PNO-III-10-007, Unusual Event Declared at Quad Cities Due to Freon Leak in the Access Building19 May 2010PNO-III-10-007, Unusual Event Declared at Quad Cities Due to Freon Leak in the Access Building
PNO-III-08-013, A: Quad Cities Unit 2 Startup After Repairs to the Steam Piping Bellows Failure Inside of the Main Condenser - Update22 December 2008PNO-III-08-013A: Quad Cities Unit 2 Startup After Repairs to the Steam Piping Bellows Failure Inside of the Main Condenser - Update
ML08350057915 December 2008PNO-III-08-013, Quad Cities, Unit 2 Shutdown Due to a Steam Piping Bellows Failure Inside of the Main Condenser
PNO-III-08-012, A - Quad Cities Notice of Unusual Event Due to Onsite Explosion - Update29 October 2008PNO-III-08-012A - Quad Cities Notice of Unusual Event Due to Onsite Explosion - Update
ML08301009827 October 2008PNO-III-08-012 - Quad Cities Notice of Unusual Event Due to Onsite Explosion
ML07289026216 October 2007PNO-III-08-011:Exelon Nuclear Generating Co, Tritium Leakage
PNO-III-06-010, Exelon Generation Co - Cracking Identified in Unit 2 Steam Dryer7 April 2006PNO-III-06-010, Exelon Generation Co - Cracking Identified in Unit 2 Steam Dryer
PNO-III-06-001, A Quad Cities Degraded Actuators for Electromagnetic Relief Valves (Update)19 January 2006PNO-III-06-001A Quad Cities Degraded Actuators for Electromagnetic Relief Valves (Update)Flow Induced Vibration
ML06017075517 January 2006PNO-III-06-001 Quad Cities: Degraded Actuators for Electromagnetic Relief ValvesFlow Induced Vibration
PNO-III-03-026, A: Quad Cities, Cracks Discovered in Unit 2 Steam Dryer - Update20 June 2003PNO-III-03-026A: Quad Cities, Cracks Discovered in Unit 2 Steam Dryer - Update
PNO-III-03-020, A: Quad Cities, Alert Declared Due to Relief Valve Failing to Close (Update)17 April 2003PNO-III-03-020A: Quad Cities, Alert Declared Due to Relief Valve Failing to Close (Update)
PNO-III-02-032, Shutdown to Determine and Correct the Cause of Fluctuations in Main Steam Line Parameters (Flow, Pressure, Carryover)15 July 2002PNO-III-02-032 - Shutdown to Determine and Correct the Cause of Fluctuations in Main Steam Line Parameters (Flow, Pressure, Carryover)
PNO-III-02-001, Shut Down Due to Jet Pump Inoperability10 January 2002PNO-III-02-001 - Shut Down Due to Jet Pump Inoperability