EPID:L-2017-FPR-0069, Package: Request for Additional Information Regarding Portland General Electric Company'S Decommissioning Funding Plan Update for Trojan Independent Spent Fuel Storage Installation (Open) |
|
MONTHYEARML18094A4892018-04-0303 April 2018 Letter to M. E. Tursa Request for Additional Information Regarding Portland General Electric Company'S Decommissioning Funding Plan Update for Trojan Independent Spent Fuel Storage Installation Project stage: RAI ML18094A4862018-04-0303 April 2018 Package: Request for Additional Information Regarding Portland General Electric Company'S Decommissioning Funding Plan Update for Trojan Independent Spent Fuel Storage Installation Project stage: Request ML18094A4872018-04-0303 April 2018 Enclosurequest for Additional Information (Request for Additional Information Regarding Portland General Electric Company'S Decommissioning Funding Plan Update for Trojan Independent Spent Fuel Storage Installation) Project stage: RAI ML19175A1302019-05-30030 May 2019 E-Mail to K. Niles/Oregon State Trojan ISFSI Decommissioning Funding Plan: Review Draft Ea/Fonsi Project stage: Draft Other 2018-04-03
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24226A1152024-08-12012 August 2024 Tom Sanders Email Updated Trojan Quality Assurance Plan_8-12-2024 ML24212A3432024-07-25025 July 2024 Email Brian Gutherman, Portland General QA Manager Qualifications Response July 25 2024 ML24213A2442024-07-22022 July 2024 Portland General Tom Sanders Email to NRC Trojan Quality Assurance Plan Rev. 31 Submittal - Follow-Up July 22, 2024 ML24213A2472024-07-18018 July 2024 Email Trojan Quality Assurance Plan Rev. 31 Submittal - Follow-Up July 18, 2024 ML24066A0492024-03-0404 March 2024 Trojan Quality Assurance Program Proposed Revision 31 Approval E-Mail ML20275A2542020-09-30030 September 2020 State of Oregon No Comment E-Mail ML20244A1532020-08-27027 August 2020 NRC E-Mail Transmitting Draft EA to State of Oregon ML20140A0172020-05-19019 May 2020 Trojan Probability E-Mail ML19175A1302019-05-30030 May 2019 E-Mail to K. Niles/Oregon State Trojan ISFSI Decommissioning Funding Plan: Review Draft Ea/Fonsi ML19078A2432019-03-19019 March 2019 E-Mail from C. Markley to M. Tursa Summary of Trojan ISFSI Renewal RAI Supplement Scope/Schedule ML18365A1712018-12-31031 December 2018 E-Mail from C. Markley to T. Mark and L. Kim Revised RAI Response Date for Trojan ISFSI Renewal Application ML18264A0212018-09-19019 September 2018 E-Mail from C. Markley to M. Tursa Revised RAI Response Date for Trojan ISFSI Renewal Application ML14157A2412014-06-0404 June 2014 NRR E-mail Capture - Joseph M. Farley, Unit 1 and Unit 2, Regarding the Licensees Updated Schedule to Respond to NRCs NFPA-805 Request for Additional Information 2024-08-12
[Table view] |
Text
From: Longmire, Pamela To: ken.niles@oregon.gov
Subject:
Trojan ISFSI Decommissioning Funding Plan: Review draft EA/FONSI Date: Thursday, May 30, 2019 9:31:00 PM Attachments: Trojan DFP Consultation Letter to State - DRAFT.pdf Trojan Final EA (Pre-Decisional).pdf
Dear Mr. Niles:
I am processing the backlog of decommissioning funding plans (DFPs) and DFP triennial updates for ISFSIs. More specifically, I am processing the DFP triennial update for the Trojan ISFSI that Portland General Electric Company (PGE) on behalf of PGE, the City of Eugene, Oregon, and PacifiCorp submitted in December 2015, for NRC staffs review and approval.
Part of the DFP review process is to document findings regarding environmental impacts of a proposed action; in this case, review and approval of the DFP triennial update for Trojans ISFSI. An environmental assessment (EA) has been prepared with findings. Consultation with agencies and parties regarding the environmental impacts of a proposed action is an important step in the review process. So, I am reaching out to you as part the consultation action. For your consideration, I have attached the draft copies of the transmittal letter and its enclosure. Both attached files contain pre-decisional information and the information is limited to use by the Oregon Department of Energy, Nuclear Safety and Energy Emergency Preparedness Division. This information shall not be disclosed without prior NRC permission.
Please email me to let know if you will have comments and if the comments can be submitted within 30 days or sooner. I will follow up with you, by phone, Monday (June 3rd). I look forward to your reply and I thank you in advance for both your time and kind consideration.
Best wishes.
PL Pamela Longmire, Ph.D.
Office of Nuclear Material Safety & Safeguards Division of Spent Fuel Management Spent Fuel Licensing Branch 11555 Rockville Pike One White Flint North: OWFN 14A21 Rockville, MD 20852 Phone: 301.415.7465