MONTHYEARML24023A0392024-01-22022 January 2024 NEI Comments on the Information Collection Renewal for Domestic Licensing of Special Nuclear Material, Docket Id NRC-2023-0118 ML23355A1972023-12-14014 December 2023 NEI, Comments on NRC Draft Resolution of SFAQ 2022-02, SAE Program Requirements ML23219A1672023-10-25025 October 2023 Response Letter to Fee Exemption Request for Pre-Submittal Activities, Review, and Endorsement of NEI 20-07 ML23270B9002023-09-27027 September 2023 NEI Letter Request for an Extension of Comment Period on Proposed Revision to Standard Review Plan Section 15.0, Introduction - Transient and Accident Analyses, Docket Id NRC 2023 0079 ML23268A0102023-09-22022 September 2023 NEI, Fee Exemption Request for Endorsement, Review and Meeting to Discuss Draft Nuclear Energy Institute Technical Report NEI 23-01, Operator Cold License Training Plan for Advanced Nuclear Reactors ML23241A8612023-08-25025 August 2023 Consolidated Industry Comments to NRC Regulatory Issue Summary 2023-02, Scheduling Information for the Licensing of Accident Tolerant, Increased Enrichment, and Higher Burnup Fuels ML23236A4992023-08-24024 August 2023 Industry Feedback on Region II Fuel Cycle Facility Construction Oversight Workshop Held August 15, 2023, and Suggested Topics for Additional Public Meetings in Fall 2023 ML23256A1622023-08-0101 August 2023 Incoming NEI Letter Dated August 1, 2023 Regarding Increase in Fees 2023-2025 ML23206A0292023-07-24024 July 2023 Incoming Fee Exemption Request for Pre-Submittal Activities, Review, and Endorsement of NEI 20-07 ML23143A1232023-06-22022 June 2023 NRC Fee Waiver Request for Draft NEI 23-01 ML23200A1662023-05-30030 May 2023 NEI Proposed Metrics for a Performance-Based Emergency Preparedness Program ML23116A0732023-05-25025 May 2023 Letter to Hillary Lane in Response to a Request for a Fee Exemption for NEI 23-03 ML23135A7332023-05-0909 May 2023 NEI Comments on NRC Safety Culture Program Effectiveness Review ML23110A6752023-04-18018 April 2023 04-18-23_NRC_Fee Waiver for NEI 23-03 ML23110A6782023-04-18018 April 2023 Request for Review and Endorsement of NEI 23-03, Supplemental Guidance for Application of 10 CFR 50.59 to Digital Modifications at Non-Power Production or Utilization Facilities ML23110A6762023-04-18018 April 2023 04-18-23_NRC_NEI 23-03 Review + Endorse ML23107A2302023-03-31031 March 2023 NEI Letter, to Andrea Veil, NRC, Regarding Industry Recommendations for a 10 CFR 50.46a/c Combined Rulemaking ML23138A1662023-03-24024 March 2023 Transmittal of NEI 22-05 Revision a, Technology Inclusive Risk Informed Change Evaluation (Tirice) Guidance for the Evaluation of Changes to Facilities Utilizing NEI 18-04 and NEI 21-07 ML23083B4622023-03-24024 March 2023 Transmittal of NEI 22-05 Revision a, Technology Inclusive Risk Informed Change Evaluation (Tirice) Guidance for the Evaluation of Changes to Facilities Utilizing NEI 18-04 and NEI 21-07 ML23060A3272023-03-0101 March 2023 NEI, Wireless Cyber Security Guidance ML23060A2142023-03-0101 March 2023 NEI, Request for NRC Endorsement of NEI White Paper, Enabling a Remote Response by Members of an Emergency Response Organization, Revision 0 ML23023A2752023-01-23023 January 2023 Request for Extension of Comment Period from the Nuclear Energy Institute on PRM-50-124 - Licensing Safety Analysis for Loss-of-Coolant Accidents ML22348A1122023-01-17017 January 2023 Letter to Richard Mogavero Response to Fee Exemption NEI 08-09 Revision 7 ML22353A6082023-01-11011 January 2023 U.S. Nuclear Regulatory Commission Report of the Regulatory Audit of the NEI-Proposed Aging Management Program Revision to Selective Leaching Program (XI.M33) ML22349A1012022-12-12012 December 2022 LTR-22-0343 Ellen Ginsberg, Sr. Vice President, General Counsel and Secretary, Nuclear Energy Institute, Expresses Concerns Related to Issuance of Regulatory Issue Summary 2022-02; Operational Leakage ML22336A0372022-11-16016 November 2022 Fee Exemption Request for NEI 08-09 Revision 7 - Changes to NEI 08-09 Cyber Security Plan for Nuclear Power Reactors ML22321A3152022-11-16016 November 2022 NEI Letter with Comments on Significance Determination Process Timeliness Review ML22298A2262022-10-25025 October 2022 Endorsement of NEI 15-09, Cyber Security Event Notifications, Revision 1, Dated October 2022 ML22298A2302022-10-17017 October 2022 Submittal of NEI 22-03, Draft Revision 0, Nuclear Generation Quality Assurance Program Description ML22207B6512022-07-26026 July 2022 NEI, Full Fee Exemption Request for Industry Guidance Proposal - Weather Related Administrative Controls During Transient Outdoor Dry Cask Operations ML22195A1662022-07-14014 July 2022 NEI, Draft G of NEI 99-01, Development of Emergency Action Levels for Non-Passive Reactors, Revision 7 ML22195A0202022-07-13013 July 2022 07-13-22 NRC Fee Exemption Request for NEI 21-05 Review ML22195A0672022-07-13013 July 2022 Fee Exemption Request for Review and Meeting to Discuss Draft Nuclear Energy Institute Technical Report NEI 21-05, Reporting Guidance for Licensees with Risk-Informed Licensing Bases ML22159A2772022-06-28028 June 2022 Response Letter to Richard Mogavero for Fee Exemption for the Nuclear Regulatory Commission Review Ad Endorsement of NEI 15-09, Revision 1 ML22153A2782022-06-0202 June 2022 Nie, Fee Exemption Request for Endorsement of NEI 15-09, Cyber Security Event Notifications, Revision 1, Dated May 2022 ML22154A2962022-06-0202 June 2022 LTR from R. Mogavero to M. Sampson Dated Jun 2 2022 Endorsement of NEI 15-09 Cyber Security Event Notifications Rev 1 Dated May 2022 ML22152A2712022-06-0101 June 2022 Digital Instrumentation and Control Common Cause Failure Policy Considerations, Revision 1 ML22143A9362022-05-20020 May 2022 May 13, 2022, Public Meeting on Draft Regulatory Issue Summary Operational Leakage, 87 Fed. Reg. 2361 (Jan. 14, 2022) (Docket Id NRC-2021-0173) ML22110A1752022-05-0303 May 2022 NRC Response to the Nuclear Energy Institute April 1, 2022, Letter, Regarding the Nrc'S CUI Implementation Plan ML22109A2082022-04-0808 April 2022 April 8, 2022, NEI White Paper on Digital Instrumentation and Control Common Cause Policy Considerations Version 2.0 ML22110A1782022-04-0101 April 2022 April 1, 2022, Letter from NEI Regarding Nrc'S Controlled Unclassified Information Program Implementation ML22048A5812022-02-16016 February 2022 NEI 22-02: Guidelines for Weather-Related Administrative Controls for Short Duration Outdoor Dry Cask Storage Operations ML22019A2922022-01-12012 January 2022 NEI, Submittal of Proposed Revisions to Aging Management Programs XI.M33, Selective Leaching and XI.E3, Inaccessible Power Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements ML21343A2922021-12-0808 December 2021 NEI, Transmittal of NEI 21-07 Revision 0-B, Technology Inclusive Guidance for Non-Light Water Reactor Safety Analysis Report: for Applicants Utilizing NEI 18-04 Methodology ML21337A3802021-12-0303 December 2021 NEI Technical Report NEI 17-06 - Guidance on Using Iec 61508 SIL Certification to Support the Acceptance of Commercial Grade Digital Equipment for Nuclear Safety Related Applications, Revision 1 ML21319A3522021-11-10010 November 2021 NRC NEI Fee Waiver Request Changes to NEI 10-04 and NEI 13-10, Dated November 10, 2021 ML21306A3652021-10-29029 October 2021 NEI Letter from D. Young to NRC S. Atack to Cease Work on Draft D of NEI 20-05, Methodological Approach and Considerations for a Technical Analysis to Demonstrate Compliance with the Eligibility Criteria of 10 CFR 73.55(a)(7) ML21342A1682021-10-29029 October 2021 Letter from W. Gross to S. Atack, Endorsement of Nuclear Energy Institute 10-04, Identifying Systems and Assets Subject to the Cyber Security Rule, Revision 3, Dated October 29, 2021 ML21342A2032021-10-29029 October 2021 Letter from W. Gross to S. Atack, Endorsement of Nuclear Energy Institute 13-10, Cyber Security Control Assessments, Revision 7, Dated October 29, 2021 ML22081A2002021-10-29029 October 2021 NEI Backfitting Concerns with NRCs Developing Position on Protection of Dry Storage Systems from Natural Phenomena During Short Term Operations 2024-01-22
[Table view] |
Text
May 17, 2012
Mr. Alex Marion Vice President, Nuclear Operations Nuclear Energy Institute 1776 I Street NW, Suite 400 Washington, DC 20006-3708
SUBJECT:
REQUEST FOR ASSISTANCE IN IDENTIFYING LICENSEE VOLUNTEERS FOR AN EXTENDED BATTERY OPERATION STUDY
Dear Mr. Marion:
The U.S. Nuclear Regulatory Commission (NRC) staff is requesting the Nuclear Energy Institute's (NEI's) support in the performance of a study to fully evaluate a commercial nuclear power plant (NPP) batteries' response to station blackout (SBO) events outside the scope of the current SBO rule (i.e., extended SBO events). Specifically, the NRC requests the NEI obtain volunteers to provide existing and revised SBO profiles. These profiles should address the condition where all alternating current (AC) power is recognized to be lost for a prolonged period within 10 minutes of an SBO event. The profiles should reflect the loads necessary to bring the plant to a safe shutdown condition.
On April 4, 2012, an addendum to the Memorandum of Understanding was executed between the NRC's Office of Nuclear Regulatory Research (RES), the Electric Power Research Institute, and the Department of Energy to participate in this study. Together with the information provided by the NEI, the NRC staff expects to more fully understand the capability of station batteries for an extended duration.
The testing is comprised of two sequences. The first sequence will verify how long the batteries can operate at reduced discharge rates. The series of tests is intended to provide a bounding set of performance expectations for extended battery operation under lower load conditions to provide data that shows the state of health of the batteries. The second sequence will test the batteries to the modified SBO profiles to determine how long the battery can support maintaining the plant in a safe shutdown condition. The NRC staff plans to have the Brookhaven National Lab test batteries to the modified SBO profiles to demonstrate the capability of station batteries for an extended duration (i.e., beyond 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />).
On April 16, 2012, Sequence 1 began and it is estimated to conclude around September 2012. Sequence 2 will be performed once the profiles have been provided and once the revised profiles have been reviewed to verify the validity of the load sequence assumptions.
We anticipate that the volunteer licensees for this project and the NEI could obtain several benefits from participating in this study. Participation will provide the NRC staff with direct current (DC) load profiles to be modeled and tested, which should yield test results more closely representing existing station battery SBO coping capabilities. The goal is to use the insights gained through the cooperative research program to potentially develop and provide guidance to extend battery performance during a prolonged SBO event.
The nuclear industry could benefit from the research data by the development of coping strategies for extended SBO events.
Because of the testing, the RES staff will gain an improved understanding of station battery performance under select extended SBO load profiles. The results from the test program will be made available via a NUREG/CR.
The NRC staff is requesting that the NEI obtain six NPPs willing to provide data in support of this study, including at least two pressurized water reactor designs, and two boiling water reactor designs. In order to meet the project schedule, we request that the volunteer sites be identified no later than June 29, 2012. Your assistance in this matter is greatly appreciated. Our technical contact for this project is Liliana Ramadan of RES. Responses and questions should be forwarded to Sheldon Stuchell at 301-415-1847 or via e-mail at Sheldon.Stuchell@nrc.gov. Sincerely,
/RA/ Timothy J. McGinty, Director Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
ML121290329 *concurred via e-mail NRR-106 OFFICE PLPB/PM PLPB/LA RES/DE/MEEB DE/EEEB/BC RES/DE/MEEB NAME SStuchell DBaxley LRamadan* JAndersen JBurke* DATE 5/8/2012 5/10/2012 5/10/20125/14/20125/10/2012 OFFICE PLPB/BC DPR/DD RES/DE/D DPR/D NAME JJolicoeur SBahadur MCase* TMcGinty DATE 5/10/2012 5/14/2012 5/16/20125/17/2012