MONTHYEARM121206, M121206A - Affirmation Session: I. SECY-12-0124 - Entergy and ENO (Pilgrim) Review of Memo & Order LBP-12-11; Ii. SECY-12-0063 - Final Rule: Revisions to Environmental Review of Nuclear Power Plant Operating Licenses (10 CFR Part 51; Rin 312012-12-0606 December 2012 M121206A - Affirmation Session: I. SECY-12-0124 - Entergy and ENO (Pilgrim) Review of Memo & Order LBP-12-11; Ii. SECY-12-0063 - Final Rule: Revisions to Environmental Review of Nuclear Power Plant Operating Licenses (10 CFR Part 51; Rin 31 ML12346A0612012-12-0606 December 2012 M121206A - Affirmation Session: I. SECY-12-0124 - Entergy and ENO (Pilgrim) Review of Memo & Order LBP-12-11; Ii. SECY-12-0063 - Final Rule: Revisions to Environmental Review of Nuclear Power Plant Operating Licenses (10 CFR Part 51; Rin 31 ML1205400782012-02-22022 February 2012 M120222A - Affirmation Session: I. SECY-11-0174 - Entergy Nuclear (Pilgrim) Pilgrim Watch'S Petition for Review of Memo and Order (Denying Request for Hearing); Ii. SECY-11-0179 - Crow Butte Resources (License Renewal - in Situ Leach Facili M120209, M120209B - Affirmation Session: I. SECY-11-0164 Entergy Nuclear (Pilgrim); Ii. SECY-11-0166 Vogtle Draft Mandatory Hearing Decision2012-02-0909 February 2012 M120209B - Affirmation Session: I. SECY-11-0164 Entergy Nuclear (Pilgrim); Ii. SECY-11-0166 Vogtle Draft Mandatory Hearing Decision ML1204100482012-02-0909 February 2012 M120209B - Affirmation Session: I. SECY-11-0164 Entergy Nuclear (Pilgrim); Ii. SECY-11-0166 Vogtle Draft Mandatory Hearing Decision ML1030903832010-11-0505 November 2010 M101105A - Affirmation: I. SECY-10-0129 - Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station) Pilgrim Watch Motion Seeking Commission to Order Board to Respond or to Respond Itself to Pilgrim M100326, M100326 - Affirmation Session: I SECY-09-0147 - Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. - (Pilgrim Nuclear Power Station): Ii. SECY-10-0014 - TVA (Watts Bar Nuclear Plant, Unit 2)2010-03-26026 March 2010 M100326 - Affirmation Session: I SECY-09-0147 - Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. - (Pilgrim Nuclear Power Station): Ii. SECY-10-0014 - TVA (Watts Bar Nuclear Plant, Unit 2) ML1008504832010-03-26026 March 2010 M100326 - Affirmation Session: I SECY-09-0147 - Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. - (Pilgrim Nuclear Power Station): Ii. SECY-10-0014 - TVA (Watts Bar Nuclear Plant, Unit 2) ML0915507002009-06-0404 June 2009 M090604B-Affirmation: I. SECY-09-0025 Entergy Nuclear (Pilgrim and Vermont Yankee); Ii. SECY-09-0040 - Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station) M090604, M090604B-Affirmation: I. SECY-09-0025 Entergy Nuclear (Pilgrim and Vermont Yankee); Ii. SECY-09-0040 - Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station)2009-06-0404 June 2009 M090604B-Affirmation: I. SECY-09-0025 Entergy Nuclear (Pilgrim and Vermont Yankee); Ii. SECY-09-0040 - Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station) ML0823509712008-08-22022 August 2008 M080822 - Affirmation Session: I. SECY-08-0081, SECY-08-0087, Petitions to Intervene Entergy Nuclear Operations, Inc. (Pilgrim Station), Application for Order Approving Indirect Transfer of Control of Licenses (Filed July 30, 2007) II M080822, M080822 - Affirmation Session: I. SECY-08-0081, SECY-08-0087, Petitions to Intervene Entergy Nuclear Operations, Inc. (Pilgrim Station), Application for Order Approving Indirect Transfer of Control of Licenses (Filed July 30, 2007) Ii2008-08-22022 August 2008 M080822 - Affirmation Session: I. SECY-08-0081, SECY-08-0087, Petitions to Intervene Entergy Nuclear Operations, Inc. (Pilgrim Station), Application for Order Approving Indirect Transfer of Control of Licenses (Filed July 30, 2007) Ii M080516, M080516A-Affirmation Session: I. SECY-08-0058 - Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), Docket No. 50-293-LR - Entergy'S Request for Guidance on the First Circuit'S Administrative2008-05-16016 May 2008 M080516A-Affirmation Session: I. SECY-08-0058 - Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), Docket No. 50-293-LR - Entergy'S Request for Guidance on the First Circuit'S Administrative ML0813702162008-05-16016 May 2008 M080516A-Affirmation Session: I. SECY-08-0058 - Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), Docket No. 50-293-LR - Entergy'S Request for Guidance on the First Circuit'S Administrative M070315, M070315 - Affirmation: I. SECY-07-0041 Motion for Reconsideration of Entergy Nuclear Vermont Yankee LLC & Entergy Nuclear Op Inc (Vermont Yankee Nuclear Power Station); Entergy Nuclear Generation Co. & Entergy Nuclear Op Inc (Pilgrim)2007-03-15015 March 2007 M070315 - Affirmation: I. SECY-07-0041 Motion for Reconsideration of Entergy Nuclear Vermont Yankee LLC & Entergy Nuclear Op Inc (Vermont Yankee Nuclear Power Station); Entergy Nuclear Generation Co. & Entergy Nuclear Op Inc (Pilgrim) ML0707406942007-03-15015 March 2007 M070315 - Affirmation: I. SECY-07-0041 Motion for Reconsideration of Entergy Nuclear Vermont Yankee LLC & Entergy Nuclear Op Inc (Vermont Yankee Nuclear Power Station); Entergy Nuclear Generation Co. & Entergy Nuclear Op Inc (Pilgrim) ML0702203642007-01-22022 January 2007 M070122 - Affirmation Session: (a) SECY-06-0240 - Vermont Yankee and Pilgrim Nuclear Power Stations; (B) SECY-07-0003 - Clinton ESP ML0701105032007-01-11011 January 2007 M070111 - Affirmation Session: (a) SECY-06-0227 - Vermont Yankee; (B) SECY-06-0238 - Pilgrim ML0628304162006-10-10010 October 2006 M061010-Affirmation Session: A. SECY-06-0199 Entergy Nuclear Operations, Inc., (Pilgrim Nuclear Power Station and Vermont Yankee Nuclear Power Station), Massachusetts Attorney General'S Petition for Backfit Order 2012-02-09
[Table view] |
Text
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
AFFIRMATION SESSION
PUBLIC MEETING
Nuclear Regulatory Commission Commission Hearing Room
11555 Rockv ille Pike Rockville, Maryland August 22, 2008 The Commission met in open session, pursuant to notice, at 9:35 a.m.,
Dale E. Klein, Chairman, presiding.
COMMISSIONERS PRESENT:
DALE E. KLEIN, Chairman of the Commission (Via Telecon)
GREGORY B. JACZKO, Member of the Commission
PETER B. LYONS, Member of the Commission (Via Telecon)
KRISTINE L. SVINICKI, Member of the Commission
STAFF AND PRESENTERS SEATED AT THE COMMISSION TABLE:
KAREN CYR, General Counsel KENNETH HART, for the Secretary of the Commission
2
DISCLAIMER
This is an unofficial transcript of a meeting of the United States Nuclear Regulatory Commission on August 22, 2008 in the Commission
=s office at One White Flint North, Rockville, Maryland. The meeting was open to public attendance and observation. This transcript has not been reviewed, corrected or edited, and it may contain inaccuracies. The transcript is intended solely for general information purposes. As provided by 10 CFR 9.103, it is not part of the formal or informal record of decision of the matters discussed.
Expressions of opinion in this transcript do not necessarily reflect final determination or beliefs.
No pleading or other paper may be filed with the Commission in any proceeding as the result of, or addressed to, any statement or argument contained herein, except as the Commission may authorize.
3 [9:35 a.m.] P R O C E E D I N G S CHAIRMAN KLEIN: We are ready to start with the affirmation. MR. HART: The first item for affirmation Entergy Nuclear Operations, Indirect Transfer of Control of Licenses. The Commission is being asked to act on a Memorandum and Order responding to two petitions to intervene in the Entergy Nuclear Operation's application for approval of the indirect transfer of control of licenses for the Pilgrim, Palisades, FitzPatrick, Vermont Yankee, Indian Point and Big Rock Point facilities. Petitions were submitted by the Union Locals 369 and 590 of the Utility Workers of America (AFL-CIO) repr esenting the workers at Pilgrim Nuclear Power Station and by West Chester Citizens Awareness Network, Rockland County Conservation Association, Promoting Health and Sustainable Energy, Sierra Club, North East Chapter and State Representative Richard Brodsky representing the Indian Point Nuclear Generating Units. Subsequently, Union Local 369 withdrew from the proceeding. The Commission has voted to approve a Memorandum and Order which denies the petitions to intervene and their associated requests and terminates this adjudication. Commissioner Jaczko disapproved the order in part. Would the Commissioners in the room please affirm your votes? COMMISSIONER JACZKO: Aye.
COMMISSIONER SVINICKI: Aye. Chairman Klein would you please affirm your vote? CHAIRMAN KLEIN: Aye. Commissioner Lyons would you please affirm your vote?
COMMISSIONER LYONS: Aye. MR. HART: The second item for affirmation Petitions of the State of Nevada and Dr. Jacob Paz to Reject the Department of Energy's Application to Construct a Geologic Repository 4 at Yucca Mountain, Nevada. The Commission is being asked to act on a Memorandum and Order responding to Petitions by the State of Nevada and Dr. Jacob Paz requesting that the Commission reject the Department of Energy's license application seeking authorization to construct a geologic repository at Yucca Mountain, Nevada. The Commission has voted to approve a Memorandum and Order which rejects the Petitions without prejudice to the Petitioners right to pursue identical claims as proposed contentions if and when the application is docketed and a notice of hearing issues. Commissioner Jaczko voted to approve the Memorandum and Order but would have provided the staff with guidance not to docket the Department of Energy's Yucca Mountain Application until the Environmental Protection Agency issues its final rule regarding r adiation prot ection standards at the proposed facility. Would the Commissioners in the room please affirm your votes? COMMISSIONER JACZKO: Aye.
COMMISSIONER SVINICKI: Aye. Chairman Klein would you please affirm your vote? CHAIRMAN KLEIN: Aye. Commissioner Lyons would you please affirm your vote?
COMMISSIONER LYONS: Aye. MR HART: That's all I have. Thank you.
CHAIRMAN KLEIN: Thank you. Meeting's adjourned.
5 CERTIFICATE
This is to certify that the attached description of a meeting of the U.S. Nuclear Regulatory Commission entitled:
TITLE OF MEETING: Affirmation Session (PUBLIC MEETING)
PLACE OF MEETING: Rockville, Maryland DATE OF MEETING: August 22, 2008
was held as herein appears, is a true and accurate record of the meeting, and that this is the original transcript thereof taken stenographically by me, thereafter reduced to typewriting by me or under the direction of the court reporting company.
Transcriber: ANTOINETTE M. LEWIS Reporter: (TAPE RECORDING)