Final Deficiency Rept 55-84-15 Re Fabrication & Installation of Skewed Auxiliary Steel Connections W/O Approved Design Details.Initially Reported on 840629.Details Now in Design Drawings.Item Not Reportable Per 10CFR50.55(e)
ML20107K786
Person / Time
Site: Clinton Constellation icon.png
Issue date: 10/26/1984
From: Hall D
ILLINOIS POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
55-84-15, U-10215, NUDOCS 8411130278
Download: ML20107K786 (3)


Text

- - .

iw m, -

y I , _..

ILLIN0/8 POWER COMPANY = NE 130

~ -

((J U-10215

. CLINTON POWER STATION. P.O. BOX 678. CLINTON, ILLINOIS 61727 s-OctoberH26, 1984 Docket No.f50-461 Mr-. James.G. Keppler Regional Administrator 1 Region III U.S.-Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Potential.10CFR50.55(e) Deficiency 55-84-15:

Skewed Auxiliary Steel Connections

Dear Mr. Keppler:

On June 29, 1984, Illinois Power Company notified Mr. F.

Jablonski, NRC Region III, (Ref: IP Memorandum Y-20708 dated' June 29, 1984) of a potentially reportable deficiency concerning the fabrication and installation _of skewed auxiliary steel connections without the required approved design details. This initial notification was followed by one (1) interim report.

(Ref: IP letter, D. P. Hall to J. G. Keppler, U-10183, dated July 26, 1984). Illinois Power's investigation of the above matter is complete and has determined that the issue does not represent a reportable deficiency under the provisions of 10CFR50.55(e). This letter is submitted as a final report l regarding this potentially reportable deficiency. Attachment A l provides the details of our investigation.

We trust that this final report provides you sufficient background information to perform a general assessment of this potentially reportable deficiency and adequately describes our overall approach to resolve the issue.

Sincerely yours, i

j 8411130278 e41026 ~~

DR ADOCK 05000 ,

p,,

D. P. Hall Vice President RLC/cbc (NRC) cc: NRC Resident Office Director, Office of I&E, US NRC, Washington, DC 20555

-Illinois Department of Nuclear Safety INPO Records Center 007 3 y agg I(p() I g

~ - - . . . . .. . . .

ATTACHMENT A Illinois Power Company Clinton Power Station Docket No. 50-461 S abj ect : Potential 10CFR50.55(e) Deficiency 55-84-15:

Skewed Auxiliary Steel Connections

- Final Report Statement of Potentially Reoortable Deficiency (Withdrawn)/ Background The Clinton Power Station (CPS) Constructor generated 13 Field Change Requests (FCRs) which indicate that 37 cable tray support and 22 conduit support hangers were installed in Seismic Category I areas utilizing skewed auxiliary steel connections.

These skewed auxiliary steel connections were fabricated and installed without approved design details. The Constructor used a standard 90 , double angle connection detail from Sargent &

Lundy (S&L) drawing E05-1912 as a guide in bending the clip angles to the angle required to suit the configuration of the auxiliary steel in the field. The final as-built skewed con-nection, neither conforms to approved design details, nor to standard suggested skewed connection details of the AISC Manual.

The Constructor also fabricated and installed connections of two beans without approved design details, which were also investigated as a part of this potentially reportable condition.

Investigation Results/ Corrective Action Illinois Power has prepared and implemented an investigation plan to determine the extent of this problem at CPS. The investi-gation included:

1. A review was performed to identify all conduit and cable tray supports, utilizing skewed auxiliary steel connections s

that were installed without approved design details,

2. Forty-four (44) nonconformance reports (NCks) were generated to document those nonconforming or indeterminate connections identified by Item fl. All NCRs have been dispositioned in accordance with approved site procedures.
3. S&L analyzed and evaluated each as-built connection, iden-tified in Item 1, for adequacy to carry design loads, and
4. Baldwin Associates Quality Assurance Group evaluated this petential problem with respect to similar skewed connections which may have been installed by other disciplines.

Page 1 of 2

ATTACHMENT A (Continued)

5. NCRs 17544, 50984, and 50998 were generated to document the fabrication and installation of structural steel beam end connections without approved design details. These NCRs were resolved in accordance with approved site procedures.

To prevent the recurrence of the problem, S&L' issued Field Engineering-Change Notices (FECNs) 4986, 4996, 5098, 6001, 6003, 6004, 6005, 6224, and 6227 covering generic skewed connection details. These FECNs will be utilized for all future installations of cable trcy and conduit supports. To ensure that dkeWed Connections do not become a potential problem in other disciplines, it has been verified that standard skewed connection details are covered in design drawings.

Rcat Cause The E05-19XX series drawings contain standard details for auxiliary steel connections. In most cases, these details contain complete installation information, in other cases, notes on the drawings refer to the AISC Manual for necessary supplemental information to complete the installation. The drawings also contain a general detail for right angle connections which refercnces the AISC Manual for further details.

Since there was no detail for skewed connections, the Constructor felt that they could use the general detail, modifying it as necessary, utilizing the guidance provided in the AISC Manual.

Safety-Implications / Significance Illinois Power requested Sargent & Lundy (S&L) to evaluate the safety significance of the as-built skewed auxiliary steel '

connections. S&L letter, SLS-I-4710 dated August 21, 1984, documents the S&L evaluation. S&L has stated that the as-built skewed auxiliary steel connections would have no safety signifi-cance had the condition gone uncorrected. The structural steel beam end connections were also evaluated for safety signifi'cance.

The evaluation determined that the beam end connections, as installed, were adequate and sound for the loads / reactions posted on the design drawings.

Investigation of this potential ly reportable issue is complete. Illinois Power Company has reviewed and evaluated the findings of the investigation and has determined that no condi-tions. adverse to the safe operations of CPS were found. There-fore, this issue is considered to be not reportable under the provisions of 10CFR50.55(e).

1 Page 2 of 2