IE energy
~
harbor Rod L. Penfield Site Vice President, Beaver Valley Nuclear May 20, 2020 L-20-051 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-001
SUBJECT:
Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Energy Harbor Nuclear Corp.
Beaver Valley Power Station P. 0. Box4 Shippingport, PA 15077 724-682-5234 10 CFR 50.71 (e) 10 CFR 50.54(a) 10 CFR 54.37(b)
Submittal of the Updated Final Safety Analysis Report, Revision 32 In accordance with the requirements of 10 CFR 50.71 (e), the Energy Harbor Nuclear Corp. is hereby submitting to the Nuclear Regulatory Commission (NRC) the Beaver Valley Power Station, Unit No. 1 (BVPS-1), Updated Final Safety Analysis Report (UFSAR) Revision 32 in CD-ROM format. This submittal reflects facility and procedure changes implemented between May 10, 2018 (the end of Refueling Outage 25), and November 5, 2019 (the end of Refueling Outage 26), along with several changes implemented after Refueling Outage 26.
In accordance with 10 CFR 50.4(b)(6), the BVPS-1 UFSAR Revision 32 is being submitted electronically{ on a total replacement basis. As required by NRC guidance for electronic submissions to the Commission, Attachment 1 and 2 provide a listing of the document components that make up the two enclosed CD-ROMs. In addition to the UFSAR, the first enclosed CD-ROM includes the following:
BVPS-1 Licensing Requirements Manual (LRM), Revision 105 Technical Specification (TS) Bases, Revision 37, submitted to satisfy TS 5.5.1 0.d, which requires submittal of TS Bases changes implemented without prior NRC approval
Beaver Valley Power Station, Unit No. 1 L-20-051 Page2 The second enclosed CD-ROM includes the BVPS-1 UFSAR, LRM, and TS Bases with information identified in accordance with NRC Regulatory Issue Summary (RIS) 2015-17, "Review and Submission of Updates to Final Safety Analysis Reports, Emergency Preparedness Documents, and Fire Protection Documents," removed.
For this BVPS-1 UFSAR update, no excessive detail, obsolete information, or redundant information has been removed in accordance with Appendix A to Nuclear Energy Institute (NEI) 98-03, Revision 1, "Guidelines for Updating Final Safety An_alysis Reports," as endorsed by Regulatory Guide 1.181, "Content of the Updated Final Safety Analysis Report in Accordance with 10 CFR 50.71(e)."
Energy Harbor Nuclear Corp. conducted a review of BVPS-1 plant changes for 10 CFR 54.37(b) applicability. No components were determined to meet the criteria for newly identified components as clarified by Regulatory Information Summary (RIS) 2007-16, Revision 1, "Implementation of the Requirements of 10 CFR 54.34(b) for Holders of Renewed Licenses."
There are no regulatory commitment changes to be submitted in accordance with NEI 99-04, "Guidelines for Managing NRC Commitment Changes," Revision 0, as endorsed by NRC RIS 2000-17, "Managing Regulatory Commitments Made by Power Reactor Licensees to the NRC Staff."
This certifies, to the best of our judgment and belief, that Revision 32 of the BVPS-1 UFSAR accurately presents changes made since the previous submittal that are necessary to reflect information and analysis submitted to the Commission or pursuant to Commission requirements.
This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact Mr. Thomas A. Lentz, Manager - Nuclear Licensing and Regulatory Affairs, at (330) 315-6810.
Sincerely, K_/ _ In Penfield, Rod C6593
~dr~ May20202011:47~
Rod L. Penfield
Beaver Valley Power Station, Unit No. 1 L-20-051 Page3 Attachments:
- 1.
List of Document Components on CD-ROM 1
- 2.
List of Document Components on CD-ROM 2 (Information Identified Per RIS 2015 -17 Removed)
Enclosures:
A.
Beaver Valley Power Station, Unit No. 1 UFSAR, Licensing Requirements Manual, and Technical Specification Bases (on CD-ROM 1)
B.
Beaver Valley Power Station, Unit No. 1 UFSAR With Information Identified Per RIS 2015-17 Removed, Licensing Requirements Manual, and Technical Specification Bases (on CD-ROM 2) cc:
NRC Region I Administrator (without Enclosure B)
NRC Resident Inspector (without Enclosure B)
NRC Project Manager (without Enclosure B)
Director BRP/DEP (without Enclosures)
Site BRP/DEP Representative (without Enclosures)
L-20-051 List of Document Components on CD-ROM 1 Page 1 of 1 File Name 001 UFSAR List of Effective Pages Rev 32.pdf 002 UFSAR Section 1.pdf 003 UFSAR Section 2.pdf 004 UFSAR Section 3.pdf 005 UFSAR Section 4.pdf 006 UFSAR Section 5.pdf 007 UFSAR Section 6.pdf 008 UFSAR Section 7.pdf 009 UFSAR Section 8.pdf 010 UFSAR Section 9.pdf 011 UFSAR Section 10.pdf 012 UFSAR Section 11.pdf 013 UFSAR Section 12.pdf 014 UFSAR Section 13.pdf 015 UFSAR Section 14.pdf 016 UFSAR Section 15.pdf 017 UFSAR Section 16.pdf 018 UFSAR Appendix A.pdf 019 UFSAR Appendix B.pdf 020 BVPS-1 LRM Rev 105.pdf 021 BVPS TS Bases Rev 37 (Part 1 of 2).pdf 022 BVPS TS Bases Rev 37 (Part 2 of 2).pdf 93KB 3,187KB 43,412KB 6,515KB 1,791KB 4,128KB 9,690KB 4,642KB 1,868KB 2,069KB 1,036KB 1,179KB 139KB 415KB 6,725KB 131KB 403KB 618KB 1,742KB 34,277KB 1,396KB 1,296KB L-20-051 List of Document Components on CD-ROM 2 (Information Identified Per RIS 2015-17 Removed)
Page 1 of 1 File Name 001 UFSAR List of Effective Pages Rev 32.pdf 002 UFSAR Section 1.pdf 003 UFSAR Section 2.pdf 004 UFSAR Section 3.pdf 005 UFSAR Section 4.pdf 006 UFSAR Section 5.pdf 007 UFSAR Section 6.pdf 008 UFSAR Section 7.pdf 009 UFSAR Section 8.pdf 010 UFSAR Section 9.pdf 011 UFSAR Section 1 0.pdf 012 UFSAR Section 11.pdf 013 UFSAR Section 12.pdf 014 UFSAR Section 13.pdf 015 UFSAR Section 14.pdf 016 UFSAR Section 15.pdf 017 UFSAR Section 16.pdf 018 UFSAR Appendix A.pdf 019 UFSAR Appendix B.pdf 020 BVPS-1 LRM Rev 105.pdf 021 BVPS TS Bases Rev 37 (Part 1 of 2).pdf 022 BVPS TS Bases Rev 37 (Part 2 of 2).pdf 93KB 1,216KB 42,922KB 6,515KB 1,791KB 2,917KB 9,690KB 4,642KB 3,492KB 2,069KB 1,036KB 1,179KB 139KB 41~KB 6,724KB 131KB 403KB 618KB 1,742KB 34,277KB 1,396KB 1,296KB