Meeting Slides - TVA Phase 0 Meeting with NRC Bellefonte Units 1 & 2 Main Control Room Modernization
ML11200A115
Person / Time
Site: Bellefonte  Tennessee Valley Authority icon.png
Issue date: 07/14/2011
From: Hinson A
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
Hinson A
Shared Package
ML11200A124 List:
References
Download: ML11200A115 (21)


Text

TVA Phase 0 Meeting with NRC Bellefonte Units 1 & 2 Main Control Room Modernization Alvin Hinson - TVA I&C Engineering Manager July 14, 2011 July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 1

TVA, AREVA

  • Desmond Raymond - AREVA HFE Manager
  • Bob Kershner - HFE Engineering Discipline Lead
  • Dominick Logalbo - HFE Analysis Lead
  • Jim Hawks - TVA Oversight
  • Jerry Mauck - TVA Oversight July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 3

Bellefonte MCR/HFE

Background

  • Control room designed and built in early 1980s
  • Bailey equipment installed in main control room July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 4

Bellefonte MCR/HFE Background (continued)

  • Detailed control room design review performed in early 1980s to address TMI action item I.D.1
  • 795 HEDs identified with 425 HED still to be resolved
  • Some legacy issues, documented as HEDs, remain to be resolved July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 6

Bellefonte MCR/HFE Background (continued)

July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 7

Bellefonte MCR/HFE Background (continued)

  • MCR/HFE modernization will address:

- Unresolved HEDs that required significant modifications to correct

- Obsolescence of existing controls and indication

  • Modernization of balance of plant I&C offered opportunity for use of integrated controls, displays, and alarms

- Significantly better than the relocation, paint, tape, and label fixes previously envisioned July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 8

Conceptual Plan for Modern Bellefonte Control Room

  • Consolidate number of panels with safety related components
  • Normal control from sitting work stations
  • Safety-related control from standing work stations
  • Safety-related work stations set on each side of unit supervisor desk July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 9

Conceptual Plan for Modern Bellefonte Control Room (continued)

  • Shift turnover/briefing room and shift manager office added
  • Use of mosaic technology for safety-related work stations
  • Use of group-view panel for plant overview monitoring safety and crew situational awareness July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 10

Conceptual Control Room Layout July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 11

Conceptual Control Room Layout July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 12

Conceptual Plan for Operation

  • General Concept of Operations -

Normal Operation

- RO1 controls reactivity and NSSS from non-safety controls

- RO2 controls turbine and BOP from non-safety Controls July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 13

Conceptual Plan for Operation (continued)

  • General Concept of Operations -

Emergency

Response

- RO1 performs safety-related actions of EOPs from safety panel (and EDG panel, if required)

- RO2 performs supporting EOP actions from non-safety panels July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 14

Conceptual Plan for Operation (continued)

  • General Concept of Operations - Loss of Offsite Power

- RO1 performs safety-related actions of AOPs from safety panel

- RO2 recovers electrical power at EDG panel and directs field operations July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 15

Conceptual Plan for Operation (continued)

  • General Concept of Operations - High Workload Surveillance Testing

- RO1 controls reactivity and NSSS from non-safety controls

- RO2 controls turbine and BOP from non-safety controls

- RO3 performs surveillance at safety panel or EDG panel, as required July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 16

HFE Process Operating PRA/HRA Experience Review Risk-Significant Human Actions

  • Bellefonte Human Requirements Management Factors Engineering Plan FRA/FA Design Assessment

- Integrated plan based on Task Analysis NUREG 0700 and NUREG 0711 DESIGN

  • Uses previous CRDR HED Training Program Development HSI Design Procedure Development work as operating experience input HFE V&V
  • Builds on industry experience from B&W Design Implementation operating plants Human Performance Monitoring July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 17

Conceptual Control Room Mockup July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 18

Conceptual Control Room Mockup (continued)

July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 19

Conceptual Control Room Mockup (continued)

July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 20

Questions

  • Open Discussion July 14, 2011 Bellefonte MCR/HFE Phase 0 Meeting 21