ML20071C211

From kanterella
Revision as of 06:56, 15 December 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in IE Insp Repts 50-438/82-22 & 50-439/82-22.Corrective Actions Delayed by Extensive Vendor Evaluation But Will Be Completed by 830701
ML20071C211
Person / Time
Site: Bellefonte  
Issue date: 12/16/1982
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8303010563
Download: ML20071C211 (1)


Text

.

ggcTENNESSEE VALLEY AUTHORITY

' " A ' CH ATTANOOGA, TENNESSEE 374ol 400 Chestnut Street Tower II g g 22 b '.

December 16, 1982 U.S. Nuclear Regulatory Commission Region II Attn:

Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 - SUPPLEMENTAL RESPONSE TO VIOLATION 50-438,50-439/82-22 VIOLATION OF CABLE MINIMUM BEND RADIUS This is in response to R. C. Lewis' letter dated August 12, 1982, report numbers 50-438/82-22, 50-439/82-22, concerning activities at the Bellefonte Nuclear Plant which appeared to have been in violation of NRC regulations.

The original response to this violation was submitted September 9, 1982, and a revised response was submitted September 24, 1c82. As discussed with NRC-0IE Inspector R. V. Celenjak by telephone or, December 3,1982, the date of December 20, 1982 for completion of corrective actions indicated in our revised response on this matter will not be met. Although TVA has contacted the vendors of the cables, they require more time to evaluate this condition. The corrective action on this matter will be completed by July 1, 1983.

If you have any questions concerning this matter, please get in touch with R. H. Shell at FTS 858-2688.

To the best of my knowledge, I declare the statements contained herein are complete and true.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Licensing Mr. Richard C. DcYoung, Director cc:

Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.

20555 oh4hg 0

PDR An Ecual Opportumty Employ er L

7

,