MONTHYEARML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23156A3042023-05-31031 May 2023 Acceptance of Requested Licensing Action Amendment Request to Remove Period of Applicability from Pressure Temperature Limits and Low Temperature Over Pressure Protection Curves ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23066A1892023-03-0303 March 2023 OEDO-22-00419: Email Dated 3-3-2023 to Petitioner on Seabrook ASR Petition ML23066A0892023-02-24024 February 2023 OEDO-22-00419 - Email Dated 02/24/2023 to Petitioner on Seabrook Unit 1 ASR Petition ML23020A9392023-01-19019 January 2023 Acceptance of Requested Licensing Action Amendment Request to Revise Cooling Tower Service Water Loop or Cell Requirements (EPID L-2022-LLA-0183) (Email) ML23011A3082023-01-11011 January 2023 Request for Additional Information Regarding Relief Request 4RA-22-001 (L-2022-LLR-0074) ML22341A0012022-12-0606 December 2022 Acceptance of Requested Licensing Action Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) ML22333A7452022-11-22022 November 2022 OEDO-22-00419 - Email: C-10 Response on PRB Initial Assessment - C-10 Petition on Seabrook ASR Concrete Degradation ML22287A1472022-10-13013 October 2022 2.026 Petition Screen-in Email ML22228A0552022-08-15015 August 2022 Request for Additional Information Steam Generator Tube Inspection Report Review ML22200A1082022-07-19019 July 2022 Acceptance Review for TSTF-577 Amendment ML22153A4152022-05-31031 May 2022 Request for Additional Information Re 120V Inverter LAR from TS Branch - Final ML22116A2442022-04-26026 April 2022 Acceptance of Requested Licensing Action Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage ML22048B5522022-02-17017 February 2022 LTR-22-0010 Reply to Geoff Gilbert Email Concern About Seabrook Station Concrete Degradation ML22062B6642022-02-0707 February 2022 Request for Additional Information 120V Inverter LAR from the Electrical Branch ML22063A0002022-01-25025 January 2022 Requests for Additional Information from Risk Branch Regarding 120V Inverter LAR ML22020A2542022-01-20020 January 2022 LTR-22-0010 Geoff Gilbert, E-mail Concern About Seabrook Station Concrete Degradation ML21097A2512021-04-0707 April 2021 Request for Additional Information Regarding Steam Generator Tube Inspection Report Review for RFO 20 (EPID L-2020-LRO-0066) (Email) ML21054A0482021-02-23023 February 2021 Request for Additional Information Regarding Heat Flux Hot Channel Requirement Amendment Request ML20343A0942020-12-0303 December 2020 Request for Additional Information Regarding Seabrook (COVID-19) Part 73 Force-on-Force Exemption Request (L-2020-LLE-0219) ML20273A2812020-09-22022 September 2020 Acceptance of Requested Licensing Action License Amendment Request to Resolve Non-Conservative Heat Flux Hot Channel Factor Requiments ML20258A1502020-09-14014 September 2020 Request for Additional Information Related to Seabrook License Amendment Request Regarding One-Time Change to the AC Sources Operating TS ML20260H4932020-09-11011 September 2020 NRR E-mail Capture - Comanche Peak - Acceptance of Requested Licensing Action - Request to Use Later Code Edition of ASME OM Code ML20230A2962020-08-14014 August 2020 Acceptance of Requested Licensing Action License Amendment Request to Allow a One-Time Change to the AC Sources Operating TS ML20167A1842020-06-11011 June 2020 Request for Additional Information Related to Seabrook License Amendment Request Regarding TSTF-411 and TSTF-418 (L-2019-LLA-0237) ML20124A0012020-05-0101 May 2020 Cancellation of Call with Seabrook on Steam Generator Tube Inspections ML20114E1592020-04-23023 April 2020 Email and Request for Additional Information Related to Seabrook License Amendment Request to Degraded Voltage Time Delay Setpoint (L-2020-LLA-0012) ML20101N0932020-04-10010 April 2020 Acceptance of Requested Licensing Action Re Relief Request to Defer ASME Inspections Due COVID-19 (EPIDs L-2020-LLR-0055, -56, and -57) ML20101L0402020-04-10010 April 2020 Acceptance of Requested Licensing Action Relief Request to Use Code Case OMN-13 with 2012 Edition of the OM Code ML20101H3912020-04-0808 April 2020 Verbal Authorization for Seabrook Relief Request 3IIR-7 ML20087K8262020-03-27027 March 2020 Upcoming Steam Generator Tube Inservice Inspection ML20063J9792020-02-28028 February 2020 Acceptance of Requested Licensing Action Amendment Request to Revise Degraded Voltage Time Delay Setpoint ML19347C6732019-12-13013 December 2019 Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-418 ML19296D9122019-10-23023 October 2019 NRR E-mail Capture - Request for Additional Information Related to Seabrook Inverter Amendment (L-2019-LLA-0216) ML19295F5422019-10-15015 October 2019 NRR E-mail Capture - Seabrook Station, Unit No. 1 - Acceptance of Requested Licensing Action Amendment Request to Revise Onsite Power Distribution Requirements ML19275G7832019-10-0101 October 2019 Limited Appearance Statement from New Hampshire State Representative, Robert Harb Regarding the Seabrook Station Unit 1 License Amendment Application ML19270E6512019-09-27027 September 2019 Limited Appearance Statement from Joanna Hammond Regarding the Seabrook Station Unit 1 License Amendment Application ML19270E6542019-09-26026 September 2019 Limited Appearance Statement from Brian Campbell Regarding the Seabrook Station Unit 1 License Amendment Application ML19196A3592019-07-15015 July 2019 NRR E-mail Capture - Seabrook Station, Unit No. 1 - Acceptance of Requested Licensing Action Amendment Request to Revise the Emergency Core Cooling System Accumulator Technical Specifications ML19169A2412019-06-13013 June 2019 NRR E-mail Capture - Seabrook Station, Unit No. 1 - Acceptance of Requested Licensing Action Relief Requests for the Containment Building Spray Pump Flow and Vibration Testing (Epids L-2019-LLR-00 and L-2019-LLR-00) ML19162A0662019-06-0404 June 2019 Reply to Mr. Rick Jakious'S E-mail of 5-29-2019 to Stephen B. Comley Sr., We the People with Attachments ML19112A1782019-04-22022 April 2019 NRR E-mail Capture - Point Beach; Seabrook; Turkey Point - Acceptance of Requested Licensing Action Amendment Request to Revise Technical Specifications to Adopt TSTF-563 ML19101A4042019-04-11011 April 2019 NRR E-mail Capture - Point Beach; Seabrook; St. Lucie; Turkey Point - Acceptance of Licensing Action Relief Request to Use Encoded Phased Array Ultrasonic Examination Techniques for Ferritic and Austenitic Welds ML19070A2382019-03-10010 March 2019 LTR-19-0088 Maura Healey, Attorney General, the Commonwealth of Massachusetts, Ltr NextEras Requests for a License Amendment and Twenty-year Extension Prior to Issuance of a Final Decision in Adjudicatory Hearing on Concrete Degradation at ML19056A4522019-02-25025 February 2019 Comment from Philip Hurzeler Regarding the Emergency Petition Filed by C-10 on February 13, 2019 ML19056A4582019-02-25025 February 2019 Comment from Deborah A. Jones Regarding the Emergency Petition Filed by C-10 on February 13, 2019 ML19056A4602019-02-25025 February 2019 Comment from Lisa Conti Regarding the Emergency Petition Filed by C-10 on February 13, 2019 ML19050A2212019-02-19019 February 2019 NRR E-mail Capture - Seabrook Station, Unit No. 1 - Acceptance of Requested Licensing Action Relief Request Proposed Alternative 3IR-17 Implementation of an Extended Reactor Vessel Inservice Inspection Interval ML19050A3202019-02-13013 February 2019 Package from Stephen B. Comley, Sr. at February 13, 2019 Seabrook Station, Unit 1, Public Meeting 2023-06-22
[Table view] |
Text
SeabrookLANPEm Resource From: Poole, Justin Sent: Tuesday, August 22, 2017 4:22 PM To: 'Deborah Grinnell'
Subject:
RE: Re: NextEra meeting with NRC Attachments: 2017-8-24 Seabrook LAR Stage 3 Public Meeting - FINAL.PDF
- Debbie, Here are the staff's slides that we'll present at the public meeting and below is the conference line information. The meeting focus is on their stage 3 building evaluations.
Participant passcode: 46681#
Toll Free Number: 1-888-790-7136 Justin C. Poole Project Manager NRR/DORL/LPL I U.S. Nuclear Regulatory Commission (301)415-2048
Original Message-----
From: Deborah Grinnell [1]
Sent: Tuesday, August 22, 2017 4:18 PM To: Poole, Justin <Justin.Poole@nrc.gov>
Subject:
[External_Sender] Re: NextEra meeting with NRC
- Justin, What is the content of your meetin with NextEra g..the outline of your questions.
Thank you, Debbie
> On Aug 22, 2017, at 4:12 PM, Deborah Grinnell <grinnelldebbie2@gmail.com> wrote:
> Hello Justin
> I will listen, follow, and may speak with C-10 on the Aug 24th 2017 meeting you will have with NextEra on August 24 at 1-3PM.
> Debbe Grinnell 1
Hearing Identifier: Seabrook_LA_NonPublic Email Number: 1117 Mail Envelope Properties (31be334fd633433eb89aa50f9181c219)
Subject:
RE: Re: NextEra meeting with NRC Sent Date: 8/22/2017 4:21:48 PM Received Date: 8/22/2017 4:21:40 PM From: Poole, Justin Created By: Justin.Poole@nrc.gov Recipients:
"'Deborah Grinnell'" <grinnelldebbie2@gmail.com>
Tracking Status: None Post Office: HQPWMSMRS01.nrc.gov Files Size Date & Time MESSAGE 973 8/22/2017 4:21:40 PM 2017-8-24 Seabrook LAR Stage 3 Public Meeting - FINAL.PDF 1591357 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Seabrook Station License Amendment Request Stage 3 Methodology Justin Poole, Project Manager, DORL, NRR Bryce Lehman, Structural Engineer, DE, NRR George Thomas, Senior Structural Engineer, DE, NRR
Agenda Issues with Current Stage 3 Methodology Staff Expectations for Methodology Path Forward Schedule Discussion 2
Stage 3 as Described in LAR Description in LAR of advanced techniques proposed to be used is high-level with no implementation details provided for staff to evaluate as a generic method of evaluation Includes methods whose implementation appear open to interpretation, with no specific applicability limitations, justification or acceptance criteria, and may be outside the design code (ACI 318-71)
LAR notes that analysis will demonstrate compliance with ACI 318-71 3
Staff Concerns with Stage 3 It is unclear how the methodology as described in the LAR could be consistently applied and similar results obtained
- Significant decisions in the Containment Enclosure Building (CEB) calculation appear to be based on engineering judgement
- Stage 3 uses iterative processes with no clear limitations 4
Staff Concerns with Stage 3 Review of Containment Enclosure Building (CEB) calculation identified several general issues:
- ACI 318-71 requirements for moment redistribution do not appear to be met or justified; approach used does not appear to be supported by accepted concrete codes
- Acceptance criteria are not provided for the structural adequacy of sections to develop a plastic hinge
- A limit on moment redistribution iterations is not provided
- No guidance is provided on determining the threshold factor or under what circumstances it can be modified
- No evaluation of serviceability limit state included under normal service load conditions that include ASR 5
Staff Expectations for Methodology The LAR or UFSAR mark-up should include sufficient detail to allow qualified engineer to follow the process through any Stage 3 calc
- How ACI 318-71 requirements will be met and/or justification for alternatives and requirements that are not met
- Guidance/criteria on when proposed analysis techniques and methods can be used
- Limits on the use of iterative processes
- Identified rebar strain limits under normal service conditions including ASR load 6
Path Forward:
Potential LAR Supplement Potential LAR supplement options:
- Update LAR to include detailed, consistently applicable methodology; staff will review a sample of completed calculations
- Approval of partial methodology (Stage 1 & 2); all final Stage 3 evaluations for NRC review and approval
- Other options?
Approach is up to NextEra 7
Impacts on Schedule Staff intends to review a sampling of completed Stage 1, 2 and 3 analyses
- Sampling dependent on analysis complexity and issues identified Schedule dependent on analyses availability
- Analyses should be approved and incorporated by NextEra prior to NRC review 8
Questions?
9