EPID:L-2017-LLA-0393, Issuance of Amendments 132 and 131 - Change to Natural Circulation and Passive Residual Heat Removal Heat Exchanger Startup Tests (LAR 17-041) (Approved, Closed) |
|
MONTHYEARML18179A4132018-07-11011 July 2018 Attachment - Vogtle Electric Generating Plant Unit 4(LAR-17-041) Project stage: Acceptance Review ML18179A4122018-07-11011 July 2018 Attachment - Vogtle Electric Generating Plant, Unit 3(LAR-17-041) Project stage: Acceptance Review ML18179A3402018-07-11011 July 2018 Safety Evaluation - Vogtle Electric Generating Plant Units 3 and 4 (LAR 17-041) Project stage: Approval ML18179A3362018-07-11011 July 2018 Issuance of Amendments 132 and 131 - Change to Natural Circulation and Passive Residual Heat Removal Heat Exchanger Startup Tests (LAR 17-041) Project stage: Request ML18179A3392018-07-11011 July 2018 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 17-041) Project stage: Other ML18179A3382018-07-11011 July 2018 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 17-041) Project stage: Other ML18179A3372018-07-11011 July 2018 Cover Letter - Vogtle Electric Generating Plant Units 3 and 4 for (LAR 17-041) Project stage: Other 2018-07-11
[Table View] |
|
---|
Category:Letter
MONTHYEARNL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program IR 05000424/20240052024-08-26026 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 - Report 05000424/2024005 and 05000425/2024005 ML24235A1952024-08-22022 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 and 4 - Report 05200025/2024005 and 05200026/2024005 IR 05000424/20244012024-08-15015 August 2024 4 - Security Baseline Inspection Report 05000424-2024401, 05000425-2024401, 05200025-2024402, and 05200026-2024403 - Cover Letter ML24218A1842024-08-0707 August 2024 Examination Report and Cover Letter ML24212A1442024-08-0101 August 2024 Integrated Inspection Report 05200025/2024002 and 05200026/2024002 IR 05000424/20240022024-07-29029 July 2024 Integrated Inspection Report 05000424/2024002 and 05000425/2024002 IR 05000424/20244042024-07-26026 July 2024 Material Control and Accounting Program Inspection Report 05000424/2024404 and 05000425/2024404 (Cover Letter) NL-24-0126, – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.62024-07-25025 July 2024 – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.6 NL-24-0282, License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements2024-07-25025 July 2024 License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements ML24204A0722024-07-23023 July 2024 Issuance of Amendment No. 225, Regarding LAR to Revise TS 3.7.9 for a one-time Change to Support Nuclear Service Cooling Water Transfer Pump Repairs - Emergency Circumstances NL-24-0286, Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair2024-07-20020 July 2024 Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair ML24191A4562024-07-19019 July 2024 Request for Relief and Alternative Requirements for Squib (Explosively Actuated) Valves First Test Interval NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24194A0342024-07-12012 July 2024 Review of the Refueling Outage 1R24 Steam Generator Tube Inspection Report ML24191A3792024-07-10010 July 2024 – Initial Test Program and Operational Programs Inspection Report 05200026/2024011 NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2024-07-0303 July 2024 Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0087, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks2024-06-21021 June 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks NL-24-0201, Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2024-06-18018 June 2024 Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0243, Registration of Spent Fuel Cask Use2024-06-18018 June 2024 Registration of Spent Fuel Cask Use ML24163A0632024-06-12012 June 2024 2024 Licensed Operator Re-qualification Inspection Notification Letter Vogtle, Units 3 & 4 ML24155A1772024-06-0505 June 2024 Regulatory Audit in Support of Review of the LAR to Revise Emergency Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, Surveillance Requirements NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24094A1402024-05-16016 May 2024 Staff Response to Request for Revision to NRC Staff Assessment of Updated Seismic Hazard Information and Latest Understanding of Seismic Hazards at the Vogtle Plant Site Following the NRC Process for the Ongoing Assessment of Natural Hazard ML24130A2412024-05-13013 May 2024 Integrated Inspection Report 05200025/2024001 and 05200026/2024001 ML24120A1812024-05-13013 May 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage IR24 Steam Generator Tube Inspection Report – Enclosure 2 ML24101A2112024-05-11011 May 2024 Expedited Issuance of Amendment No. 198 Change to Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 ML24127A2372024-05-0909 May 2024 Initial Test Program and Operational Programs Inspection Report 05200026/2024010 NL-24-0194, Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1)2024-05-0707 May 2024 Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1) IR 05000424/20244032024-05-0101 May 2024 Cyber Security Inspection Report 05000424/2024403 and 05000425/2024403 Public ML24120A2832024-04-30030 April 2024 Project Manager Reassignment NL-24-0170, Responses to Second Round NRC Request for Additional Information for Refueling Outage 1 R24 Steam Generator Tube Inspection Report2024-04-25025 April 2024 Responses to Second Round NRC Request for Additional Information for Refueling Outage 1 R24 Steam Generator Tube Inspection Report NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 IR 05000424/20240012024-04-23023 April 2024 –Integrated Inspection Report 05000424/2024001 and 05000425/2024001 NL-24-0154, Preservice Inspection Progam Owners Activity Report2024-04-16016 April 2024 Preservice Inspection Progam Owners Activity Report ML24030A9092024-04-10010 April 2024 Issuance of Amendment Nos. 224 and 207, Regarding Revision to Technical Specification 3.4.14 (Reactor Coolant System) Pressure Isolation Valve Leakage Surveillance Requirement 3.4.14.1 ML24079A0062024-04-10010 April 2024 – Proposed Alternative to the Requirements of ASME Code of Operation and Maintenance of Nuclear Power Plants for Pressure Isolation Valve Testing Frequency ML24096A1322024-04-0505 April 2024 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing and Order (EPID L-2024-LLA-0043) - Letter NL-24-0128, License Amendment Request: Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) Testing Frequency2024-04-0404 April 2024 License Amendment Request: Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) Testing Frequency NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. NL-24-0112, Request for Revision to NRC Staff Assessment of Vogtle Site Updated Seismic Hazards2024-03-28028 March 2024 Request for Revision to NRC Staff Assessment of Vogtle Site Updated Seismic Hazards NL-24-0098, Report on Status of Decommissioning Funding2024-03-28028 March 2024 Report on Status of Decommissioning Funding NL-24-0097, Exemption Request: Final Safety Analysis Report Update Schedule2024-03-22022 March 2024 Exemption Request: Final Safety Analysis Report Update Schedule NL-22-0267, License Amendment Request to Revise Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, AC Sources – Operating, Surveillance Requirements2024-03-20020 March 2024 License Amendment Request to Revise Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, AC Sources – Operating, Surveillance Requirements ML24047A0362024-03-0404 March 2024 Response to Hatch and Vogtle FOF Dates Change Request (2025) 2024-09-09
[Table view] |
Text
July 11, 2018 Mr. Brian H. Whitley, Director Regulatory Affairs Southern Nuclear Operating Company, Inc.
3535 Colonnade Parkway, Bin N-226-EC Birmingham, AL 35243
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT UNITS 3 AND 4 ISSUANCE OF AMENDMENTS (LAR 17-041) RE: CHANGE TO NATURAL CIRCULATION AND PASSIVE RESIDUAL HEAT REMOVAL HEAT EXCHANGER STARTUP TESTS (LAR-17-041)
(EPID L-2017-LLA-0393)
Dear Mr. Whitley:
In response to your application dated November 17, 2017, as supplemented by letter dated June 8, 2018, the U.S. Nuclear Regulatory Commission has granted the enclosed Amendment Nos. 132 and 131 to Combined License (COL) Nos. NPF-91 and NPF-92 for the Vogtle Electric Generating Plant (VEGP) Units 3 and 4, respectively. The amendments consist of changes to the COL and Updated Final Safety Analysis Report (UFSAR) in the form of departures from the plant-specific Design Control Document (PS-DCD) Tier 2* and Tier 2 information.
The amendment authorizes changes to the VEGP Units 3 and 4 UFSAR in the form departures from the incorporated PS-DCD Tier 2 information and, involves changes to COL License Conditions 2.D.(4)(b) and 2.D.(5)(b). The amendment revises the License Condition 2.D.(4)(b) to allow the COL Appendix A Technical Specification 3.4.4 to be suspended during performance of the Natural Circulation test. Also, the amendment changes the Passive Residual Heat Removal Heat Exchanger test to be performed as part of the Power Ascension Testing as specified in COL License Condition 2.D.(5)(b) instead of as part of the Initial Criticality and Low-Power Testing requirements as currently specified in COL License Condition 2.D.(4)(b).
B. Whitley A copy of the related Safety Evaluation, which includes the evaluation of the amendment is enclosed. The notice of issuance of the amendment documents included in this letter will be published in the Federal Register.
Sincerely,
/RA Jennifer Dixon-Herrity for/
Chandu P. Patel, Senior Project Manager Licensing Branch 4 Division of Licensing, Siting, and Environmental Analysis, Office of New Reactors Docket Nos.: 52-025 52-026
Enclosures:
- 1. Amendment No. 132 to NPF-91
- 2. Amendment No. 131 to NPF-92
- 3. Safety Evaluation cc: See next page
ML18179A336 Package *via e-mail NRO-008 OFFICE DLSE/LB4:LA DLSE/LB4:PM DCIP/QVIB-2:BC NRR/DSS/STSB NAME RButler CPatel KKavanaugh VCusumano DATE 6/28/18 7/11/18 6/29/18 7/11/18 OFFICE DSRA/SRXB:BC OGC/NLO DLSE/LB4:BC NAME RKaras JMartin JDixon-Herrity DATE 7/11/18 7/10/18 7/11/18 Vogtle Units 3 & 4 Mailing List (Revised 03/13/2018) cc:
Office of the Attorney General Resident Inspector 40 Capitol Square, SW Vogtle Plant Units 3 & 4 Atlanta, GA 30334 8805 River Road Waynesboro, GA 30830 Resident Manager Oglethorpe Power Corporation Mr. Barty Simonton Alvin W. Vogtle Nuclear Plant Team Leader 7821 River Road Environmental Radiation Program Waynesboro, GA 30830 Air Protection Branch Environmental Protection Division Southern Nuclear Operating Company 4244 International Parkway, Suite 120 Document Control Coordinator Atlanta, GA 30354-3906 3535 Colonnade Parkway, Bin N-226-EC Birmingham, AL 35243 George B. Taylor, Jr.
2100 East Exchange Pl Anne F. Appleby Atlanta, GA 30084-5336 Olgethorpe Power Corporation 2100 East Exchange Place Brian H. Whitley Tucker, GA 30084 Regulatory Affairs Director Southern Nuclear Operating Company County Commissioner 3535 Colonnade Parkway, Bin N-226-EC Office of the County Commissioner Birmingham, AL 35243 Burke County Commission Waynesboro, GA 30830 Mr. Michael Yox Site Regulatory Affairs Director Mr. Wayne Guilfoyle Vogtle Units 3 & 4 Commissioner District 8 7825 River Road, Bin 63031 Augusta-Richmond County Commission Waynesboro, GA 30830 4940 Windsor Spring Rd Hephzibah, GA 30815 Gwendolyn Jackson Burke County Library 130 Highway 24 South Waynesboro, GA 30830 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Atlanta, GA 30334 Page 1 of 3
Vogtle Units 3 & 4 Mailing List Email acchambe@southernco.com (Amy Chamberlian) agaughtm@southernco.com (Amy Aughtman)
ALPUGH@southernco.com (Amanda Pugh) awc@nei.org (Anne W. Cottingham) becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley)
Bill.Jacobs@gdsassociates.com (Bill Jacobs) bjadams@southernco.com (Brad Adams) bwwaites@southernco.com (Brandon Waites) castelca@westinghouse.com (Curtis Castell) comerj@westinghouse.com (James Comer) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dgbost@southernco.com (Danny Bost) dlfulton@southernco.com (Dale Fulton) drculver@southernco.com (Randy Culver) durhamdc@westinghouse.com (David Durham) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David) erg-xl@cox.net (Eddie R. Grant) fdhundle@southernco.com (Forrest Hundley) fhwillis@southernco.com (Fred Willis)
G2NDRMDC@southernco.com (SNC Document Control) graysw@westinghouse.com (Scott W. Gray) jadwilli@southernco.com (J.D. Williams) james1.beard@ge.com (James Beard) jannina.blanco@pillsburylaw.com (Jannina Blanco) jantol1dj@westinghouse.com (David Jantosik) jenmorri@southernco.com (Jennifer Buettner)
JHaswell@southernco.com (Jeremiah Haswell) jim@ncwarn.org (Jim Warren)
John.Bozga@nrc.gov (John Bozga)
Joseph_Hegner@dom.com (Joseph Hegner) jpredd@southernco.com (Jason R. Redd) jranalli@meagpower.org (Jerry Ranalli) karen.patterson@ttnus.com (Karen Patterson) karlg@att.net (Karl Gross) kmstacy@southernco.com (Kara Stacy)
KSutton@morganlewis.com (Kathryn M. Sutton)
Page 2 of 3
Vogtle Units 3 & 4 Mailing List kwaugh@impact-net.org (Kenneth O. Waugh) lchandler@morganlewis.com (Lawrence J. Chandler)
Marc.Pickering@hq.doe.gov (Marc Pickering) markus.popa@hq.doe.gov (Markus Popa) mdmeier@southernco.com (Mike Meier) media@nei.org (Scott Peterson)
Melissa.Smith@Hq.Doe.Gov (Melissa Smith)
Michael.Kuca@hq.doe.gov (Michael Kuca) mike.price@opc.com (M.W. Price)
MKWASHIN@southernco.com (MKWashington) mlgraves@southernco.com (Michelle Graves)
MSF@nei.org (Marvin Fertel) myox@southernco.com (Mike Yox) nirsnet@nirs.org (Michael Mariotte)
Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell)
Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) r.joshi15@comcast.net (Ravi Joshi)
RJB@NEI.org (Russell Bell)
Ronald.Jones@scana.com (Ronald Jones) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak) sblanton@balch.com (Stanford Blanton)
Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) skauffman@mpr.com (Storm Kauffman) sroetger@psc.state.ga.us (Steve Roetger) stephan.moen@ge.com (Stephan Moen) stephen.burdick@morganlewis.com (Stephen Burdick) tom.miller@hq.doe.gov (Tom Miller)
TomClements329@cs.com (Tom Clements)
Vanessa.quinn@dhs.gov (Vanessa Quinn) vcsummer2n3@gmail.com (Brian McIntyre) wasparkm@southernco.com (Wesley A. Sparkman) wayne.marquino@gmail.com (Wayne Marquino) weave1dw@westinghouse.com (Doug Weaver) x2gabeck@southernco.com (Gary Becker) x2kmseib@southernco.com (Kristin Seibert)
Page 3 of 3