PNO-III-10-007, Unusual Event Declared at Quad Cities Due to Freon Leak in the Access Building | 19 May 2010 | PNO-III-10-007, Unusual Event Declared at Quad Cities Due to Freon Leak in the Access Building | |
PNO-III-08-013, A: Quad Cities Unit 2 Startup After Repairs to the Steam Piping Bellows Failure Inside of the Main Condenser - Update | 22 December 2008 | PNO-III-08-013A: Quad Cities Unit 2 Startup After Repairs to the Steam Piping Bellows Failure Inside of the Main Condenser - Update | |
ML083500579 | 15 December 2008 | PNO-III-08-013, Quad Cities, Unit 2 Shutdown Due to a Steam Piping Bellows Failure Inside of the Main Condenser | |
PNO-III-08-012, A - Quad Cities Notice of Unusual Event Due to Onsite Explosion - Update | 29 October 2008 | PNO-III-08-012A - Quad Cities Notice of Unusual Event Due to Onsite Explosion - Update | |
ML083010098 | 27 October 2008 | PNO-III-08-012 - Quad Cities Notice of Unusual Event Due to Onsite Explosion | |
ML072890262 | 16 October 2007 | PNO-III-08-011:Exelon Nuclear Generating Co, Tritium Leakage | |
PNO-III-06-010, Exelon Generation Co - Cracking Identified in Unit 2 Steam Dryer | 7 April 2006 | PNO-III-06-010, Exelon Generation Co - Cracking Identified in Unit 2 Steam Dryer | |
PNO-III-06-001, A Quad Cities Degraded Actuators for Electromagnetic Relief Valves (Update) | 19 January 2006 | PNO-III-06-001A Quad Cities Degraded Actuators for Electromagnetic Relief Valves (Update) | Flow Induced Vibration |
ML060170755 | 17 January 2006 | PNO-III-06-001 Quad Cities: Degraded Actuators for Electromagnetic Relief Valves | Flow Induced Vibration |
PNO-III-03-026, A: Quad Cities, Cracks Discovered in Unit 2 Steam Dryer - Update | 20 June 2003 | PNO-III-03-026A: Quad Cities, Cracks Discovered in Unit 2 Steam Dryer - Update | |
PNO-III-03-020, A: Quad Cities, Alert Declared Due to Relief Valve Failing to Close (Update) | 17 April 2003 | PNO-III-03-020A: Quad Cities, Alert Declared Due to Relief Valve Failing to Close (Update) | |
PNO-III-02-032, Shutdown to Determine and Correct the Cause of Fluctuations in Main Steam Line Parameters (Flow, Pressure, Carryover) | 15 July 2002 | PNO-III-02-032 - Shutdown to Determine and Correct the Cause of Fluctuations in Main Steam Line Parameters (Flow, Pressure, Carryover) | |
PNO-III-02-001, Shut Down Due to Jet Pump Inoperability | 10 January 2002 | PNO-III-02-001 - Shut Down Due to Jet Pump Inoperability |