Finding | |
---|---|
Title | Failure Of Seasonal Readiness Procedure To Identify Operability Issues |
Description | The inspectors identified a finding of very low safety significance and an NCV of 10 CFR Part 50, Appendix B, Criterion V, on June 26, 2012, due to the licensees failure to have procedures appropriate to the circumstance for coordinating and preparing for the onset of hot weather conditions. Specifically, Procedure FP-WM-SR-01, Seasonal Readiness Program, Attachment 2, failed to include criteria to ensure that issues associated with the ability of the Unit 1 EDGs to operate when outside air temperatures exceeded 97 degrees Fahrenheit were identified and addressed prior to the onset of hot weather. This resulted in both Unit 1 EDGs being rendered inoperable, and the D1 EDG being rendered unavailable, on July 2, 2012. The inspectors determined that this issue was more than minor as it impacted the protection against external events objective of the Mitigating Systems Cornerstone. In addition, this finding impacted the cornerstone objective of ensuring the availability of systems that respond to initiating events to prevent undesirable consequences. The inspectors determined that this issue was of very low safety significance because each of the questions listed in IMC 0609, Appendix A, Exhibit 2, Mitigating Systems Screening Questions, could be answered no. This finding was cross cutting in the Human Performance, Work Control area because Procedure FP-WM-SR-01 was not written to ensure that activities needed to support long term equipment reliability and availability were planned such that they were performed in a preventative manner rather than in a reactive manner |
Site: | Prairie Island |
---|---|
Report | IR 05000282/2012005 Section 4OA5 |
Date counted | Dec 31, 2012 (2012Q4) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | |
Inspectors (proximate) | D Mcneil K Riemer T Bilik C Moore M Phalen R Baker K Stoedter D Passehl J Laughlin K Barclay M Jones M Learn J Beavers D Oliver |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |
Finding - Prairie Island - IR 05000282/2012005 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Prairie Island) @ 2012Q4