Limerick, Unit 2 - Tech Spec Pages for Amendment 145 One-Time Change to the Drywell Average Air Temperature Limit
ML061920258
Person / Time
Site: Limerick Constellation icon.png
Issue date: 07/07/2006
From:
Plant Licensing Branch III-2
To:
References
TAC MD2315
Download: ML061920258 (2)


Text

-3-(4) Pursuant to the Act and 10 CFR Parts 30, 40, 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5) Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility, and to receive and possess, but not separate, such source, byproduct, and special nuclear materials as contained in the fuel assemblies and fuel channels from the Shoreham Nuclear Power Station.C. This license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I (except as exempted from compliance in Section 2.D. below) and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below: (1) Maximum Power Level Exelon Generation Company is authorized to operate the facility at reactor core power levels of 3458 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 145, are hereby incorporated into this license. Exelon Generation Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.(3) Fire Protection (Section 9.5, SSER-2, -4)*Exelon Generation Company shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Updated Final Safety Analysis Report for the faaility, and as approved in the NRC Safety Evaluation Report dated August 1983 through Supplement 9, dated August 1989, and Safety Evaluation dated November 20, 1995, subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.*The parenthetical notation following the title of license conditions denotes the section of the Safety Evaluation Report and/or its supplements wherein the license condition is discussed.

Amendment No. 4, 27, 68, G2,108 CONTAINMENT SYSTEMS DRYWELL AVERAGE AIR TEMPERATURE LIMITING CONDITION FOR OPERATION 3.6.1.7 Drywell average air temperature shall not exceed 145OF**.APPLICABILITY:

OPERATIONAL CONDITIONS 1, 2, and 3.ACTION: With the drywell average air temperature greater than 145 0 F**, reduce the average air temperature to within the limit within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.I I SURVEILLANCE REQUIREMENTS 4.6.1.7 The drywell average air temperature shall be the volumetric average of the temperatures at the following locations and shall be determined to be within the limit at least once per 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />s: Approximate Elevation Number of Installed Sensors*a. 330'b. 320'c. 260'd. 248'3 3 3 6*At least one reading from each elevation is required for a volumetric average calculation.

    • Operation may continue with drywell average air temperature no greater than 148°F for the remainder of the current operating cycle (Cycle 9), or until the next shutdown of sufficient duration to allow for unit cooler fan repairs, whichever comes first.LIMERICK -L114IT 2 314 6-10 Amendment No. 145