PNO-III-08-013A: Quad Cities Unit 2 Startup After Repairs to the Steam Piping Bellows Failure Inside of the Main Condenser - Update
ML083570641
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 12/22/2008
From: Jamie Benjamin, Ring M
NRC/RGN-III
To:
References
PNO-III-08-013A
Download: ML083570641 (1)


PRELIMINARY NOTIFICATION- REGION III December 22, 2008 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE - PNO-III-08-013A This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by the Region III staff on this date.

Facility Licensee Emergency Classification Quad Cities Station 2 Notification of Unusual Event Exelon Generation Company, LLC Alert Cordova, Illinois Site Area Emergency Docket: 50-265 General Emergency License: DPR-30 x Not Applicable

SUBJECT:

QUAD CITIES UNIT 2 STARTUP AFTER REPAIRS TO THE STEAM PIPING BELLOWS FAILURE INSIDE OF THE MAIN CONDENSER - Update DESCRIPTION:

This is an update to Preliminary Notification (PNO-III-08-013) related to a shutdown for Quad Cities Unit 2. On December 12, 2008, a normal plant shutdown of Unit 2 was performed to enter a planned maintenance outage early in order to investigate a partial loss of feedwater heating.

At 1:30 p.m. CST, on December 20, 2008, Exelon Nuclear Company notified the NRC Resident Inspectors that Quad Cities Unit 2 had commenced a normal reactor startup following a maintenance outage to perform switchyard work and replace extraction steam piping in the main condenser. The reactor was declared critical at 7:24 p.m. CST, on December 20, 2008. The main generator was placed onto the grid at 1:42 a.m. CST, on December 22, 2008.

Currently, the plant is in Mode 1, with power ascension to full rated electrical power in progress.

The NRC resident inspectors are monitoring the utilitys on-going activities.

The information in this preliminary notification has been reviewed with licensee management.

The State of Illinois has been notified.

This information is current as of 9:30 a.m. on December 22, 2008.

CONTACTS:

Mark Ring Jamie Benjamin 630-829-9703 630/829-9753