ML20082H963
| ML20082H963 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 03/31/1995 |
| From: | Hollomon T, Shell R TENNESSEE VALLEY AUTHORITY |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| NUDOCS 9504180003 | |
| Download: ML20082H963 (10) | |
Text
____.
)
nn Tennessee Valley Authonty. Post Othee Box 2000 Soddy-Damy. Tennessee 37379 April 10, 1995 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:
In the Matter of ) Docket Nos. 50-327 Tennessee Valley Authority ) 50-328 SEQUOYAH NUCLEAR PLANT (SQN) - MARCH 1995 MONTHLY OPERATING REPORT Enclosed is the March 1995 Monthly operating Report as required by SQN Technical Specification 6.9.1.10.
If you have any questions concerning this matter, ,e , call J. W. Proffitt at (615) 843-6651.
Sincerely, Yo R. H. Shell Manager SQN Site Licensing Enclosure cc See page 2 1SC052 $k 9504180003 950410 PDR ADOCK 05000327 M "7 i R _.._ ,_.PDR, ,$
-. . . . . - - . ., ~. - . . - . ..._ -..
1 U.S. Nuclear Regulatory commission I Page 2 l April 10,-1995 1 l
1
-cc'(Enclosure):
'I'PO Records Center Institute of Nuclear Power Operations 1 700 Galleria Parkway- -);
Atlanta,. Georgia.30339-5957 I
Mr. D. E. LaBarge, Project Manager U.S. Nuclear Regulatory Commission i i
One White Flint,-North 11555 Rockville. Pike.
Rockville,_ Maryland 20852-2739 i Mr.' Joseph Santucci, Manager l l . Advanced Reactor' Department, j l Electric Power Research Institute- -l 3340 Hillview Avenue l Palo Alto,' California 94304
]
NRC Resident Inspector i Sequoyah Nuclear Plant
, 2600 Igou Ferry Road .
- l. Soddy-Daisy, Tennessee 37379-3624 Regional Administration I U.S. Nuclear Regulatory Commission j office of Inspection and Enforcement l Region II 101 Marietta Street, NW, Suite 2900-Atlanta, Georgia 30323-2711 Regional Administrator U.S. Nuclear Regulatory Commission j Region II-
- l. -101 Marietta Street, NW, Suite 2900 l Atlanta, Georgia 30323-2711 l
t
. Mr..F. Yost,' Director Research Services Utility Data Institute 1200 G Street, NW, Suite 250 Washington, D.C. 20005 j .-
i i
l~ l l'
-l
i l.
l TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR PLANT ,
l MONTHLY OPERATING REPORT TO THE NUCLEAR REGULATORY COMMISSION ,
l MARCH 1995 I e I
UNIT 1 DOCKET NUMBER 50-327 P LICENSE NUMBER DPR-77 UNIT 2 DOCKET NUMBER 50-328 l LICENSE NUMBER DPR-79
, _ _ . . _ . . _ _ _ , _ _ . _ _ . . _ _ . . --.m..- ,
6 OPERATIONAL
SUMMARY
MARCH 1995 i
e UNIT 1 [
Unit 1 generated 718,250 megawatthours (MWh) (gross) electrical' power-during March with a capacity factor of 83.9 percent.
Unit i remained in Mode 4 at the beginning of March'as inspections .
continued on reactor vessel' level indicating system (RVLIS) compression fittings following a reactor coolant system leak at a_ compression fitting.
on a RVLIS line in the incore instrument room. The Unit 1 reactor was taken critical on March 3 at 2250 Eastern standard time (EST). Unit 1 was tiedLto.the grid at 1259 EST on March 4. Unit 1 reached 100 percent
-reactor power on March--14.
Unit 1 operated at near 100 percent reactor. power through the end of ,
March.
UNIT 2 Unit 2 generated 860,910.megawatthours (MWh) (gross) electrical power during March with a capacity factor of 101 percent. -
F i
1 I
l l
b i
! I l-l l
\
l
- s. :
l ,
o
.s .
AVERACE DAILY UNIT POWER LEVEL DOCKET NO.- 50-327' UNIT.No. One DATE:' 04-03-95 COMPLETED BY: T.'J.'Ho11omon- ' TELEPHONE: f615) 843-7528 1 MONTH: MARCH 1995 AVERAGE DAILY POWER LEVEL . AVERAGE' DAILY POWER LEVEL'. j D&1 'fMWe-Net) ]Zh1 (MWe-Net) ')
1 -28 11 7 - 1153 1
-33 '18 1156 l l
j; '3 -33 119 :1151' ,
.i j 4 81 20 1150-5 489 21 '1149
, 6 522 22 -1144- ,
i 4
l' 7 616 23. 1148-8 958 ;
2 4- '1152-i 9 990 25. 1155 10 1113 26 1154 l
l- 11 1134 27 1150 12 1132 28 ~1149 13 1130 29 1146 14 1152 30 1147 15 '1153 31' 1152 16 1153 i
l t i i
, , -. , . . -- , - -a_. - - . .
1
- AVERAGE DAILY UNIT POWER LEVEL 1 l DOCKET NO. 50-328' UNIT No. Two' DATE: 04-03-95 l
COMPLETED BYr T. J. Hollomon TELEPHONE: f615) 843-7528. 1 MONTH: MARCH 1995 I . AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL l I
Q&1 (MWe-Net)' QA1 (MWe-Net)'
j 1 -1142 17 3134
-2' 1138 18 1131 3 1139 19 1131 4 1142 20 1127 l'
! 5 1142 21 1122 -I 6 1141 22 1112' 7 1134 23 1113 8 1101 24 1117
. 9 1085 25 1119 l
j 10 1083~ 26 1119 l
11 1036 27 1121 12 1116 28 1123 13 1123 29 1124 14 1130 30 1120 l
15 1130 31 1117 16 1117 ]
l I
- l. .
OPERATING DATA REPORT DOCKET NO. _50-327 DATE 04/03/95 COMPLETED BY T. J. Ho' lomon
! TELEPHONE (615) 843-7528 l OPERATING STATUS l l Notes l l- 1. Unit Name: Seouovah Unit One l l l 2. Reporting Period: March 1995 l l l 3. Licensed Thermal Power (MWt): 3411.0 l l
- 4. Nameplate Rating (Gross MWe): 1220.6 l l
- 5. Design Electrical Rating (Net MWe): 1148.0 l l l 6. Maximum Dependable Capacity (Gross MWe): 1151.0 l l l 7. Maximum Dependable Capacity (Net MWe): 1111.0 l I
- 8. If Changes Occur in Capacity Ratings (Item Numbers 3 Through 7) Since Last Report, Give Reasons:
- 9. Power Level To Which Restricted, If Any (Net MWe): N/A
- 10. Reasons For Restrictions, If Any: N/A This Month Yr-to-Date Cumulative
- 11. Hours in Reporting Period 744 2.160 120.529
- 12. Number of Hours Reactor Was Critical 673.2 1.963.6 64 013 j
- 13. Reactor Reserve Shutdown Hours 0 0 0
- 14. Hours Generator On-Line 659.0 1.949.2 62.553.5
- 15. Unit Reserve Shutdown Hours 0 0 0 4
- 16. Gross Thermal Energy Generated (MWH) 2.060.933.9 6.432.797.6 204.008.794 l
- 17. Gross Electrical Energy Generated (MWH) 718.250 2.242.960 69.293.844 l
- 18. Net Electrical Energy Generated (MWH) 691.605 2.165.485 66.428.898
- 19. Unit Service Factor 88.6 90.2 51.9
- 20. Unit Availability Factor 88.6 90.2 51.9
- 21. Unit Capacity Factor (Using MDC Net) 83.7 90.2 49.6
- 22. Unit Capacity Factor (Using DER Net) 81.0 87.3 48.0
- 23. Unit Forced Outage Rate 11.4 9.8 36.0
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
The Unit 1 Cvele 7 refuelino outaae is scheduled to beain September 9,1995. with a duration of 51 days.
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup:
4 OPERATING DATA REPORT DOCKET NO. 50-328 DATE 04/03/95 l COMPLETED BY T. J. Ho11omon TELEPHONE (615) 843-7528 l
1 OPERATING STATUS j l Notes l
- 1. Unit Name: Seauovah Unit Two l l
- 2. Reporting Period: March 1995 l l
- 3. Licensed Thermal Power (MWt): 3411.0 l l l
- 4. Nameplate Ra*,ing (Gross MWe): 1220.6 l l
- 5. Design Electrical Rating (Net MWe): 1148.0 l l
- 6. Maximum Dependable Capacity (Gross We): 1146,0 l l.
- 7. Maximum Dependable Capacity (Net HWe): 1106.0 l l
- 8. If Changes Occur in Capacity Ratings (Item Numbers 3 Through 7) Since Last Report, Give Reasons:
- 9. Power Level To Which Restricted, If Any (Net HWe): N/A
- 10. Reasons For Restrictions, If Any: N/A This Month Yr-to-Date Cumulative
- 11. Hours in Reporting Period 744 2.160 112,489
- 12. Number of Hours Reactor Was Critical 744.0 2.137.7 66.494
- 13. Reactor Reserve Shutdown Hours 0 0 0
- 14. Hours Generator On-Line 744.0 2.098.7 , 64.808.4
- 15. Unit Reserve Shutdown Hours 0 0 0
- 16. Gross Thermal Energy Generated (HWH) 2.500.844.1 6.974.737.3 204.502.200
- 17. Gross Electrical Energy Generated (MWH) 860.910 2.398.403 69.406.012
- 18. Net Electrical Energy Generated (MWH) 832.002 2.314.039 66.428.221
- 19. Unit Service Factor 100.0 97.2 57.6
- 20. Unit Availability Factor 100.0 97.2 57.6 j
, 21. Unit Capacity Factor (Using HDC Net) 101.1 96.9 53.4 l
- 22. Unit Capacity Factor (Using DER Net) 97.4 93.3 51.4 l
- 23. Unit Forced Outage Rate 0.0 2.8 34.4 ;
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each): l Unit 2 is scheduled to becin a forced maintenance on April 6.1995. with a duration of I 16 days.
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup
i I
,1 -
DOCKET NO: 50-327 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME: One ,
DATE: 04/01/95
- REPORT MONTH: March 1995 COMPLETED BY:T. O. Ho' lomon TELEPHONE:(615) 843-7528 Method of Licensee Cause and Corrective Duration Shutting Down Event Systy Compgnent Action to
- No. .Date Type (Hours) Reason Reactor Report No. Code Code Prevent Recurrence. "
1 950301 F 84.98- A 1 50-327/95002 AB N/A Unit I remained in Mode 4 at the beginning of March as inspections continued on RVLIS compression fittings. The Unit I reactor was taken critical on March 3 and was tied to the grid at 1259 EST on March 4.
2 Reason: 3 4 I:F Forced Method: Exhibit G-Instructions S: Scheduled ' a-tquipment Failure (Explain) 1-Manual -for Preparation of Data B-Maintenance or.. Test 2-Manual Scram - Entry sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restruction 4-Continuation of Existing Outage - '(NUREG-1022)
E-Operator Training and License' Examination '5-Reduction
'F-Administrative. 9-Other~
5 G-Operational Error (Explain) Exhibit I-Same Source H-Other (Explain)
DOCKET NO: 50-328 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME: Two *'
DATE: ('4/01/95 REPORT MONTH: March 1995 COMPLETED BY:T. . . Ho' lomon
-TELEPHONE:(61b) 843-7528-Method of Licensee Cause and Corrective Duration Shutting Down Event Systy Comppent Action to-
- No. Date Type (Hours) Reason Reactor Report No. Code Code Prevent Recurrence There were no outages or power ~
reductions of greater than 20 percent to report during March.
1 2 Reason: 3 Method: 4 I:F Forced Exhibit G-Instructions.
5: Scheduled A-Equipment Failure (Explain) 1-Manual 'for Preparation of Data-B-Maintenance or Test 2-Manual Scram - Entry sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) Flie D-Regulatory Restruction 4-Continuation of Existing Outage . -(NUREG-1022)
E-Operator Training and License Examination 5-Reduction F-Administrative 9-Other S
G-Operational Error (Explain) Exhibit I-Same Source H-Othe'r (Explain)
_