ENS 55345
From kanterella
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
ENS Event | |
---|---|
11:00 May 13, 2021 | |
Title | Invalid Actuation of Containment Isolation Signal |
Event Description | This 60-Day telephone notification is being made per the reporting requirements specified in 10 CFR 50.73(a)(2)(iv)(A) to describe an invalid actuation of containment isolation signal affecting more than one system. On May 13, 2021, during the restoration of the Unit 2 Refuel Floor High Radiation Isolation Logic an invalid isolation signal was received. The condition requiring an isolation signal was verified not to be present prior to restoring the logic; however, it was not recognized that a previous isolation signal was latched in and had not been reset. When the isolation logic was restored, the Primary Containment Isolation System (PCIS) isolated on the invalid signal. The systems successfully completed the isolation per the plant design and plant configuration.
The following systems actuated due to the Unit 2 PCIS Group 6C Isolation: - Isolation of Containment Hydrogen and Oxygen Sampling Valves, - Start of the 2A Reactor Enclosure Recirculation System, - Trip of the Units 1 and 2 Refuel Floor HVAC, - Start of the A and B Trains of Standby Gas Treatment Systems. The NRC Resident Inspector was notified. |
Where | |
---|---|
Limerick Pennsylvania (NRC Region 1) | |
Reporting | |
10 CFR 50.73(a)(1), Submit an LER, Invalid Actuation | |
Time - Person (Reporting Time:+1353.12 h56.38 days <br />8.054 weeks <br />1.854 months <br />) | |
Opened: | Richard Wagner 20:07 Jul 8, 2021 |
NRC Officer: | Brian P. Smith |
Last Updated: | Jul 8, 2021 |
55345 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 55345\u003C/a\u003E - \u003Ca href=\"/Limerick\" title=\"Limerick\"\u003ELimerick\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EInvalid Actuation of Containment Isolation Signal\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 55345 - Limerick\n","link":"","lat":40.22646666666667,"lon":-75.58323333333334,"icon":"/w/images/b/be/Constellation_icon.png"}],"imageoverlays":null} | |
Unit 2 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Hot Shutdown (0 %) |
After | Power Operation (100 %) |
WEEKMONTHYEARENS 564642023-02-16T12:05:00016 February 2023 12:05:00
[Table view]Other Unspec Reqmnt, 10 CFR 50.73(a)(1), Submit an LER 60 Day Notification for an Invalid Actuation of the Emergency Service Water System ENS 562832022-11-02T23:29:0002 November 2022 23:29:00 10 CFR 50.73(a)(1), Submit an LER 60-DAY Telephonic Notification - Invalid Specific System Actuation ENS 553452021-05-13T11:00:00013 May 2021 11:00:00 10 CFR 50.73(a)(1), Submit an LER Invalid Actuation of Containment Isolation Signal ENS 540832019-04-18T06:49:00018 April 2019 06:49:00 10 CFR 50.73(a)(1), Submit an LER Invalid Actuation of a Unit 2 Containment Isolation Logic Due to a Blown Fuse ENS 540142019-02-22T15:30:00022 February 2019 15:30:00 10 CFR 50.73(a)(1), Submit an LER Invalid Actuation of a Unit 1 Containment Isolation Logic Due to a Blown Fuse ENS 519522016-03-28T05:50:00028 March 2016 05:50:00 10 CFR 50.73(a)(1), Submit an LER Invalid Actuation of Inboard Isolation Logic ENS 485752012-10-13T23:41:00013 October 2012 23:41:00 10 CFR 50.73(a)(1), Submit an LER 60-Day Optional Telephonic Notification of Invalid Multiple System Actuations ENS 468832011-04-02T16:18:0002 April 2011 16:18:00 10 CFR 50.73(a)(1), Submit an LER Loss of Rps/Ups Power Supply ENS 459622010-04-03T01:56:0003 April 2010 01:56:00 10 CFR 50.73(a)(1), Submit an LER Overvoltage Condition Causes Reactor Protective System Actuation ENS 455182009-10-19T16:05:00019 October 2009 16:05:00 10 CFR 50.73(a)(1), Submit an LER Automatic Closure of Primary Containment Isolation Valves Due to Invalid Signal ENS 442602008-04-09T08:16:0009 April 2008 08:16:00 10 CFR 50.73(a)(1), Submit an LER 60-Day Optional Notification for Invalid Specified System Actuation ENS 433662007-03-19T06:20:00019 March 2007 06:20:00 10 CFR 50.73(a)(1), Submit an LER Invalid Specified System Actuations During Testing ENS 428302006-07-09T22:49:0009 July 2006 22:49:00 10 CFR 50.73(a)(1), Submit an LER Invalid Actuation of the B Esw Pump ENS 425722006-03-14T21:40:00014 March 2006 21:40:00 10 CFR 50.73(a)(1), Submit an LER Inadvertant Core Spray Pump Actuation ENS 416672005-03-06T19:07:0006 March 2005 19:07:00 10 CFR 50.73(a)(1), Submit an LER Invalid Safety System Actuation During an Outage ENS 408952004-05-26T20:22:00026 May 2004 20:22:00 10 CFR 50.73(a)(1), Submit an LER 60 Day Invalid Automatic Actuation Report: Containment Isoaltion Valves in More than One System 2023-02-16T12:05:00 | |
Retrieved from "https://kanterella.com/w/index.php?title=ENS_55345&oldid=3258697"