Category:Letter type:ND
MONTHYEARND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0592, ITAAC Closure Notification on Completion of 2.7.06.03.i (Index Number 726)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of 2.7.06.03.i (Index Number 726) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) ND-23-0581, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) ND-23-0486, ITAAC Closure Notification on Completion of ITAAC 2.2.01.11a.iv (Index Number 117)2023-07-11011 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.01.11a.iv (Index Number 117) ND-23-0559, CFR26.719(c)(1) 30-Day Report for a Blind Sample Analysis Error2023-07-11011 July 2023 CFR26.719(c)(1) 30-Day Report for a Blind Sample Analysis Error ND-23-0443, ITAAC Closure Notification on Completion of ITAAC 2.3.10.07a.ii (Index Number 444)2023-07-0808 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.10.07a.ii (Index Number 444) ND-23-0183, ITAAC Closure Notification on Completion of ITAAC Item 2.3.11.03b (Index Number 454)2023-07-0808 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.11.03b (Index Number 454) 2024-02-01
[Table view] |
Text
Michael J. Yox 7325 River Road Regulatory Affairs Director Waynesboro, GA 306010 Southern Nuclear Vogtle 3& 4 706-848-6459 tel myox@southernco.com JUL 3 0 2019 Docket Nos.: 52-025 52-026 ND-19-0624 10CFR 52.99(c)(3)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.6.03.04a [Index Number 6011 Ladies and Gentlemen:
Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of June 10, 2019, Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses and Acceptance Criteria (ITAAC) Item 2.6.03.04a
[Index Number 601] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing ITAAC 2.6.03.04a [Index Number 601]. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.
This notification is informed by the guidance described in NEI-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed.
All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).
This letter contains no new NRC regulatory commitments.
If there are any questions, please contact Tom Petrak at 706-848-1575.
Respectfully submitted.
Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.03.04a [Index Number 601]
MJY/DJG/sfr
U.S. Nuclear Regulatory Commission ND-19-0624 Page 2 of 3 To:
Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)
Mr. D. L. McKlnney (w/o enclosures)
Mr. M. D. Meier(w/o enclosures)
Mr. D. H. Jones(w/o enclosures)
Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Vox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:
Nuclear Reoulatorv Commission Mr. W. Jones (w/o enclosures)
Mr. F. D. Brown Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. V. Hall Mr. G. Armstrong Ms. T. Lamb Mr. M. Webb Mr. T. Fredette Mr. C. Weber Qqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen
U.S. Nuclear Regulatory Commission ND-19-0624 Page 3 of 3 Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Oriani(w/o enclosures)
Mr. D. C. Durham (w/o enclosures)
Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.
Mr. 8. Roetger, Georgia Public Sen/ice Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham
U.S. Nuclear Regulatory Commission ND-19-0624 Page 1 of 5 Southern Nuclear Operating Company ND-19-0624 Enclosure Vogtle Electric Generating Plant(VEGP)Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.03.04a [Index Number 601]
U.S. Nuclear Regulatory Commission ND-19-0624 Page 2 of 5 TAAC Statement Design Commitment 4.a) The IDS provides electrical independence between the Class 1E divisions.
Inspections/Tests/Analvses Testing will be performed on the IDS by providing a simulated test signal in each Class 1E division.
Acceptance Criteria A simulated test signal exists at the Class 1E equipment identified in Table 2.6.3-1 when the assigned Class 1E division is provided the test signal.
ITAAC Completion Description Testing is performed on the Class 1E equipment identified in the VEGP Unit 3 and Unit 4 COL Appendix C Table 2.6.3-1 (Attachment A)to demonstrate the Class 1E do and Uninterruptible Power Supply System (IDS) provides electrical independence between the Class 1E divisions.
This ITAAC performs testing on the IDS by providing a simulated test signal in each Class 1E division.
Testing is performed in accordance with the Unit 3 and Unit 4 component test package work orders(References 1 and 2)for IDS which ensures IDS provides electrical independence between the Class IE divisions. Testing verifies electrical independence of the divisions of Class 1E IDS by energizing a single division and verifying the presence or absence of power at all division's components being tested, then the single division is de-energized. This same sequence is repeated until all division components identified in Table 2.6.3-1 as being Class IE are verified to be energized/de-energized when the appropriate power source is cycled.
Unit 3 and Unit 4 component test package work orders (References 1 and 2, respectively) confirm that a simulated test signal exists at the Class 1E equipment identified in Table 2.6.3-1 when the assigned Class 1E division is provided the test signal.
References 1 and 2 are available for NRC inspection as part of Unit 3 and Unit 4 ITAAC Completion Packages(References 3 and 4).
List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.
U.S. Nuclear Regulatory Commission ND-19-0624 Page 3 of 5 References(available for NRG inspection)
- 1. SNC921217,"IDS Component Power Verification Test- ITAAC:SV3-2.6.03.04a"
- 2. SNCXXXXXX,"IDS Component Power Verification Test- ITAAC:SV4-2.6.03.04a"
- 3. 2.6.03.04a-U3-CP-Rev 0, ITAAC Completion Package
- 4. 2.6.03.04a-U4-CP-Rev 0, ITAAC Completion Package
- 5. NEI 08-01,"Industry Guideline for tfie ITAAC Closure Process Under 10 CFR Part 52"
U.S. Nuclear Regulatory Commission ND-19-0624 Page 4 of 5 Attachment A Equipment Name
Division A 250 Vdc 24-Hour Battery Bank IDSA-DB-1 Division B 250 Vdc 24-Hour Battery Bank 1 IDSB-DB-1 Division B 250 Vdc 72-Hour Battery Bank 2 IDSB-DB-2 Division C 250 Vdc 24-Hour Battery Bank 1 IDSC-DB-1 Division C 250 Vdc 72-Hour Battery Bank 2 IDSC-DB-2 Division D 250 Vdc 24-Hour Battery Bank IDSD-DB-1 Spare 250 Vdc Battery Bank IDSS-DB-1 Division A 24-Hour Battery Cfiarger 1 IDSA-DC-1 Division B 24-Hour Battery Charger 1 IDSB-DC-1 Division B 72-Hour Battery Charger 2 IDSB-DC-2 Division C 24-Hour Battery Charger 1 IDSC-DC-1 Division C 72-Hour Battery Charger 2 IDSC-DC-2 Division D 24-Hour Battery Charger 1 IDSD-DC-1 Spare Battery Charger 1 IDSS-DC-1 Division A 250 Vdc Distribution Panel IDSA-DD-1 Division B 250 Vdc Distribution Panel IDSB-DD-1 Division C 250 Vdc Distribution Panel IDSC-DD-1 Division D 250 Vdc Distribution Panel IDSD-DD-1 Division A 120 Vac Distribution Panel 1 IDSA-EA-1 Division A 120 Vac Distribution Panel 2 IDSA-EA-2 Division B 120 Vac Distribution Panel 1 IDSB-EA-1 Division B 120 Vac Distribution Panel 2 IDSB-EA-2 Division B 120 Vac Distribution Panel 3 IDSB-EA-3 Division C 120 Vac Distribution Panel 1 IDSC-EA-1 Division C 120 Vac Distribution Panel 2 IDSC-EA-2 Division C 120 Vac Distribution Panel 3 IDSC-EA-3 Division D 120 Vac Distribution Panel 1 IDSD-EA-1 Division D 120 Vac Distribution Panel 2 IDSD-EA-2 Division A Fuse Panel 4 IDSA-EA-4 IDSA Battery Monitor Fuse Panel IDSA-EA-5 Division B Fuse Panel 4 IDSB-EA-4 Division B Fuse Panel 5 IDSB-EA-5 Division B Fuse Panel 6 IDSB-EA-6 IDSB Battery Monitor Fuse Panel IDSB-EA-7 IDSB Battery Monitor Fuse Panel IDSB-EA-8 Division C Fuse Panel 4 IDSC-EA-4 Division C Fuse Panel 5 IDSC-EA-5 Division C Fuse Panel 6 IDSC-EA-6 IDSC Battery Monitor Fuse Panel IDSC-EA-7 IDSC Battery Monitor Fuse Panel IDSC-EA-8 Division D Fuse Panel 4 IDSD-EA-4 Excerpt from COL Appendix C Table 2.6.3-1
U.S. Nuclear Regulatory Commission ND-19-0624 Enclosure Page 5 of 5 Attachment A(Cent.)
Equipment Name
IDSD Battery Monitor Fuse Panel IDSD-EA-5 IDSS Battery Monitor Fuse Panel IDSS-EA-1 Division A Fused Transfer Switch Box 1 IDSA-DF-1 Division B Fused Transfer Switch Box 1 IDSB-DF-1 Division B Fused Transfer Switch Box 2 IDSB-DF-2 Division C Fused Transfer Switch Box 1 IDSC-DF-1 Division C Fused Transfer Switch Box 2 IDSC-DF-2 Division D Fused Transfer Switch Box 1 IDSD-DF-1 Spare Fused Transfer Switch Box 1 IDSS-DF-1 Division A 250 Vdc MCC IDSA-DK-1 Division B 250 Vdc MCC IDSB-DK-1 Division C 250 Vdc MCC IDSC-DK-1 Division D 250 Vdc MCC IDSD-DK-1 Division A 250 Vdc Switchboard 1 IDSA-DS-1 Division B 250 Vdc Switchboard 1 " IDSB-DS-1 Division B 250 Vdc Switchboard 2 IDSB-DS-2 Division C 250 Vdc Switchboard 1 IDSC-DS-1 Division C 250 Vdc Switchboard 2 IDSC-DS-2 Division D 250 Vdc Switchboard 1 IDSD-DS-1 Division A Regulating Transformer IDSA-DT-1 Division B Regulating Transformer IDSB-DT-1 Division C Regulating Transformer IDSC-DT-1 Division D Regulating Transformer IDSD-DT-1 Division A 24-Hour Inverter 1 IDSA-DU-1 Division B 24-Hour Inverter 1 IDSB-DU-1 Division B 72-Hour Inverter 2 IDSB-DU-2 Division C 24-Hour Inverter 1 IDSC-DU-1 Division C 72-Hour Inverter 2 IDSC-DU-2 Division D 24-Hour Inverter 1 IDSD-DU-1 Spare Battery Termination Box IDSS-DF-3 Excerpt from COL Appendix C Table 2.6.3-1