Finding | |
---|---|
Title | Licensee-Identified Violation |
Description | Title 10 CFR 50.54(q)(2) requires that a holder of a nuclear power reactor operating license follow and maintain the effectiveness of an emergency plan that meets the requirements in Appendix E to this part and the planning standards of 10 CFR 50.47(b). The Prairie Island Nuclear Generating Plant (PINGP) Emergency Plan, Section 4.0 states in part, PINGP has and maintains the capability to assess, classify, and declare an emergency condition within 15 minutes after the availability of indications to plant operators that an EAL has been exceeded. Upon identification of the appropriate emergency classification level the emergency condition will be promptly declared. Contrary to the above, on October 31, 2012, the licensee failed to follow its Emergency Plan during an actual emergency which resulted in a failure to implement. Specifically, inaccurate communications resulted in the over classification of a NOUE based on EAL HU4.1. Using IMC 0609, Appendix B, Emergency Preparedness Significance Determination Process, dated February 24, 2012, Section 4.0, Actual Event Implementation Issue (Failure to Implement), the inspectors determined that the violation was not greater than very low safety significance (Green) because no public official protective actions were implemented as a result of this event over classification. The issue was documented in the licensees corrective action program as CAP 1357663. Corrective actions included making revision to emergency procedures regarding this type of security event and providing additional training to security personnel. components. Based on the above, the SRA concluded that the total risk increase to the plant due this finding based on CDF was very low (Green). The licensee documented this issue in the CAP as CAP 1345525. Corrective actions included re-installing the flood barrier, labeling the flood barrier, and ensuring that information was readily available to alert plant personnel to the fact that the concrete trench cover was used as an internal flooding barrier. |
Site: | Prairie Island |
---|---|
Report | IR 05000282/2012005 Section 4OA7 |
Date counted | Dec 31, 2012 (2012Q4) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Licensee-identified |
Inspection Procedure: | |
Inspectors (proximate) | D Mcneil K Riemer T Bilik C Moore M Phalen R Baker K Stoedter D Passehl J Laughlin K Barclay M Jones M Learn J Beavers D Oliver |
INPO aspect | |
' | |