Attachment 5: Summary of Regulatory Commitments
ML100850401
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 03/25/2010
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML100850379 List:
References
Download: ML100850401 (1)


Text

ATTACHMENT 5 Summary of Regulatory Commitments The following table identifies commitments made by Exelon Generation Company, LLC (EGC) in this document. Any other actions discussed in the submittal represent intended or planned actions. They are described to the NRC for the NRC's information and are not regulatory commitments.

COMMITMENT TYPE COMMITMENT COMMITTED DATE OR "OUTAGE" O NE-T IME A CTION (Yes/No)PROGRAMMATIC (Yes/No)Limitations regarding operation with an inoperable LEFM system will be included in the TRM. Prior to uprate implementation Yes No The LEFM system for LGS, Units 1 and 2 will be installed.

Prior to uprate implementation Yes No Plant maintenance and calibration procedures will be revised to incorporate Camerons maintenance and calibration requirements.

Prior to uprate implementation Yes No Final acceptance of the site-specific uncertainty analyses will occur after the completion of the commissioning process.

Prior to uprate implementation Yes No Modifications for the power uprate will be implemented.

Prior to uprate implementation Yes No Necessary procedure revisions for the power uprate will be completed.

Prior to uprate implementation Yes No The plant simulator will be modified for the uprated conditions and the changes will be

validated in accordance with plant configuration control processes.

Prior to uprate implementation Yes No Maintenance personnel will be qualified on the LEFM system.

Prior to work on the system No Yes Operator training will be completed prior to implementation of the proposed power uprate changes. Prior to uprate implementation Yes No Plant testing for the proposed changes will be completed as described in Attachment 6, Section 10.4, "Testing." As described Yes No Plant-specific analyses for all potentially limiting events will be performed on a cycle-specific basis as part of the reload licensing

process. Prior to uprate implementation Yes No