MONTHYEARML20116L0221985-04-25025 April 1985 Informs That Revised Amend Request Re Shunt & Undervoltage Trip Attachment,Item 4.5.3 of Generic Ltr 83-28, Required Actions Based on Generic Implications of Salem ATWS Events, Will Be Submitted by 850531 Project stage: Other ML20128Q2451985-05-29029 May 1985 Proposed Tech Specs,Revising Table 4.3.1 to Provide for Testing to Confirm Operability of Shunt & Undervoltage Trip Devices of CRD Trip Breakers Project stage: Other ML20128Q2241985-05-29029 May 1985 Application for Amend to License NPF-3,revising Tech Spec Table 4.3.1 to Provide for Testing to Confirm Operability of Shunt & Undervoltage Trip Devices of CRD Trip Breakers.Fee Paid Project stage: Request ML20138R4621985-11-0404 November 1985 Requests Rev to 850529 Application for Amend to License NPF-3,changing Tech Specs to Provide for Testing to Confirm Operability of Shunt & Undervoltage Trip Devices of CRD Trip Breakers.Revised Significant Hazards Consideration Required Project stage: Other ML20205P9541987-03-27027 March 1987 Proposed Tech Specs,Adding Silicon Controlled Rectifier to Functional Unit Lists for Table 3.3-1, Reactor Protection Sys Instrumentation & Table 4.3-1, Reactor Protection Sys Instrumentation Surveillance Requirements Project stage: Other ML20205P9421987-03-27027 March 1987 Application for Amend to License NPF-3,revising Tech Spec Tables 3.3-1 & 4.3-1 in Response to Generic Ltrs 83-28 & 85-10 Re Silicon Controlled Rectifier Relays & Reactor Protection Sys Instrumentation Project stage: Request ML20205P9121987-03-27027 March 1987 Forwards Application for Amend to License NPF-3,revising Tech Spec Tables 3.3-1 & 4.3-1 in Response to Generic Ltrs 83-28 & 85-10 Re Silicon Controlled Rectifier Relays & Reactor Protection Sys Instrumentation Project stage: Request 1985-04-25
[Table View] |
|
---|
Category:OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING
MONTHYEARML20216E6051999-09-0707 September 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20210H0631999-07-28028 July 1999 Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, by Allowing Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G4131999-07-27027 July 1999 Application for Amend to License NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G8831999-07-26026 July 1999 Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrumentation - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5251999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G4631999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumention & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20195F9121999-06-10010 June 1999 Application for Amend to License NPF-3,changing TS 3/4.6.4.4 Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20207E7861999-05-21021 May 1999 Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capability ML20205E4961999-03-19019 March 1999 Application for Amend to License NPF-3,requesting Withdrawal of Proposed New Action B to TS 3.6.5.2,previously Submitted in 981027 Application ML20204F1691999-03-0909 March 1999 Application for Amend to License NPF-3,adopting Changes in Frequency & Scope of Volumetric Exams Justified by W TR WCAP-14535A ML20196F3791998-11-30030 November 1998 Supplemental Application for Amend to License NPF-3, Proposing Changes to License Conditions 2.C(6) & 2.E by Transferring Operating Authority for DBNPS from Toed & Centerior Svc Co to Firstenergy Nuclear Operating Co ML20155E3181998-10-28028 October 1998 Application for Amend to License NPF-3,revising Various Sections of TS 6.0, Administrative Controls, Including Relocation of Contents of 6.11 to Plant Ufsar,Per NUREG-1430,Rev 1 ML20155E0701998-10-27027 October 1998 Application for Amend to License NPF-3,revising TSs 3/4.3.1.1 Re RPS Instrumentation & 3/4.3.2.3 Re ARTS Instrumentation by Providing Potential Reduction in Spurious Trip Rate to Provide Cost Savings in Excess of $50,000 ML20155D7731998-10-27027 October 1998 Application for Amend to License NPF-3,relocating Existing TS SR 4.6.5.1.d.4 Re Evs Negative Pressure Testing to TS 3/4.6.5.2,deleting TS Definition 1.24 & Making Related Changes Associated with Deletion of Subject Definition ML20155D8481998-10-27027 October 1998 Application for Amend to License NPF-3,revising Existing TS SRs 4.8.2.3.2.d,4.8.2.3.2.e,4.8.2.3.2.f & Table 4.8-1 Re Testing of 125 Volt DC Station Batteries & Applicable TS Bases ML20151W2811998-09-0808 September 1998 Application for Amend to License NPF-3,permitting Use of Framatome Cogema Fuels M5 Advanced Alloy Fuel Rod Cladding & Fuel Assembly Spacer Grids ML20151W2851998-09-0808 September 1998 Application for Amend to License NPF-3,revising TS Section 3/4.7.6, Plant Systems - CREVS & Associated Bases ML20236G6461998-06-29029 June 1998 Application for Amend to License NPF-3,transferring Operating Authority for DBNPS from TE & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Marked Up License,Safety & Environ Assessments Included ML20236R2301998-06-29029 June 1998 Resubmitted Application for Amend to License NPF-3, Transferring Operating Authority for DBNPS from Teco & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Safety Assessment & EA Included ML20217P8671998-04-24024 April 1998 Application for Amend to License NPF-3,modifying Existing TS 3/4.3.1.1,3/4.3.2.1,3/4.3.2.2 & Associated Bases by Relocating Tables of Response Time Limits from TS to Plant USAR Technical Requirements Manual ML20217P8251998-04-24024 April 1998 Application for Amend to License NPF-3,clarifying Discussion of Margin Between RPS High Pressure Trip Setpoint & Lift Setting for Pressurizer Code Safety Valves ML20203L0861998-02-26026 February 1998 Application for Amend to License NPF-3 to Revise TS 3/4.4.5 & TS 3/4.4.6.2,incorporating New Repair Roll Process for SG Tubes W/Defects in Upper Tube Sheet ML20197J2511997-12-23023 December 1997 Application for Amend to License NPF-3.Amend Changes TS Definitions 1.12,TS 3/4.9.5 & New TS 3.0.6 ML20197J5861997-12-23023 December 1997 Application for Amend to License NPF-3,revising TS Surveillance Requirements for ISI Requirements of Internal Auxiliary Feedwater Header,Header to Shroud Attachment Welds & External Header Thermal Sleeves ML20217R2801997-08-26026 August 1997 Application for Amend to License NPF-3,clarifying LCO 3.6.1.3.a & Revising Surveillance Requirement 4.6.1.3.c ML20217R2831997-08-26026 August 1997 Application for Amend to License NPF-3,modifying TS 3.2.5 Action Statement to Require Power Reduction to Less than 5% of Rated Thermal Power within Four Hrs If RCS Flow Rate Is Less than Specified Limit for Greater than Two Hrs ML20217G5931997-07-29029 July 1997 Suppl 950929 to Application for Amend to License NPF-3, Change TS 3/4.4.3 Re Safety Valves & Pilot Operated Relief valve-operating & Associated Bases 3/4.4.2 & 3/4.4.3 ML20141F1051997-06-24024 June 1997 Application for Amend to License NPF-3,deleting Requirements for Safety Features Actuation Sys Containment High Radiation Monitors ML20138A3201997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Conversion to 24-month Fuel Cycle ML20138C3131997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Rev to TS 3/4.7.6 to Include New Required Actions in Event That One or Both Channels of Radiation Monitoring Instrumentation Becomes Inoperable ML20137M1061997-03-31031 March 1997 Application for Amend to License NPF-57,revising TS to Improve Consistency Between TS & Plant Configuration, Operation & Testing & Complete Required CA to Resolve TS Discrepancies Identified in CA Program ML20138M1251997-02-14014 February 1997 Application for Amend to License NPF-3,requesting Delay of Heat Removal Sys Valve Pit Surveillance Requirements ML20134D7461997-01-30030 January 1997 Application for Amend to License NPF-3,revising SR Intervals from 18 to 24 Months Based on Results of DBNPS Instrument Drift Study & TS 2.2, Limiting Safety Sys Settings, Based on Results of Revised Framatome RPS Instrument String Error ML20134B0561997-01-20020 January 1997 Application for Amend to License NPF-3,involving TS 3/4.5.3 Re ECCS Subsystems ML20132C7771996-12-13013 December 1996 Application for Amend to License NPF-3,authorizing Transfers of Control ML20132B6871996-12-11011 December 1996 Application for Amend to License NPF-3,revising TS Definitions,Instrumentation TS & ECCS TS for Conversion to 24 Month Fuel Cycle ML20134F1851996-10-28028 October 1996 Application for Amend to License NPF-3,requesting Revisions to 3/4.8.1.1,3/4.8.1.2,3/4.8.2.3,3/4.8.2.4 & 3/4.8 Re Electrical Power Systems ML20117P5301996-09-17017 September 1996 Application for Amend to License NPF-3,supporting Conversion of DBNPS from 18 Month to 24 Month Fuel Cycle ML20117N8441996-09-12012 September 1996 Application for Amend to License NPF-3,revising Reactivity Control Systems & Emergency Core Cooling Systems ML20117M1971996-09-0404 September 1996 Application for Amend to License NPF-3,App A,Modifying TS 6.2.3 by Removing Specific Overtime Limits & Working H from TS Consistent W/Nrc Recent Determination,On Generic Basis, That Limits Need Not Be Specified ML20116K2601996-08-0707 August 1996 Application for Amend to License NPF-3,changing Tech Specs 1.0, Definitions, Bases 3/4.0, Applicability & 3/4.6.2.1, Containment Sys - Depressurization & Cooling Sys - Containment Spray Sys ML20117K1871996-05-28028 May 1996 Application for Amend to License NPF-3,revising TS 3/4.3.1.1 RPS Instrumentation & TS 3/4.3.2.2 - Anticipatory RTS Instrumentation to Increase Trip Device Test Interval ML20107L3541996-04-18018 April 1996 Application for Amend to License NPF-3,requesting NRC Review & Approval to Use Alternate Electrical Lineup.Station Blackout DG as Standby Emergency Power Source to Supply Loads Normally Supplied by EDG 1,while Being Reworked ML20101M1601996-03-29029 March 1996 Application for Amend to License NPF-3,App A,Re Surveillance Requirements for Charcoal Filter Lab Testing to Revise Testing Methodology Used to Determine Operability of Charcoal Filters in ESF Air Handling Units ML20101C6911996-03-0606 March 1996 Application for Amend to License NPF-3,revising TS 3/4.5.2 to Allow Deferment of SR 4.5.2.b for ECCS Flowpath Containing HPI 1-2 Pump Until 10th Refueling Outage, Scheduled to Begin 960408 ML20100E0051996-02-0505 February 1996 LAR 93-0003 to License NPF-3,revising Table 3.3-3 of TS 3/4.3.2.1 Re Safety Features Actuation Sys Instrumentation to More Accurately Reflect Design & Actuation Logic of Plant Sequencers & Undervoltage Relays ML20095F5861995-12-12012 December 1995 Application for Amend to License NPF-3,revising TSs Re Containment Sys ML20098C5131995-10-0202 October 1995 Application for Amend to License NPF-3,revising TS Section 5.0,design Features & Adopting Improved STS for B&W Plants Format & Content ML20098C1071995-09-29029 September 1995 Application for Amend to License NPF-3,modifying TS 3.4.3 & Associated Bases for Pressurizer Code Safety Valve Lift Setpoint Tolerances ML20098C3931995-09-29029 September 1995 Application for Amend to License NPF-3,revising Tech Spec 3/4.1.2.8, Reactivity Control Sys - Borated Water Sources - Shutdown, Tech Spec 3/4.1.2.9, Reactivity Control Sys - Operating & TS 3/4.5.1, ECCS - Core Flooding Tanks 1999-09-07
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML20216E6051999-09-0707 September 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20210H0631999-07-28028 July 1999 Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, by Allowing Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G4131999-07-27027 July 1999 Application for Amend to License NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G8831999-07-26026 July 1999 Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrumentation - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5251999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G4631999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumention & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20195F9121999-06-10010 June 1999 Application for Amend to License NPF-3,changing TS 3/4.6.4.4 Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20207E7861999-05-21021 May 1999 Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capability ML20205E4961999-03-19019 March 1999 Application for Amend to License NPF-3,requesting Withdrawal of Proposed New Action B to TS 3.6.5.2,previously Submitted in 981027 Application ML20204F1691999-03-0909 March 1999 Application for Amend to License NPF-3,adopting Changes in Frequency & Scope of Volumetric Exams Justified by W TR WCAP-14535A ML20196F3791998-11-30030 November 1998 Supplemental Application for Amend to License NPF-3, Proposing Changes to License Conditions 2.C(6) & 2.E by Transferring Operating Authority for DBNPS from Toed & Centerior Svc Co to Firstenergy Nuclear Operating Co ML20155E3181998-10-28028 October 1998 Application for Amend to License NPF-3,revising Various Sections of TS 6.0, Administrative Controls, Including Relocation of Contents of 6.11 to Plant Ufsar,Per NUREG-1430,Rev 1 ML20155E0701998-10-27027 October 1998 Application for Amend to License NPF-3,revising TSs 3/4.3.1.1 Re RPS Instrumentation & 3/4.3.2.3 Re ARTS Instrumentation by Providing Potential Reduction in Spurious Trip Rate to Provide Cost Savings in Excess of $50,000 ML20155D7731998-10-27027 October 1998 Application for Amend to License NPF-3,relocating Existing TS SR 4.6.5.1.d.4 Re Evs Negative Pressure Testing to TS 3/4.6.5.2,deleting TS Definition 1.24 & Making Related Changes Associated with Deletion of Subject Definition ML20155D8481998-10-27027 October 1998 Application for Amend to License NPF-3,revising Existing TS SRs 4.8.2.3.2.d,4.8.2.3.2.e,4.8.2.3.2.f & Table 4.8-1 Re Testing of 125 Volt DC Station Batteries & Applicable TS Bases ML20151W2811998-09-0808 September 1998 Application for Amend to License NPF-3,permitting Use of Framatome Cogema Fuels M5 Advanced Alloy Fuel Rod Cladding & Fuel Assembly Spacer Grids ML20151W2851998-09-0808 September 1998 Application for Amend to License NPF-3,revising TS Section 3/4.7.6, Plant Systems - CREVS & Associated Bases ML20236G6461998-06-29029 June 1998 Application for Amend to License NPF-3,transferring Operating Authority for DBNPS from TE & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Marked Up License,Safety & Environ Assessments Included ML20236R2301998-06-29029 June 1998 Resubmitted Application for Amend to License NPF-3, Transferring Operating Authority for DBNPS from Teco & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Safety Assessment & EA Included ML20217P8671998-04-24024 April 1998 Application for Amend to License NPF-3,modifying Existing TS 3/4.3.1.1,3/4.3.2.1,3/4.3.2.2 & Associated Bases by Relocating Tables of Response Time Limits from TS to Plant USAR Technical Requirements Manual ML20217P8251998-04-24024 April 1998 Application for Amend to License NPF-3,clarifying Discussion of Margin Between RPS High Pressure Trip Setpoint & Lift Setting for Pressurizer Code Safety Valves ML20203L0861998-02-26026 February 1998 Application for Amend to License NPF-3 to Revise TS 3/4.4.5 & TS 3/4.4.6.2,incorporating New Repair Roll Process for SG Tubes W/Defects in Upper Tube Sheet ML20197J2511997-12-23023 December 1997 Application for Amend to License NPF-3.Amend Changes TS Definitions 1.12,TS 3/4.9.5 & New TS 3.0.6 ML20197J5861997-12-23023 December 1997 Application for Amend to License NPF-3,revising TS Surveillance Requirements for ISI Requirements of Internal Auxiliary Feedwater Header,Header to Shroud Attachment Welds & External Header Thermal Sleeves ML20217R2801997-08-26026 August 1997 Application for Amend to License NPF-3,clarifying LCO 3.6.1.3.a & Revising Surveillance Requirement 4.6.1.3.c ML20217R2831997-08-26026 August 1997 Application for Amend to License NPF-3,modifying TS 3.2.5 Action Statement to Require Power Reduction to Less than 5% of Rated Thermal Power within Four Hrs If RCS Flow Rate Is Less than Specified Limit for Greater than Two Hrs ML20217G5931997-07-29029 July 1997 Suppl 950929 to Application for Amend to License NPF-3, Change TS 3/4.4.3 Re Safety Valves & Pilot Operated Relief valve-operating & Associated Bases 3/4.4.2 & 3/4.4.3 ML20141F1051997-06-24024 June 1997 Application for Amend to License NPF-3,deleting Requirements for Safety Features Actuation Sys Containment High Radiation Monitors ML20138A3201997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Conversion to 24-month Fuel Cycle ML20138C3131997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Rev to TS 3/4.7.6 to Include New Required Actions in Event That One or Both Channels of Radiation Monitoring Instrumentation Becomes Inoperable ML20137M1061997-03-31031 March 1997 Application for Amend to License NPF-57,revising TS to Improve Consistency Between TS & Plant Configuration, Operation & Testing & Complete Required CA to Resolve TS Discrepancies Identified in CA Program ML20138M1251997-02-14014 February 1997 Application for Amend to License NPF-3,requesting Delay of Heat Removal Sys Valve Pit Surveillance Requirements ML20134D7461997-01-30030 January 1997 Application for Amend to License NPF-3,revising SR Intervals from 18 to 24 Months Based on Results of DBNPS Instrument Drift Study & TS 2.2, Limiting Safety Sys Settings, Based on Results of Revised Framatome RPS Instrument String Error ML20134B0561997-01-20020 January 1997 Application for Amend to License NPF-3,involving TS 3/4.5.3 Re ECCS Subsystems ML20132C7771996-12-13013 December 1996 Application for Amend to License NPF-3,authorizing Transfers of Control ML20132B6871996-12-11011 December 1996 Application for Amend to License NPF-3,revising TS Definitions,Instrumentation TS & ECCS TS for Conversion to 24 Month Fuel Cycle ML20134F1851996-10-28028 October 1996 Application for Amend to License NPF-3,requesting Revisions to 3/4.8.1.1,3/4.8.1.2,3/4.8.2.3,3/4.8.2.4 & 3/4.8 Re Electrical Power Systems ML20117P5301996-09-17017 September 1996 Application for Amend to License NPF-3,supporting Conversion of DBNPS from 18 Month to 24 Month Fuel Cycle ML20117N8441996-09-12012 September 1996 Application for Amend to License NPF-3,revising Reactivity Control Systems & Emergency Core Cooling Systems ML20117M1971996-09-0404 September 1996 Application for Amend to License NPF-3,App A,Modifying TS 6.2.3 by Removing Specific Overtime Limits & Working H from TS Consistent W/Nrc Recent Determination,On Generic Basis, That Limits Need Not Be Specified ML20116K2601996-08-0707 August 1996 Application for Amend to License NPF-3,changing Tech Specs 1.0, Definitions, Bases 3/4.0, Applicability & 3/4.6.2.1, Containment Sys - Depressurization & Cooling Sys - Containment Spray Sys ML20117K1871996-05-28028 May 1996 Application for Amend to License NPF-3,revising TS 3/4.3.1.1 RPS Instrumentation & TS 3/4.3.2.2 - Anticipatory RTS Instrumentation to Increase Trip Device Test Interval ML20107L3541996-04-18018 April 1996 Application for Amend to License NPF-3,requesting NRC Review & Approval to Use Alternate Electrical Lineup.Station Blackout DG as Standby Emergency Power Source to Supply Loads Normally Supplied by EDG 1,while Being Reworked ML20101M1601996-03-29029 March 1996 Application for Amend to License NPF-3,App A,Re Surveillance Requirements for Charcoal Filter Lab Testing to Revise Testing Methodology Used to Determine Operability of Charcoal Filters in ESF Air Handling Units ML20101C6911996-03-0606 March 1996 Application for Amend to License NPF-3,revising TS 3/4.5.2 to Allow Deferment of SR 4.5.2.b for ECCS Flowpath Containing HPI 1-2 Pump Until 10th Refueling Outage, Scheduled to Begin 960408 ML20100E0051996-02-0505 February 1996 LAR 93-0003 to License NPF-3,revising Table 3.3-3 of TS 3/4.3.2.1 Re Safety Features Actuation Sys Instrumentation to More Accurately Reflect Design & Actuation Logic of Plant Sequencers & Undervoltage Relays ML20095F5861995-12-12012 December 1995 Application for Amend to License NPF-3,revising TSs Re Containment Sys ML20098C5131995-10-0202 October 1995 Application for Amend to License NPF-3,revising TS Section 5.0,design Features & Adopting Improved STS for B&W Plants Format & Content ML20098C1071995-09-29029 September 1995 Application for Amend to License NPF-3,modifying TS 3.4.3 & Associated Bases for Pressurizer Code Safety Valve Lift Setpoint Tolerances ML20098C3931995-09-29029 September 1995 Application for Amend to License NPF-3,revising Tech Spec 3/4.1.2.8, Reactivity Control Sys - Borated Water Sources - Shutdown, Tech Spec 3/4.1.2.9, Reactivity Control Sys - Operating & TS 3/4.5.1, ECCS - Core Flooding Tanks 1999-09-07
[Table view] |
Text
. .
~
.f TOLEDO
%ms EDISON RCHARO P. CROUSE Vce prenders Docket No. 50-346 $,w License No. NPF-3 Serial No. 1155 May 29, 1985 Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz Operating Reactor Branch No. 4 Division of Licensing United States Nuclear Regulatory Commission
' Washington, DC 20555
Dear Mr. Stolz:
Under separate cover, we are transmitting three (3) original and forty (40) conformed copies of an application for Amendment to Facility Operating License Nc. NPF-3 for the Davis-Besse Nuclear Power Station Unit No. 1.
-This application requests that the Davis-Besse Nuclear Power Station Unit 1 Technical Specifications, Appendix A, be revised to reflect the changes attached. The proposed' changes involve Table 4.3-1.
The attachment identifies the proposed change and its safety evaluation
.and a significant hazard consideration. The proposed change provides for testing to independently confirm the operability of the shunt and under-voltage trip devices of the control rod drive trip breakers.
Toledo Edison requests that this amendment request be granted by January, 1986.
Enclosed is a check for $150 as required by 10CFR170.12(C) for license application.
Very truly yours, B P %Q +
RPC LCS: GAB f'
Attachment i p cc: DB-1 NRC Resident Inspector State of Ohio U g g 4
~
8506040126 850529 !
PDR ADOCK 05000346 P PDR THE TOLEDO EDISCN COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43052 1
_ _ _ _ _ _ _ _ _ _ . _ _ ___________________.._____________________d
r a .
- APPLICATION FOR AMENDMENT TO FACILITY OPERATING LICENSE NO. NPF-3 FOR DAVIS-BESSE NUCLEAR POWER STATION UNIT NO. 1 Enclosed are forty-three (43) copies of the requested changes to the Davis-Besse Nu: lear Power Station Unic No. 1 Facility Operating License No. NPF-3, together with the Safety Evaluation for the requested change.
The proposed changes include Table 4.3-1.
t By /s/ Terry D. Murray Terry D. Murray Assistant Vice President, Nuclear Operations t'
For R. P. Crouse Vice President, Nuclear Sworn and subscribed before me this 29th day of May, 1985.
/s/ Laurie A. Hinkle, nee (Brudzinski)
Notary Public -- State of Ohio My Commission Expires May 16, 1986 SEAL.
m - c , - , -,.m.,m--,- - - - - - . - - - - - - , - - ,- , - - - - - , , - -
Docket No. 50-346 License No. NPF-3
-Serial No. 1155 May 29. 1985 Attachment I. Changes to-Davis-Besse Nuclear Power Station Unit 1, Appendix A Technical Specifications Table 4.3-1 A. Time required to Implement. This change is to be effective upon NRC approval.
B. Reason for Change (Facility Change Request 85-0064, Rev. A).
This request is in response to the requirement in the Supplemental Safety Evaluation Report for Davis-Besse Unit 1 Generic Letter 83-28, Item 4.3, Reactor Breaker Automatic Shunt Trip. The attached change
'for Table 4.3-1 for testing to confirm the OPERABILITY of the shunt and undervoltage trip devices.
C. Safety Evaluation (See Attached)-
D. Significant Hazard Consideration (See. Attached)
e ,
e ..; ...
F SAFETY EVALUATION
. INTRODUCTION:
This'FCR is a result of a directive'from the NRC in.their safety evaluation report.on our addition of the shunt trip device in each of four Reactor
. Trip Breakers.(FCR 84-0026, Rev. A).
REFERENCE:
NRC Supplement Safety Evaluation Report Log No. 1683.
~ '
-' B&W report on " Review of On-Line Test Intervals. for the Reactor Trip
' System."
'FCR 84-0026 (Rev. A) Addition of the shunt trip devices to each Reactor Trip Breaker.
DISCUSSION:
The directive states, "We require that technical specification explicitly note that testing independently confirms the operability of the shunt and undervoltage trip attachments (devices)." The term attachment applies to a Westinghouse breaker, whereas the term devices applies to our GE breakers.
The. safety function of the technical specification is to provide.a surveil-lance schedule for testing the reactor trip breakers, to assure the operability' requirements of the reactor trip system are met.
LThe. safety. function of the reactor trip breakers is to remove the power from the Control Rod Drive Mechanisms (CRDMS) allowing the safety &
. regulating rods to drop into the core, bringing the' reactor to a sub-
, ' critical condition whenever it receives'an automatic trip command signal-(undervoltage conditions) from the Reactor Protection System (RPS),
Anticipatory Reactor Trip Systems (ARTS). or a manual trip command signal; from the: operator. (
Reference:
FSAR para. 7.4.1.1). .The function of the
' shunt trip device is to provide additional assurance that the reactor trip breakers will open'when required. There is no. safety function associated.
, with the shunt trip devices.
The. addition to the Davis-Besse' Unit 1 technical specification,should not
-result in additional-testing.as procedures have previously been modified to incorporate the requirement to independently confirm the shunt and undervoltage trip device. This was accompli-hed following the addition of the shunt! trip' devices. We had made the interpretation that this was
~
necessary to meet the existing technical specification operability require-ments.
~
lThe only function of.this FCR is to meet the directive to incorporate the frequired verbiage in the technical specification.
.The frequency of testing as a result of'the independent verification was addressed by the B&W Owners Group in their report entitled " Review of On-Line. Test Intervals for the' Reactor Trip Systems."
g
+
This report concluded:
"The wearout evaluation indicated that the RTS components are not susceptible to wearout caused by testing. The breakers are the major components affected by test cycling and the GE AK-2 breaker has a design cycle objective of 12,500 cycles. Aging of the trip shaft bearing lubricant is virtually eliminated as a concern when the Mobil 28 lubricant is installed." (This is completed at Davis-Besse.)
"Therefore, for the breakers, common mode failure due to wearout is not a significant source of RTS unavailability. Other components do not exhibit histories that indicate that wearout is a concern.
Reduced redundancy caused by testing does not significantly contribute to RTS unavailability. Reduced redundancy is primarily due to bypass testing of the RPS and ARTS sensor strings, which has the effect of reducing the trip logic from 2/4 to 2/3 for the duration of the tests. Other on-line tests (breakers, electronic trip, trip modules) are performed with the channel tripped and, therefore, in a " fail-safe" condition that does not affect (RTS) unavailability."
CONCLUSION:
Additional testing should not result from this technical specification change as Station procedures already include the requirement to independently confirm the operability of the shunt and undervoltage trip devices.
Surveillance testing now require 3 trips per month or 36 per year. The design number of cycles 12,500 over the 40 year plant life allows for an average of 312 per year. This margin is more than sufficient to allow for-reactor trips and bench testing (the 12 month schedule for maintenance of the breakers.)
Based on this, the technical specification change will not result in an unreviewed safety question.
s
Significant Hazard Consideration This amendment request to add surveillance requirements for testing to confirm the OPERABILITY of the SHUNT and UNDERVOLTAGE trip devices does not involve a Significant Hazard.
Resulting from the Salem ATWS event and Generic Letter 83-28, Licensees were requested, as part of their response, to review their Technical Specifications and submit any needed changes. The attached amendment request provides Toledo Edisons changes to their Technical Specifications.
These changes provide that testing independently confirms the operability of the shunt and undervoltage trip' attachments (devices). 'These devices are checked as part of the monthly channel functional test and before start up if the surveillance has not.been performed in the past seven days.
These. changes are an additional testing requirement, not presently included in the Technical Specifications, to be performed to ensure the safety function of the reactor trip breakers.
The Commission has provided guidance concerning the application of the standards in 10 CFR 50.92 by providing certain examples (48 FR 14870).
One of the examples of actions involving no significant hazards consider-ations relates to a c.hange that constitutes an additional limitation, restriction, or control not presently included in the technical specifi-cations: for example, a more stringent surveillance' requirement. The testing of the reactor trip breaker is an additional testing limitation not presently included in our Technical Specifications.
Therefore, based on the above, this. amendment request is not a Significant Hazard.