NRC Generic Letter 79-53, ATWS

From kanterella
Revision as of 17:22, 18 February 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

text

GL79053

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555

Gentlemen:

This past March, the NRC transmitted to you a copy of Volume 3 of NUREG-0460, "Anticipated Transients Without Scram for Light Water Reactors" (ATWS) and a copy of an NRC letter that was sent this past February to each of the four nuclear reactor vendors. The letters to the vendors contained requests for information needed to perform generic analyses related to ATWS.

As we pointed out in our March letters, the generic analyses we requested were intended to confirm that the modifications proposed by the NRC staff for various classes of LWR designs would in fact accomplish the degree of ATWS prevention and mitigation described by the staff in its report. We also pointed out that we had chosen to work directly with the vendors in obtaining this information in an effort to conserve both NRC and industry resources. We requested that utilities cooperate with the vendors in performing the requested analysts.

Shortly after sending the letters to the vendors, the NRC Staff met with representatives of each of the NSSS vendors and many Utility representa-

tives in Bethesda on March 1. 1979. The meeting was called to discuss the "early verification" approach in which we planned to use generic analyses as the basis for rulemaking. We hoped thereby to avoid costly and unnecessary repetitive analysis for individual plants. At the meeting, a tentative schedule was agreed to for generic analyses for each class of plants to be provided in three separate packages to be submitted May 1, September 1, and December 1, 1979.

.

Immediately following the March 1 meeting, the NRC staff met separately with each of the NSSS vendors and agreements were made as to the minimum information to be supplied in the May 1 package. Also, as noted above, copies of the ATWS staff report and the generic analyses questions were transmitted to the utilities.

On March 28, 1979 the Three Mile Island accident occurred. Because of the heavy expenditure of NRC resources required for Three Mile Island related activities, essentially no staff effort was applied to the ATWS issue for three months or so following the accident. There was also a substantial reduction in effort on the part of the PWR industry during that period, and some reduction for BWRs.

In June, 1979. the NRC Office of Nuclear Reactor Regulation was temporarily reorganized. Within this interim organization a group was assigned under the direction of S. Hanauer to work on the 19 Unresolved Safety Issues as designated by the Commission and reported to Congress this past January in NUREG-0510. ATWS is one of these 19 issues.

A preliminary NRR Staff review suggested that, for PWRs, the Three Mile Island accident raised new questions with regard to the appropriateness and adequacy of the resolution of ATWS as proposed by the Staff in Volume 3 of NUREG-0460. For BWRs, the staff has concluded that the technical impact of Three Mile Island was minimal and that the completion and review of the generic analyses for BWRs as specified in March should proceed as expeditiously as possible.

A meeting was held in Bethesda on July 251 1979 to discuss, with representa-

tives of PWR utilities and designers, considerations arising from the Three Mile Island accident that might be relevant to ATWS. For your information, a copy of the staff minutes of that meeting is attached as Enclosure 1. As can be seen from the minutest at the meeting the staff:

a) Reiterated that ATWS is still believed by the staff to be a serious safety concern and that future protection should be provided. We stated that we art unwilling to wait another year to make progress on ATWS. b) Expressed some general and specific technical concerns raised by the Three Mile Island accident with regard to the ATWS resolution proposed in Volume 3 of NUREG-0460.


c) Asked the industry to provide in writing, within 30 days of the meeting date, its preliminary assessment of the Three Mile Island impact on ATWS, the scope of effort now foreseen to resolve TMI issues, and a realistic schedule for providing the needed ATWS information. This would include both the March request and the TMI-related analyses.

.

Subsequent to the July 25 meeting, we have met with representatives of the four NSSS vendors and of soft Utility/Owners. We have met with GE to discuss the scope of the remaining generic analysis information to be supplied for BWR 4/5/6's. We have also met with representatives of the GE BWR/3 Owners, B&W, BSW ATWS Owners Group, W, W ATWS Owners Group, and CE. At all these meetings, we considered further required inforation and the schedule for its submittal.

We have now received letters (See the list in Enclosure 2, attached) from the various groups describing the information to be furnished and projected schedules, On the basis of our review of these letters and meetings with the industry representatives, we perceive that the projected responses in several casts would not address several questions in our February 15 letter. In particular, several items art lacking that we will need to justify acceptance of the hardware approaches of NUREG 0460 Vol 3 rather than using the design basis accident approach.

I am determined to submit a proposed ATWS rule to the Commission for both PWRs and BWRs early In 1980. The type and content of the rule we will propose will depend critically upon the types and content of the information available to the staff. This will, of course, include whatever responses are actually provided by the industry in response to the questions attached to the February 15 staff letter, the March meetings, and the Three Mile Island related concerns as discussed in the July 25 and subsequent meetings.

I still believe that it is possible for the early verification generic analysis program to provide an acceptable resolution of the ATWS issue and that this is the way to achieve resolution with the least possible expenditure of NRC and industry resources. However, I want to reiterate that the success of this approach depends on whether or not all of the information necessary for the suff to confirm that its proposed ATWS modifications provide an acceptable level of protection, for all plants, is provided by the industry.

I strongly encourage you to join or form Utility/Owners Groups, if you have not already done so, and provide the resources necessary to supply the needed technical information pertaining to your plants, either operating or under construction. It would further reduce the impact on the industry as well as the staff resources if the ATWS effort coordination and the review role is performed by one industry group.

If you have additional questions on the generic analysis early verification program discussed in this letter, please contact Mr. Ashok Thadani, (301-492-7341).

Sincerely,

H. R. Denton, Director Office of Nuclear Reactor Regulation

Enclosures:

1. NRC-Industry ATWS Meeting Summary dtd 7/25/79
2. List of letters from Industry on Content of Report Submittals