05000333/FIN-2012005-01Failure to Install Reserve Station Service Transformers in Accordance with Procedure
05000333/LER-2008-003
05000333/LER-2012-005Transformer Installation Error Causes Loss of Off-Site Power
05000333/LER-2012-008Automatic Reactor Shutdown Caused by a Fault in Main Transformer
IR 05000333/198801528 September 1988Insp Rept 50-333/88-15 on 880808-19.Violations & Deviations Noted.Major Areas Inspected:Reliability & Availability of Ac & Dc Power Sys,Diesel Generators,Eccs,Svc Water & Air Sys, Automatic Depressurization Sys & Maint Activities
IR 05000333/198908017 August 1989Safety Sys Functional Insp Rept 50-333/89-80 on 890501-26. Violations,Deficiencies & Unresolved Items Noted.Major Areas Inspected:Electrical Power Sys,Including Emergency Diesel Generators & Support Sys
IR 05000333/20040052 February 2005IR 05000333-04-005, on 10/01/2004 -12/31/2004, James A. FitzPatrick Nuclear Power Plant; Post Maintenance Testing, Problem Identification and Resolution, Event Follow-up
IR 05000333/20050061 February 2006IR 05000333-05-006; 10/01/2005 - 12/31/2005; James A. FitzPatrick Nuclear Power Plant; Evaluation of Changes, Tests or Experiments, Maintenance Effectiveness, and Maintenance Risk Assessment and Emergent Work Control
IR 05000333/200500828 September 2005IR 05000333-05-008; August 1-5 and August 15-19, 2005; James A. FitzPatrick Nuclear Power Plant; Engineering Team Inspection
IR 05000333/20080035 August 2008IR 05000333-08-003, on 04/01/08 - 6/30/08, James A. Fitzpatrick Nuclear Power Plant - Maintenance Risk Assessments and Emergent Work Control, and Post-Maintenance Testing
IR 05000333/201000613 August 2010IR 05000333-10-006 on 06/07/2010 - 07/01/2010 for James A. FitzPatrick, Component Design Bases Inspection
IR 05000333/20110024 May 2011IR 05000333-11-002, on 01/01/2011 - 03/31/2011, James A. FitzPatrick Nuclear Power Plant, Identification and Resolution of Problems
IR 05000333/20120057 February 2013IR 05000333012-005; 10/01/2012 - 12/31/2012; James A. FitzPatrick Nuclear Power Plant (FitzPatrick); Follow-Up of Events
IR 05000333/201200714 June 2012IR 05000333-12-007; 4/16/2012 - 5/3/2012; James A. FitzPatrick Nuclear Power Plant (Fitzpatrick); Engineering Specialist Plant Modifications Inspection
IR 05000333/201300224 April 2013IR 05000333-13-002; 01/01/2013 - 03/31/2013; James A. FitzPatrick Nuclear Power Plant (Fitzpatrick); Maintenance Effectiveness, Problem Identification and Resolution, and Other Activities
IR 05000333/20130046 November 2013IR 05000333-13-004; 07/01/2013 - 09/30/2013; James A. FitzPatrick Nuclear Power Plant; Integrated Inspection
IR 05000333/201300511 February 2014IR 05000333-13-005; 10/01/2013 - 12/31/2013; James A. FitzPatrick Nuclear Power Plant; Problem Identification and Resolution
IR 05000333/201300723 August 2013IR 05000333-13-007; 06/10/2013 to 07/11/2013; James A. FitzPatrick Nuclear Power Plant (Fitzpatrick); Component Design Bases Inspection
IR 05000333/201500221 July 2015IR 05000333/2015002; 04/01/2015 - 06/30/2015; James A. FitzPatrick Nuclear Power Plant; Routine Integrated Inspection Report
IR 05000333/20150036 November 2015IR 05000333/2015003; 07/01/2015 - 09/30/2015; James A. FitzPatrick Nuclear Power Plant (Fitzpatrick); Operability Determinations and Follow-Up of Events
IR 05000333/201500410 February 2016Integrated Inspection Report 05000333/2015004 and Independent Spent Fuel Storage Installation Report 07200012/2015001
IR 05000333/201600113 May 2016Integrated Inspection Report 05000333/2016001, 01/01/2016 - 03/31/2016
IR 05000333/201600212 August 2016Integrated Inspection Report 05000333/2016002, April 1, 2016, Through June 30, 2016
IR 05000333/20190045 February 2020Integrated Inspection Report 05000333/2019004
IR 05000333/20210124 May 2021Temporary Instruction 2515/194 Inspection Report 05000333/2021012
JAFP-06-0057, Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power30 March 2006Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power
JAFP-07-0019, License Renewal Application, Amendment 96 April 2007License Renewal Application, Amendment 9
JAFP-07-0021, License Renewal Application, Amendment 612 February 2007License Renewal Application, Amendment 6
JAFP-09-0070, Emergency License Amendment Request Application for Technical Specification 3.8.1 Required Action B.4 Completion Time4 June 2009Emergency License Amendment Request Application for Technical Specification 3.8.1 Required Action B.4 Completion Time
JAFP-09-0072, Response to Request for Additional Information Regarding: Emergency License Amendment Request Application for Technical Specification 3.8.1 Required Action B.4 Completion Time6 June 2009Response to Request for Additional Information Regarding: Emergency License Amendment Request Application for Technical Specification 3.8.1 Required Action B.4 Completion Time
JAFP-11-0102, Application for Change to the Current Licensing Basis, Authorizing Use of on Load Tap Changers with the Reserve Station Service Transformers16 August 2011Application for Change to the Current Licensing Basis, Authorizing Use of on Load Tap Changers with the Reserve Station Service Transformers
JAFP-12-0032, Response to Request for Additional Information Application for Change to the Current Licensing Basis, Authorizing Use of on Load Tap Changers with the Reserve Station Service Transformers30 March 2012Response to Request for Additional Information Application for Change to the Current Licensing Basis, Authorizing Use of on Load Tap Changers with the Reserve Station Service Transformers
JAFP-12-0150, Commitment Extension Application for Change to the Current Licensing Basis, Authorizing Use of on Load Tap Changers with the Reserve Station Service Transformers10 December 2012Commitment Extension Application for Change to the Current Licensing Basis, Authorizing Use of on Load Tap Changers with the Reserve Station Service Transformers
JAFP-15-0047, 2015 Updated Final Safety Analysis Report, Technical Specification Bases and Technical Requirements Manual Changes Transmittal8 April 20152015 Updated Final Safety Analysis Report, Technical Specification Bases and Technical Requirements Manual Changes Transmittal
JAFP-17-0018, Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)28 February 2017Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
JAFP-22-0032, Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b..16 June 2022Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b..
JAFP-22-2020, Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Info4 March 2022Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Informed
JAFP-92-0470, Ja Fitzpatrick Nuclear Power Plant Annual Summary of Changes,Tests & Experiments for 199018 June 1992Ja Fitzpatrick Nuclear Power Plant Annual Summary of Changes,Tests & Experiments for 1990
JPN-89-021, Responds to Items 6,7 & 9 of NRC 880614 Request for Addl Info Re Transfer of Reserve Power to Emergency Buses27 April 1989Responds to Items 6,7 & 9 of NRC 880614 Request for Addl Info Re Transfer of Reserve Power to Emergency Buses
JPN-90-060, Forwards Info to Satisfy 900716 Commitment Re Switchgear Deficiency,Per SSFI Insp Rept 50-333/89-80.Waiver Requested Re Design Requirements for Three Phase Bolted Fault Criteria for Switchgear Configuration for Diesel Generator Testing4 September 1990Forwards Info to Satisfy 900716 Commitment Re Switchgear Deficiency,Per SSFI Insp Rept 50-333/89-80.Waiver Requested Re Design Requirements for Three Phase Bolted Fault Criteria for Switchgear Configuration for Diesel Generator Testing
ML02175054912 June 2002Part 3 of 3 - James A. FitzPatrick Nuclear Power Plant, Technical Specifications Bases (License Amendment) as Part of Conversion to Improved Standard Technical Specifications
ML0219701023 July 2002Technical Specifications, Amendment Conversion to Improved Technical Specifications (TAC No. MA5049), B 3.7 Plant Systems
ML0821900137 August 2008Monthly Operating Reports Second Quarter 2008
ML0915503488 June 2009License Amendment, Issuance of Emergency Amendment to Facility Operating License One-Time Extension of AOT in TS 3.8.1, Required Action B.4 Completion Time
ML11255040812 September 2011ME6877, E-mail to Licensee, Acceptance of LAR Changes to the Licensing Basis, Authorizing the Use of on Load Tap Changers for Reserve Station Service Transformer
ML12058002627 February 2012ME6877, RAIs to Licensee LAR to Revise the Current Licensing Bases Authorizing On-Load Tap Changers for RSST
ML12137098314 May 2012RAI - Load Tap Changers with Service Transformers
ML12236A30426 September 2012Issuance of Amendment #302 - Revising the Update Final Safety Analysis Report to Reflect Authorization of Use of on Load Tap Changers with the New Reserve Station Transformers
ML13079A02218 March 2013G20130211 - Timothy Judson E-mail 2.206 - James A. Fitzpatrick/Pilrgim/Vermont Yankee Nuclear Power Stations
ML17342A00618 December 2017Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051