Acknowledgment Receipt of Response to Notice of Violation and NRC Inspection Report 05000285/2011007
ML112312266
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 08/19/2011
From: James Drake
NRC/RGN-IV/DRP/RPB-E
To: Bannister D
Omaha Public Power District
References
EA-11-025 IR-11-007
Download: ML112312266 (2)


See also: IR 05000285/2011007

Text

UNITED STATES

NU C LE AR RE G ULATO RY C O M M I S S I O N

R E GI ON I V

612 EAST LAMAR BLVD , SU I TE 400

AR LIN GTON , TEXAS 76011-4125

August 19, 2011

EA-11-025

David J. Bannister, Vice President

and Chief Nuclear Officer

Omaha Public Power District

Fort Calhoun Station FC-2-4

P.O. Box 550

Fort Calhoun, NE 68023-0550

SUBJECT: RESPONSE TO NOTICE OF VIOLATION AND NRC INSPECTION REPORT

05000285/2011007

Dear Mr. Bannister

Thank you for your letter dated August 17, 2011, in response to our July 18, 2011, letter and

Notice of Violation (ML111881131) concerning the failure of Omaha Public Power District to

assure that the cause of a significant condition adverse to quality was determined and corrective

actions to preclude repetition of the condition for the reactor trip contactors in the reactor

protection system were taken. We have reviewed your reply and find it responsive to the

concerns raised in our Notice of Violation. We will review the implementation of your corrective

actions during a future inspection to determine that full compliance has been achieved and will

be maintained.

Sincerely,

/RA/

James F. Drake, Chief

Project Branch E

Division of Reactor Projects

Docket No. 50-285

License No. DPR-40

Enclosure:

Fort Calhoun Station Inspection/Activity Plan

cc: Distribution via ListServ

Omaha Public Power District -2-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

Acting DRP Deputy Director (Jeff.Clark@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Tom.Blount@nrc.gov)

Senior Resident Inspector (John.Kirkland@nrc.gov)

Resident Inspector (Jacob.Wingebach@nrc.gov)

Acting Branch Chief, DRP/E (James.Drake@nrc.gov)

Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)

FCS Administrative Assistant (Berni.Madison@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Randy.Hall@nrc.gov)

Acting Branch Chief, DRS/TSB (Dale.Powers@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

NOED Resource (NOED.Resource@nrc.gov)

OE Web Resource (OEWEB.Resource@nrc.gov)

DRS/TSB STA (Loretta.Williams@nrc.gov)

OEDO RIV Coordinator (John.McHale@nrc.gov)

NRR DORL Director (Joseph.Giitter@nrc.gov)

Director, Office of Enforcement (Roy.Zimmermon@nrc.gov)

NRR/DORL/Plant Licensing Branch IV-1 Chief (Michael.Markley@nrc.gov)

NRR/DORL Deputy Director (Louise.Lund@nrc.gov)

R:\_REACTORS\_FCS\2011\FCS RESPONSE TO NOV 201101.DOCX ML112312266

ADAMS: No Yes SUNSI Review Complete Reviewer Initials: JD

Publicly Available Non-Sensitive

. Non-publicly Available Sensitive

C:DRP/PBE C:DRP/PBE

RAzua JDrake

/RA/ /RA/

8/19/11 8/19/11

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax