration of Use of Cask to Store Spent Fuel (MPC-364, -365) ML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) 05000259/LER-2024-002, Reactor Scram Due to Generator Step-Up Transformer Failure2024-06-24024 June 2024 Reactor Scram Due to Generator Step-Up Transformer Failure ML24175A0042024-06-23023 June 2024 Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System ML24176A1132024-06-23023 June 2024 American Society of Mechanical Engineers, Section XI, Fourth 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owner’S Activity Report Cycle 21 Oper ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24155A0042024-06-18018 June 2024 Proposed Alternative to the Requirements of the ASME Code (Revised Alternative Request 0-ISI-47) ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24071A0292024-06-0505 June 2024 Subsequent License Renewal Application Enclosure 3 - Proprietary Determination Letter ML24068A2612024-06-0505 June 2024 SLRA Fluence Methodology Report - Proprietary Determination Letter IR 05000259/20244032024-05-22022 May 2024 – Security Baseline Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 05000260/LER-2024-002, High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation2024-05-20020 May 2024 High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A0702024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000259/20240012024-05-14014 May 2024 Integrated Inspection Report 05000259/2024001, 05000260/2024001, and 05000296/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24123A2012024-05-0202 May 2024 NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000259/2024404, 05000260-2024404, 05000296/2024404) and Request for Information ML24122A6852024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual CNL-24-036, – 10 CFR 50.46 Annual Report2024-04-25025 April 2024 – 10 CFR 50.46 Annual Report ML24116A2522024-04-25025 April 2024 Site Emergency Plan Implementing Procedure Revision 05000296/LER-2024-002, Breaker Trip Automatically Started an Emergency Diesel Generator2024-04-24024 April 2024 Breaker Trip Automatically Started an Emergency Diesel Generator 05000296/LER-2024-001, Primary Containment Isolation Valve Inoperable Due to Incorrect Motor Operated Valve Setup2024-04-22022 April 2024 Primary Containment Isolation Valve Inoperable Due to Incorrect Motor Operated Valve Setup CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A2302024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 2024-09-03 Category:Response to Request for Additional Information (RAI) MONTHYEARCNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024
[Table view]Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 CNL-24-026, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-14014 March 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-24-029, Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 372024-03-14014 March 2024 Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 37 CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 CNL-23-037, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Request2023-06-0101 June 2023 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Requests CNL-23-019, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Request for Alternative BFN-0-ISI-322023-03-11011 March 2023 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Request for Alternative BFN-0-ISI-32 CNL-22-097, Response to Request for Additional Information and Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide .2022-12-0101 December 2022 Response to Request for Additional Information and Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide . CNL-22-075, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Unit 2, Request for Alternative, BFN-21-ISI-02, Alternative to American Society of Mechanical Engineers, Boiler and Pressure Vessel Code, Section Xi,.2022-09-12012 September 2022 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Unit 2, Request for Alternative, BFN-21-ISI-02, Alternative to American Society of Mechanical Engineers, Boiler and Pressure Vessel Code, Section Xi,. CNL-22-065, Response to Request for Confirmation of Information and Additional Information and Second Supplement Regarding Application Requesting NRC Prior Approval of a Proposed Chilled-Water Cross-tie.2022-08-0101 August 2022 Response to Request for Confirmation of Information and Additional Information and Second Supplement Regarding Application Requesting NRC Prior Approval of a Proposed Chilled-Water Cross-tie. CNL-22-066, Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 for in Support of Atrium 11 Fuel Use Supplement 3, Response to Request for Additional Information2022-07-18018 July 2022 Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 for in Support of Atrium 11 Fuel Use Supplement 3, Response to Request for Additional Information CNL-22-064, Response to Request for Additional Information Regarding Tennessee Valley Authority License Amendment Request to Revise Emergency Plan Implementing Procedure Regarding Seismic Event Emergency Action Level Change2022-06-0909 June 2022 Response to Request for Additional Information Regarding Tennessee Valley Authority License Amendment Request to Revise Emergency Plan Implementing Procedure Regarding Seismic Event Emergency Action Level Change CNL-22-007, Supplement to Application Requesting NRC Prior Approval of a Proposed Chilled-Water Cross-tie Modification to Support System Operability (BFN-TS-518)2022-04-0606 April 2022 Supplement to Application Requesting NRC Prior Approval of a Proposed Chilled-Water Cross-tie Modification to Support System Operability (BFN-TS-518) CNL-22-028, Response to Request for Additional Information Regarding License Amendment Request Regarding Criticality Safety Analysis of Spent Fuel Pool Storage of Atrium 11 Fuel (TS-534)2022-03-18018 March 2022 Response to Request for Additional Information Regarding License Amendment Request Regarding Criticality Safety Analysis of Spent Fuel Pool Storage of Atrium 11 Fuel (TS-534) CNL-21-052, Response to Request for Additional Information Regarding License Amendment Request to Modify Technical Specification 3.8.6, Battery Cell Parameters (TS-531)2021-07-21021 July 2021 Response to Request for Additional Information Regarding License Amendment Request to Modify Technical Specification 3.8.6, Battery Cell Parameters (TS-531) CNL-21-033, Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components2021-04-28028 April 2021 Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components CNL-21-017, Response to Request for Additional Information Regarding License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into the Licensing Basis, (L-2020-LLA-0099)2020-12-29029 December 2020 Response to Request for Additional Information Regarding License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into the Licensing Basis, (L-2020-LLA-0099) CNL-20-089, Response to RAI Re Application for Tech. Specification Change Re Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (BFN-TS-518)2020-12-21021 December 2020 Response to RAI Re Application for Tech. Specification Change Re Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (BFN-TS-518) CNL-20-059, Response to Request for Additional Information Regarding Proposed Alternative Request No. 0-ISI-47 for the Third, Fifth, and Fourth 10-Year Inservice Inspection Intervals2020-08-10010 August 2020 Response to Request for Additional Information Regarding Proposed Alternative Request No. 0-ISI-47 for the Third, Fifth, and Fourth 10-Year Inservice Inspection Intervals CNL-19-122, Seismic Probabilistic Risk Assessment Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights2019-12-17017 December 2019 Seismic Probabilistic Risk Assessment Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights CNL-19-064, Response to NRC Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF)-542, Reactor Pressure Vessel Water...2019-08-0808 August 2019 Response to NRC Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF)-542, Reactor Pressure Vessel Water... CNL-19-052, Response to NRC Request for Additional Information Regarding Re-Submittal of American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Inservice Inspection (ISI) Program and Augmented Program, Second2019-07-19019 July 2019 Response to NRC Request for Additional Information Regarding Re-Submittal of American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Inservice Inspection (ISI) Program and Augmented Program, Second CNL-19-017, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 7, Response to Requests for Additional Information2019-01-25025 January 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 7, Response to Requests for Additional Information CNL-19-007, Supplement 5, Response to Requests for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus2019-01-16016 January 2019 Supplement 5, Response to Requests for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus CNL-19-011, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 6, Additional Operator Training Results2019-01-16016 January 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 6, Additional Operator Training Results CNL-18-139, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information2018-12-14014 December 2018 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information CNL-18-140, Response to Request for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 42018-12-13013 December 2018 Response to Request for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 4 CNL-18-117, Response to Request for Additional Information Regarding Browns Ferry Units 1, 2, and 3: Code Case N-702 for Alternative Request ISI-462018-10-17017 October 2018 Response to Request for Additional Information Regarding Browns Ferry Units 1, 2, and 3: Code Case N-702 for Alternative Request ISI-46 CNL-18-120, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant Unit 1, American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Inservice Inspection (ISI) Program, Unit 1 Second Ten-year ..2018-10-11011 October 2018 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant Unit 1, American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Inservice Inspection (ISI) Program, Unit 1 Second Ten-year ... ML18283A8972018-10-10010 October 2018 Enclosure 1: Proposed Changes to Browns Ferry Nuclear Plant Unit 1 Technical Specifications, Attachments 1, 2, & 3 CNL-18-089, Response to Request for Additional Information Regarding Decommissioning Funding Plan Update for Browns Ferry Nuclear Plant and Sequoyah Nuclear Plant Independent Spent Fuel Storage Installations, Docket Nos. 72-052 and 72-0342018-07-23023 July 2018 Response to Request for Additional Information Regarding Decommissioning Funding Plan Update for Browns Ferry Nuclear Plant and Sequoyah Nuclear Plant Independent Spent Fuel Storage Installations, Docket Nos. 72-052 and 72-034 CNL-18-044, Tennessee Valley Authority Response to NRC Request for Additional Information Related to Topical Report TVA-NPG-AWA16, TVA Overall Basin Probable Maximum Precipitation.2018-04-19019 April 2018 Tennessee Valley Authority Response to NRC Request for Additional Information Related to Topical Report TVA-NPG-AWA16, TVA Overall Basin Probable Maximum Precipitation. NL-18-044, Browns Ferry Units 1, 2, and 3; Sequoyah Units 1 and 2; Watts Bar Units 1 and 2 - Tennessee Valley Authority Response to NRC Request for Additional Information Related to Topical Report TVA-NPG-AWA16, TVA Overall Basin Probable Maximum Pre2018-04-19019 April 2018 Browns Ferry Units 1, 2, and 3; Sequoyah Units 1 and 2; Watts Bar Units 1 and 2 - Tennessee Valley Authority Response to NRC Request for Additional Information Related to Topical Report TVA-NPG-AWA16, TVA Overall Basin Probable Maximum Prec CNL-18-032, Tennessee Valley Authority Response to NRC Request for Additional Information (Set 2) Related to BFN Application to Revise Technical Specification 5.5.12 Primary Containment Leakage Rate Testing Program2018-03-27027 March 2018 Tennessee Valley Authority Response to NRC Request for Additional Information (Set 2) Related to BFN Application to Revise Technical Specification 5.5.12 Primary Containment Leakage Rate Testing Program CNL-18-011, Tennessee Valley Authority Response to NRC Request for Additional Information Related to BFN Application to Revise Technical Specification 5.5.12 Primary Containment Leakage Rate Testing Program (BFN-TS-497)2018-02-0505 February 2018 Tennessee Valley Authority Response to NRC Request for Additional Information Related to BFN Application to Revise Technical Specification 5.5.12 Primary Containment Leakage Rate Testing Program (BFN-TS-497) CNL-17-130, Update to Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection For..2017-10-23023 October 2017 Update to Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection For.. CNL-17-109, Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Genera2017-09-18018 September 2017 Response to NRC Request for Additional Information for License Amendment Request to Revise Modifications and an Implementation Item Related to NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generati CNL-17-098, Revised Response to NRC Request for Additional Information Related to TVA Fleet License Amendment Request to Adopt NEI 99-01 Revision 6 Emergency Action Levels2017-07-27027 July 2017 Revised Response to NRC Request for Additional Information Related to TVA Fleet License Amendment Request to Adopt NEI 99-01 Revision 6 Emergency Action Levels CNL-17-085, Response to NRC Request for Additional Information Related to TVA Fleet License Amendment Request to Adopt NEI 99-01 Revision 6 Emergency Action Levels2017-07-0707 July 2017 Response to NRC Request for Additional Information Related to TVA Fleet License Amendment Request to Adopt NEI 99-01 Revision 6 Emergency Action Levels CNL-17-039, Response to NRC Request for Information, Per 10CFR50.54(f) Regarding Recommendations 2.1, 2.3 and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident - Withdrawal of Regulatory..2017-03-10010 March 2017 Response to NRC Request for Information, Per 10CFR50.54(f) Regarding Recommendations 2.1, 2.3 and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident - Withdrawal of Regulatory.. CNL-17-035, Proposed Technical Specifications Change TS-505 - Request for License Amendments - Extended Power Uprate(Epu) - Supplement 38, Spent Fuel Pool Criticality Safety Analysis - Updated Information2017-03-0303 March 2017 Proposed Technical Specifications Change TS-505 - Request for License Amendments - Extended Power Uprate(Epu) - Supplement 38, Spent Fuel Pool Criticality Safety Analysis - Updated Information CNL-17-017, Proposed Technical Specifications (TS) Change TS-505 Request for License Amendments - Extended Power Uprate (EPU) - Supplement 37, Transmission System Update - Environmental Aspects2017-02-0303 February 2017 Proposed Technical Specifications (TS) Change TS-505 Request for License Amendments - Extended Power Uprate (EPU) - Supplement 37, Transmission System Update - Environmental Aspects CNL-17-015, Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 36, Transmission System Update -Safety Aspects2017-01-20020 January 2017 Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 36, Transmission System Update -Safety Aspects NL-17-015, Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 36, Transmission System Update -Saf2017-01-20020 January 2017 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 36, Transmission System Update -Safe CNL-16-196, Revised Response to NRC Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools2016-12-19019 December 2016 Revised Response to NRC Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools CNL-16-161, Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 33, Revised Response to Request for Additional..2016-10-13013 October 2016 Transmittal of Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 33, Revised Response to Request for Additional.. CNL-16-145, Revised Responses to Requests for Additional Information Regarding Proposed Technical Specifications Change TS-505 - Extended Power Uprate - Supplement 302016-09-23023 September 2016 Revised Responses to Requests for Additional Information Regarding Proposed Technical Specifications Change TS-505 - Extended Power Uprate - Supplement 30 CNL-16-150, Revised Response to Requests for Additional Information Proposed Technical Specifications Change TS-505 - Request for License Amendment - Extended Power Uprate - Supplement 312016-09-21021 September 2016 Revised Response to Requests for Additional Information Proposed Technical Specifications Change TS-505 - Request for License Amendment - Extended Power Uprate - Supplement 31 CNL-16-133, Response to NRC Request for Additional Information Related to License Amendment Request for Adding New Specifications to Technical Specification 3.3.8.3 (BFN-TS-486) (CAC Nos. MF6738, MF6739, and MF6740) - Letter 72016-09-15015 September 2016 Response to NRC Request for Additional Information Related to License Amendment Request for Adding New Specifications to Technical Specification 3.3.8.3 (BFN-TS-486) (CAC Nos. MF6738, MF6739, and MF6740) - Letter 7 CNL-16-152, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 32, Revised Responses to Requests for Additional Information2016-09-12012 September 2016 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 32, Revised Responses to Requests for Additional Information CNL-16-126, Response to NRC Request for Additional Information Related to License Amendment Request for Adding New Specifications to Technical Specification 3.3.8.3 (BFN-TS-486)2016-08-24024 August 2016 Response to NRC Request for Additional Information Related to License Amendment Request for Adding New Specifications to Technical Specification 3.3.8.3 (BFN-TS-486) 2024-03-14 |
Text
Retrieved from "https://kanterella.com/w/index.php?title=ML17261B179&oldid=505555"