MONTHYEARML0815405932008-09-0909 September 2008 (MNGP) - Review of Licensee'S 3-Month Response to Generic Letter 2008-01 (Tac No. MD7847) Project stage: Approval L-MT-08-063, Nine-Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2008-10-14014 October 2008 Nine-Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Other ML0919504162009-07-0606 July 2009 Supplemental Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Supplement ML0921101112009-07-30030 July 2009 Draft RAI on Response to GL 2008-01 Project stage: Draft RAI ML1030602072010-11-0101 November 2010 Draft RAI on the Licensee'S Submittals in Response to Generic Letter 2008-01 Project stage: Draft RAI L-MT-11-018, Response to Request for Additional Information Related to Generic Letter 2008-012011-05-20020 May 2011 Response to Request for Additional Information Related to Generic Letter 2008-01 Project stage: Response to RAI ML1117106372011-06-23023 June 2011 Closeout of Generic Letter 2008-01 Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems TAC MD7847 Project stage: Other L-MT-15-048, License Amendment Request: Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process2015-07-15015 July 2015 License Amendment Request: Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process Project stage: Request 2009-07-06
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24022A0212024-01-20020 January 2024 NRR E-mail Capture - Monticello - Request for Additional Information ISI RR-002 Alternative to Use IWB-2500(f) ML23353A0742023-12-19019 December 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Proposed Alternative VR-09, Modifications to OMN-17 ML23348A3462023-12-14014 December 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of License Amendment Request to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML23268A0292023-09-20020 September 2023 SLRA - Requests for Confirmation of Information - Set 2 - Email from Marieliz Johnson to Shawn Hafen ML23249A2092023-09-0606 September 2023 NRR E-mail Capture - Action: Opportunity to Review and Comment on a New NRC Information Collection, 10 CFR Part 50.55a, Codes and Standards (3150-XXXX) ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23237A4822023-08-25025 August 2023 SLRA - Request for Additional Information - Set 3 - Email from Marieliz Johnson to Shawn Hafen ML23228A1212023-08-16016 August 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Request VR-11 for MO-2397 ML23227A2182023-08-15015 August 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Request RR-002 to Use IWB-2500(f) ML23219A1072023-08-0707 August 2023 SLRA - Requests for Additional Information - Set 2 - Email from Marieliz Johnson to Shawn Hafen ML23200A3502023-07-19019 July 2023 SLRA - Requests for Additional Information - Set 1 - Email from Marieliz Johnson to Christopher Domingos ML23172A1122023-06-21021 June 2023 SLRA - Requests for Confirmation of Information - Set 1 - Email from Marieliz Johnson to Christopher Domingos ML23054A3322023-02-23023 February 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Relief Request to Use Later Edition of ASME BPV Code, Section XI, for ISI Program Code of Record ML23053A1362023-02-13013 February 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Relief Request to Use Later Edition of ASME BPV Code, Section XI, for Cisi Program ML23017A2222023-01-13013 January 2023 Verbal Authorization of Proposed Alternative PR-08 Regarding Inservice Testing Requirements of Certain High Pressure Coolant Injection System Components (EPID L-2022-LLR-0088) (Email) ML23004A1982023-01-0404 January 2023 NRR E-mail Capture - Draft Request for Additional Information Monticello Nuclear Generating Plant Request Pr 08, HPCI Pump Quarterly Testing ML23012A2102022-07-26026 July 2022 Letter Submitting Monticello Outline Package ML22181A1962022-06-24024 June 2022 NRR E-mail Capture - Draft RAI Monticello Alternative VR-08 ML22175A1602022-06-24024 June 2022 NRR E-mail Capture - RAI Monticello Fuel Oil Storage Tank Inspection ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22123A2822022-05-0303 May 2022 NRR E-mail Capture - Request for Additional Information Monticello Alternative VR-10, EFCV Testing Frequency ML22101A0712022-04-11011 April 2022 NRR E-mail Capture - Monticello - Acceptance of Requested Licensing Action License Amendment Request to Revise TS 3.6.1.8 Residual Heat Removal (RHR) Drywell Spray Header and Nozzle Surveillance Frequency ML22089A1302022-03-30030 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Related Excess Flow Check Valve Testing Frequency ML22082A1812022-03-23023 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of VR-08 Alternative to Adopt ASME OM Code Case OMN-28 ML22075A2612022-03-16016 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of VR-07 Alternative Related to MOV Testing Per ASME OM Code Case OMN-26 ML22067A2032022-03-0808 March 2022 Audit Plan to Support Review of an Amendment to Transition to Atrium 11 Fuel (Redacted) ML22011A0642022-01-11011 January 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Support Diesel Generator Fuel Oil Storage Tank Inspection ML22005A3612022-01-0505 January 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Pump Vibration Testing Per ASME OM Code Case OMN-22 ML21347A0082021-12-10010 December 2021 NRR E-mail Capture - Monticello and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested License Amendment Standard Emergency Plan and Consolidated Emergency Operations Facility ML21330A0382021-11-18018 November 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related RHR and RHRSW Pump Testing ML21286A7882021-10-0606 October 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Residual Heat Removal Heat Exchanger Flow Control Valve Stroke Timing ML21256A1892021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Testing the Control Rod Drive Scram Discharge Header Check Valves ML21256A1862021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to HPCI and RCIC Pump Testing ML21256A1882021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Vibration Testing Range for the Sblc Pumps ML21253A2002021-09-10010 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Pressure Isolation Valve Testing ML21252A0132021-08-31031 August 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Adopt Advanced Framatome Methodologies ML21130A3022021-05-0707 May 2021 Initial and Final Written 10 CFR 21 Notification for GE Hitachi Numac Prnm System ML21110A7042021-04-20020 April 2021 Response: Monticello Nuclear Plant Outage - Covid Risk to On-Site Employees ML21084A2522021-03-24024 March 2021 NRR E-mail Capture - Revised Review Schedule for Monticello TSTF-505 (EPID L-20200LLA-0062) ML21068A2772021-03-0909 March 2021 NRR E-mail Capture - Monticello TSTF-505, Request for Additional Information ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information ML20342A1782020-12-0707 December 2020 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-564 Safety Limit MCPR ML20302A1972020-10-26026 October 2020 NRR E-mail Capture - Monticello Request for Additional Information TSTF-505 License Amendment Request ML20289A1072020-10-0606 October 2020 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-582 Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements (EPID L-2020-LLA-0209 ML20191A0252020-07-0101 July 2020 NRR E-mail Capture - Draft Request for Additional Information Monticello Alternative Request RR-016 Related to H8, H9, and H 10 Weld Examinations ML20120A0272020-04-28028 April 2020 NRR E-mail Capture - Request for Additional Information Monticello Long Term Steam Dryer Inspection Plan ML20099F1292020-04-0606 April 2020 E-mail to Licensee for Monticello Lr Phase 4 RFI ML20077L4632020-03-17017 March 2020 NRR E-mail Capture - Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 -Acceptance of Requested Licensing Action Request to Adopt TSTF-529 ML20064C5352020-03-0404 March 2020 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Revise the Previously Authorized Alternative in RR-008 for the H8 and H9 Welds 2024-01-20
[Table view] |
Text
Accession No. ML103060207 From: Tam, Peter Sent: Monday, November 01, 2010 5:36 PM To: Salamon, Gabor; Loeffler, Richard A.
Cc: Woodyatt, Diana; Pascarelli, Robert; Ulses, Anthony
Subject:
Monticello - Draft RAI on response to Generic Letter 2008-01 re. gas accumulation in ECCS etc. (TAC MD7847)
Gabe:
By letters dated April 11, 2008 (Accession No. ML081020695), October 14, 2008 (Accession No. ML082880662), and August 14, 2009, (Accession No. ML92290180),
the licensee submitted information in response to Generic Letter 2008-01 Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, for Monticello Nuclear Generating Plant. On the basis of the provided information, the NRC staff has concluded that additional information is needed to determine that the licensee has acceptably demonstrated that the subject systems are in compliance with the current licensing and design bases and applicable regulatory requirements, and that suitable design, operational, and testing control measures are in place for maintaining this compliance as stated in Generic Letter (GL) 2008-01.
You may accept this e-mail as formal RAI, and respond to it by December 1, 2010 (30 days from today). Alternatively, you may request to hold a conference call with the NRC staff to discuss the following questions, and agree on a target date by which you will provide a formal response.
Guidance on Nuclear Regulatory Commission (NRC) staff expectations is provided by Reference 1, which is generally consistent with Nuclear Energy Institute (NEI) guidance provided to the industry in Reference 2 as clarified in later NEI communications. The NRC staff recommends that the licensee consult Reference 1 when responding to the following questions:
- 1. In the Licensing Basis evaluation section, the licensee stated that Technical Specification Surveillance Requirement 3.5.1.1 does not address emergency core cooling system (ECCS) suction piping, high pressure ECCS piping, decay heat removal, or containment spray piping. What actions are being taken to ensure that the areas not addressed in the TS SR are operable?
- 2. Industry guidance on acceptable void criteria for suction piping has been updated since submittal of Monticellos 9-month response (see Reference 8). Please provide updated void acceptance criteria, if applicable.
- 3. Training was not identified in the GL but is considered to be a necessary part of applying procedures and other activities when addressing the issues identified in the GL. Please briefly discuss training.
Peter S. Tam, Senior Project Manager (for D.C. Cook and Monticello)
Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Tel. 301-415-1451 REFERENCES
- 1. Ruland, William H., Preliminary Assessment of Responses to Generic Letter 2008-01, Managing Gas Accumulation in emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, and Future NRC Staff Review Plans, NRC letter to James H. Riley, Nuclear Energy Institute, ML091390637, May 28, 2009.
- 2. Riley, James H., Generic Letter (GL) 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Contain Spray Systems Evaluation and 3 Month Response Template, Letter to Administrative Points of Contact from Director, Engineering, Nuclear Generation Division, Nuclear Energy Institute, Enclosure 2, Generic Letter 2008-01 Response Guidance, March 20, 2008.
- 3. Case, Michael J., NRC Generic Letter 2008-01: Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Letter from Director, Division of Policy and Rulemaking, Office of Nuclear Regulation, NRC, ML072910759, January 11, 2008.
- 4. Sawatzke, Bradley J., Nuclear Management Company, LLC; Monticello Nuclear Generating Plant, Generic Letter 2008-01: Three-Month Response to Generic Letter 2008-01, Letter to Document Control Desk, NRC, from Plant Manager, Monticello Nuclear Generating Plant, ML081020695, April 11, 2008.
- 5. OConnor, Timothy J., Xcel Energy; Monticello Nuclear Generating Plant, Nine-Month Response to NRC Generic Letter 2008-01,Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems (TAC No. 7847), Letter to Document Control Desk, NRC, from Site Vice President, Monticello Nuclear Generating Plant, ML082880662, October 14, 2008.
- 6. OConnor, Timothy J., Xcel Energy; Monticello Nuclear Generating Plant, Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-01, Letter to Document Control Desk, NRC, from Site Vice President, Monticello Nuclear Generating Plant, ML092290180, August 14, 2009.
- 7. Warren C. Lyon, U.S. Nuclear Regulatory Commission, Revision 2 to NRC Staff Criteria for Gas Movement in Suction Lines and Pump Response to Gas, ML090900136, March 26, 2009.
- 8. Guidance To NRC/NRR/DSS/SRXB Reviewers for Writing TI Suggestions for the Region Inspections, ML102300053, August 18, 2010.
E-mail Properties Mail Envelope Properties (0A64B42AAA8FD4418CE1EB5240A6FED1219553AC85)
Subject:
Monticello - Draft RAI on response to Generic Letter 2008-01 re. gas accumulation in ECCS etc. (TAC MD7847)
Sent Date: 11/01/2010 5:35:53 PM Received Date: 11/01/2010 5:35:00 PM From: Tam, Peter Created By: Peter.Tam@nrc.gov Recipients:
Gabor.Salamon@xenuclear.com (Salamon, Gabor)
Tracking Status: None Richard.Loeffler@xenuclear.com (Loeffler, Richard A.)
Tracking Status: None Diana.Woodyatt@nrc.gov (Woodyatt, Diana)
Tracking Status: None Robert.Pascarelli@nrc.gov (Pascarelli, Robert)
Tracking Status: None Anthony.Ulses@nrc.gov (Ulses, Anthony)
Tracking Status: None Post Office:
HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 28622 11/01/2010 Options Expiration Date: