Category:Letter
MONTHYEARIR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 IR 05000313/20244042024-08-29029 August 2024 Cybersecurity Inspection Report 05000313/2024404 and 05000368/2024404 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) ML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 ML24128A2472024-05-0808 May 2024 Project Manager Assignment ML24017A2982024-04-18018 April 2024 Summary of Regulatory Audit Regarding the License Amendment Request to Revise Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information IR 05000313/20243012024-04-16016 April 2024 NRC Examination Report 05000313/2024301 ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML24102A1342024-03-12012 March 2024 AN1-2024-03 Post Exam Submittal IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 ML24012A0502024-02-0202 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0054 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 – Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation 2024-09-09
[Table view] Category:License-Operator Examination Report (Non-Power Reactors Only)
MONTHYEARIR 05000313/20063012006-02-15015 February 2006 Er 05000313-06-301; January 12, 2006; Arkansas Nuclear One, Unit 1; Retake Examination 2006-02-15
[Table view] |
Text
February 15, 2006Jeffrey S. ForbesVice President Operations Arkansas Nuclear One Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72801-0967SUBJECT:ARKANSAS NUCLEAR ONE, UNIT 1 - NRC RETAKE EXAMINATIONREPORT 05000313/2006301
Dear Mr. Forbes:
On January 12, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed anexamination at your Arkansas Nuclear One, Unit 1. The enclosed examination report documents the examination results, which were discussed on January 12, 2006, with Mr. Randall Martin of your staff.The examination included the evaluation of one applicant for senior operator license. Thewritten examination was developed using NUREG-1021, "Operator Licensing ExaminationStandards for Power Reactors," Revision 9. The license examiner determined that the applicant satisfied the requirements of 10 CFR Part 55, and the appropriate license has been issued.In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letterand its enclosure will be available electronically for public inspection in the NRC PublicDocument Room or from the Publicly Available Records (PARS) component of NRC'sdocument system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/Anthony T. Gody, ChiefOperations Branch Division of Reactor SafetyDockets: 50-313Licenses: DPR-51 Entergy Operations, Inc.-2-
Enclosure:
Examination Report 05000313/2006-301 w/Attachment Supplemental Information
REGION IV Docket:50-313License:DPR-51 Report No.:05000313/2006-301 Licensee:Entergy Operations, Inc.
Facility:Arkansas Nuclear One, Units 1 and 2Location:Junction of Hwy. 64W and Hwy. 333 South Russellville, Arkansas Dates:January 12, 2006 Inspector:Gary W. Johnston, Senior Operations Engineer, Operations Branch Approved By:Anthony T. Gody, ChiefOperations Branch Division of Reactor Safety Enclosure-2-
SUMMARY OF FINDINGS
IR 05000313/2006-301; January 12, 2006; Arkansas Nuclear One, Unit 1; Retake Examination.The NRC examiner evaluated the competency of one applicant for senior operator license atArkansas Nuclear One, Unit 1. The licensee developed the examination using NUREG-1021,"Operator Licensing Examination Standards for Power Reactors," Revision 9. The written examination was administered by the facility to the applicant on January 12, 2006. Theexaminer determined that the applicant satisfied the requirements of 10 CFR Part 55, and theappropriate license has been issued.
A. NRC-Identified and Self-Revealing Findings
None.
B. Licensee-Identified Violations
None.
Enclosure-3-
REPORT DETAILS
4.OTHER ACTIVITIES (OA)4OA5Other Activities (Initial Operator License Examination).1Operator Knowledge and Performance
a. Examination Scope
This examination was a retake of the written examination from the September 12, 2005,examination where the applicant passed the original operating examination and,therefore, no portions of an operating examination were administered during this retake examination. On January 12, 2006, the licensee administered the examination to the applicant. Thelicensee staff graded the examination, analyzed the results, and presented their analysisto the NRC on January 16, 2006.
b. Findings
No findings of significance were identified..2Initial Licensing Examination Development
a. Examination Scope
The licensee developed the examination in accordance with NUREG-1021, Revision 9. All licensee facility training and operations staff involved in examination preparation andvalidation were on a security agreement. The facility licensee submitted the written examination outline on October 15, 2005. The chief examiner reviewed the outlineagainst the requirements of NUREG-1021, Revision 9, and provided comments to thelicensee. The facility licensee submitted the draft examination on November 15, 2005. The chief examiner reviewed the draft examination against the requirements of NUREG-1021, Revision 9, and provided comments to the licensee on the examinationon November 28, 2005. The licensee satisfactorily completed comment resolution on November 28, 2005.
b. Findings
The NRC approved the initial examination outline and advised the licensee to proceedwith examination development.The examiner determined that the examination initially submitted by the licensee waswithin the range of acceptability expected for a proposed examination.No findings of significance were identified.
-4-3.Examination Security
a. Examination Scope
The examiners reviewed examination security for examination development andadministration with respect to NUREG-1021 requirements.
b. Findings
No findings of significance were identified.4OA6Meetings, Including ExitThe chief examiner presented the examination results to Mr. Randall Martin on January 12, 2006. The licensee acknowledged the findings presented. The licensee did not identify any information or materials used during the examinationas proprietary.ATTACHMENT:
SUPPLEMENTAL INFORMATION
AttachmentA-1SUPPLEMENTAL INFORMATIONKEY POINTS OF CONTACT
Licensee Personnel
- Randall Martin, Supervisor, Unit 1, Operations Training