 Issue dateTitle
05000321/FIN-2005009-01Failure to Follow and Maintain in Effect ITS Emergency Plan When the TSC Was Removed from Service During This Period to Allow for Modification Activities
05000321/FIN-2009005-03Failure to establish and perform preventive maintenance activities to replace aged electrolytic capacitors for Yokagawa controller power supply
05000321/FIN-2010002-02Failure to Implement Adequate Configuration Control on Unit 2 Main Generator Stator Water Cooling Temperature Control Instrument Loop, 2N43-F100
05000321/FIN-2010003-03Failure to follow procedure while in shutdown cooling to record corrected reactor water level
05000321/FIN-2010004-09Licensee-Identified Violation
05000321/FIN-2010005-01Licensee-Identified Violation
05000321/FIN-2010009-03Untimely Corrective Actions for Installing Appendix R Emergency Lights
05000321/FIN-2011003-02Failure to consider potential adverse system interactions when developing procedure to open SRVs without power
05000321/FIN-2011003-03Failure to address the anticipated environmental conditions when developing procedures to manually operate containment vent valves
05000321/FIN-2011005-02Cables for Fire Safe Shutdown Not Protected In Accordance With 10 CFR 50 Appendix R Section III.G.2
05000321/FIN-2012002-01Failure to Assess and Manage the Increase in Risk When Removing Residual Heat Removal and Core Spray from Service
05000321/FIN-2012003-01Removal of scaffolding built to allow implementation of Unit 1 manual operation of the containment hardened vent.
05000321/FIN-2012003-03Inadequate Surveillance Procedures for Evaluating Accumulated Gas in the HPCI and RCIC System
05000321/FIN-2012003-04Licensee-Identified Violation
05000321/FIN-2012004-01Failure to follow transient combustible control requirements within the sites intake structure.
05000321/FIN-2012004-02Licensed Operator Requalification Annual Operating Test Administration Issues
05000321/FIN-2012004-03Failure to establish adequate preventative maintenance for the safety related main control room air conditioning units
05000321/FIN-2012004-04Failure to follow clearance procedures for returning the A main control room air conditioning unit to service following maintenance
05000321/FIN-2012005-03Installation of a transformer for the TSC cooling coil and condensing unit control circuit not adequately designed to provide full system load
05000321/FIN-2012005-05Licensee-Identified Violation
05000321/FIN-2012008-02Failure to Adequately Account for Potential Pump Discharge Check Valve Back-leakage
05000321/FIN-2012008-03Failure to Ensure Adequacy of Intake Structure Ventilation Design
05000321/FIN-2012008-04Failure to Incorporate Appropriate Test Acceptance Criteria to Assure Satisfactory Steady State EDG Performance
05000321/FIN-2012008-05Failure to Provide Appropriate Acceptance Criteria for EDG Air-Start System Check Valves
05000321/FIN-2013002-01Failure to perform appropriate post maintenance test on 2A EDG
05000321/FIN-2013003-01Licensee-Identified Violation
05000321/FIN-2013005-01Scaffolding Installed in Safety Related Areas Failed to Meet Procedural Requirements
05000321/FIN-2013005-03Failure to Implement an Administrative Procedure for Equipment Control When Using Personal Danger Tags
05000321/FIN-2013009-02Failure to Meet Section IV.C, Fire Detection and Suppression of Appendix D of the Fire Hazards Analysis
05000321/FIN-2014004-03Failure to Promptly Identify Malfunction of HPCI Exhaust Drain Pot Level Instrumentation
05000321/FIN-2014005-03Licensee-Identified Violation
05000321/FIN-2014005-04Licensee-Identified Violation
05000321/FIN-2015001-04Licensee-Identified Violation
05000321/FIN-2016002-02Licensee-Identified Violation
05000321/FIN-2016007-02Passive Fire Protection
05000321/FIN-2016010-02Failure to Identify N2E Nozzle Weld Through-Wall Flaw
05000321/FIN-2017001-02Licensee-Identified Violation
05000321/FIN-2017002-04Licensee-Identified Violation
05000321/FIN-2017003-01Installation of Non-Conforming RPS Equipment
05000321/FIN-2018002-01Enforcement Action (EA)-18-100: Unanalyzed Conditions for a Postulated Fire Discovered During NFPA 805 Transition
05000366/FIN-2013009-03Review and Documentation of Fire Protection Program Changes
CY-92-223, G20110523/LTR-11-0411/EDATS: SECY-2011-0411 - Ltr. from Rep. E.J. Markey to Chairman Jaczko NRC Safety Requirements for Reactors Granted Construction Permits Prior to 197114 July 2011G20110523/LTR-11-0411/EDATS: SECY-2011-0411 - Ltr. from Rep. E.J. Markey to Chairman Jaczko NRC Safety Requirements for Reactors Granted Construction Permits Prior to 1971
IR 05000321/200200326 July 2002IR 05000321-02-003 & IR 05000366-02-003, on 03/31/2002 - 06/29/2002, Edwin I. Hatch Nuclear Power Plant
IR 05000321/200200515 January 2003IR 05000321-02-005, IR 05000366-02-005, on 09/29/2002 - 01/04/2003; Southern Nuclear Operating Company, Inc., Edwin I. Hatch, Flood Protection, Operability Evaluations, and Event Followup
IR 05000321/200200624 October 2002IR 05000321-02-006, IR 05000366-02-006, on 08/26/2002 - 08/30/2002 & 09/09/2002 - 09/13/2002, E. I. Hatch Nuclear Plant, Units 1 & 2; Safety System Design and Performance Capability Inspection
IR 05000321/200300726 September 2003IR 05000321-03-007 & IR 05000366-03-007, Edwin I. Hatch Plant, August 11-29, 2003. Identification and Resolution of Problems
IR 05000321/200400222 April 2004IR 05000321-04-002, IR 05000366-04-002, on 12/28/2003 - 03/27/04, Edwin I. Hatch Nuclear Plant, Units 1 & 2, Baxley, Ga; Maintenance Effectiveness
IR 05000321/200500229 April 2005IR 05000321-05-002, IR 05000366-05-002 & IR 0720000360-05-001, on 01/01/2005 - 03/31/2005, Edwin I. Hatch Nuclear Plant Unit 1 and Unit 2, Radioactive Material Processing and Transportation
IR 05000321/20050038 July 2005IR 05000321/05-003, on 04/01-06/30/2005, Southern Nuclear Operating Company, Inc., Permanent Plant Modifications
IR 05000321/200500611 August 2005IR 05000321-05-006 and IR 05000366-05-006, on 07/11-15/2005 and 07/25-29/2005, E.I. Hatch, Units 1 and 2, NRC Problem Identification and Resolution