Category:Letter
MONTHYEARBVY 24-028, Pre-Notice of Disbursement from Decommissioning Trust2024-10-31031 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-10-30030 October 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20240012024-06-28028 June 2024 NRC Inspection Report No. 05000271/2024001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24053A2572024-03-0101 March 2024 Withdrawal of Requested Licensing Action for a License Amendment Submitted for Approval of the License Termination Plan BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report IR 05000271/20230022024-02-20020 February 2024 NRC Inspection Report Nos. 05000271/2023002 and 07200059/2023001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust 2024-09-18
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 August 16, 2017 EA-17-059 Mr. Jack Boyle Director, Nuclear Decommissioning Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station Vernon, VT 05354
SUBJECT:
ACKNOWLEDGEMENT OF REPLY TO NOTICE OF VIOLATION, EA-17-059
Dear Mr. Boyle:
This letter acknowledges receipt of your letter dated July 25, 2017 [Agencywide Document and Access Management System (ADAMS) Accession No. ML17209A739], in response to our Investigation Report and Notice of Violation dated June 26, 2017 (ML17174B221). Thank you for informing us of the corrective actions documented in your letter. Additionally, from subsequent phone conversations we understand you took the additional action of meeting with all members of the Radiation Protection department and informing them of the issue and the expectations for compliance with Entergy policies and procedures and NRC regulations. We will review the implementation of your corrective actions during a future inspection to verify that full compliance has been achieved and maintained.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room and from the ADAMS, accessible from the NRC web site at http://www.nrc.gov/reading-material-rm/adams.html.
Your cooperation with us is appreciated.
Sincerely,
/RA/
Joseph Nick, Acting Director Division of Nuclear Materials Safety Docket No. 05000271 License No. DPR-28 cc: Distribution via ListServ
August 16, 2017 EA-17-059 Mr. Jack Boyle Director, Nuclear Decommissioning Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station Vernon, VT 05354
SUBJECT:
ACKNOWLEDGEMENT OF REPLY TO NOTICE OF VIOLATION, EA-17-059
Dear Mr. Boyle:
This letter acknowledges receipt of your letter dated July 25, 2017 [Agencywide Document and Access Management System (ADAMS) Accession No. ML17209A739], in response to our Investigation Report and Notice of Violation dated June 26, 2017 (ML17174B221). Thank you for informing us of the corrective actions documented in your letter. Additionally, from subsequent phone conversations we understand you took the additional action of meeting with all members of the Radiation Protection department and informing them of the issue and the expectations for compliance with Entergy policies and procedures and NRC regulations. We will review the implementation of your corrective actions during a future inspection to verify that full compliance has been achieved and maintained.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room and from the ADAMS, accessible from the NRC web site at http://www.nrc.gov/reading-material-rm/adams.html.
Your cooperation with us is appreciated.
Sincerely,
/RA/
Joseph Nick, Acting Director Division of Nuclear Materials Safety Docket No. 05000271 License No. DPR-28 cc: Distribution via ListServ DOCUMENT NAME: G:\WBL Documents\WBL Inspection Letter\LDPR-28.EA 059.Reply.Acknowledge.Public.docx SUNSI Review Complete: SHammann After declaring this document An Official Agency Record it will be released to the Public. ML17229B137 To receive a copy of this document, indicate in the box: C = Copy w/o attach/encl E = Copy w/ attach/encl N = No copy OFFICE RI/DNMS N RI/ORA N RI/DNMS N RI/DNMS NAME SHammann/sth MMcLaughlin/mmm RPowell/rjp JNick/jn DATE 8/9/17 8/15/17 8/16/17 8/16/17 OFFICIAL RECORD COPY