ML19235A317

From kanterella
Revision as of 00:12, 5 September 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
C-10 Research and Education Foundation, Inc. Rebuttal Statement of Position on C-10's Contentions Regarding Nextera'S Program for Managing ASR at Seabrook Station Nuclear Power Plant
ML19235A317
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 08/23/2019
From: Curran D
C-10 Research & Education Foundation, Harmon, Curran, Harmon, Curran, Spielberg & Eisenberg, LLP
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-443-LA-2, ASLBP 17-953-02-LA-BD01, RAS 55199
Download: ML19235A317 (8)


Text

August 23, 2019 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD _____________________________________ ) In the Matter of ) NextEra Energy Seabrook, LLC ) Docket No. 50-443 (Seabrook Station, Unit 1) ) _____________________________________) C-10 RESEARCH AND EDUCATION FOUNDATION, INC. REBUTTAL STATEMENT OF POSITION ON C- AT SEABROOK STATION NUCLEAR POWER PLANT I. INTRODUCTION Pursuant to 10 C.F.R § 2.1207(a)(2February 15, 2018 Revised Scheduling Order, C-10 Research and Education Foundation, Inc. - hereby submits its Rebuttal Statement of Position on C-contentions A, B, C, D, and H. These contentions challenge the adequacy of a license , LLC pernicious effects of Alkali Silica Reactsafety structures, including the containment. This Rebuttal Statement of Position is supported by the attached Rebuttal Testimony of C-Dr. Victor E. Saouma, one of the .1 Revised Appendix A, a list of all of C-also attached. 1 Rebuttal Testimony of Victor E. Saouma, Ph.D Regarding Scientific Evaluation of Aging Management Program for Alkali-Silica Reaction at the Seabrook Nuclear Power Plant Exh. INT028) (Proprietary) . A non-proprifiled as soon as possible.

2 The testimony and position statements submitted by NextEra and the U.S. Nuclear NRC Staff fail to overcome Dr. Saouthorough and well-supported criticisms structures.2 ASR at Seabrook and devise a long-term monitoring plan for ASR was far from adequate to Given the complexity of ASR and its potential to compromise the ability of critical safety structures like the Containment Enclosure Building to withstand a design-basis earthquake, NextEra should have taken a more scientific approach and consulted experts in the field, including obtaining independent peer review of its work. As a result -to-date sophisticated approach to the ASR problem, it failed to obtain meaningful data or conduct analyses that could adequately support the proposed monitoring, acceptance criteria, and inspection intervals in the LAR. Therefore, the ASLB does not have a basis in this record for a reasonable assurance finding or the approval of the LAR. Under the circumstances, the ASLB should order the reversal of the LAR and to refer to the Commission the question of whether the license renewal decision should also be reversed for its dependence on the seriously deficient LAR. 2 Witnesses Michael Collins, John Simons, Christopher Bagley, Oguzhan Bayrak, and Edward Carley (July 24, 2019) (Exhibit NER001) (MPR Testimony); Testimony of NextEra Witnesses Said Bolourchi, Glenn Bell, and Matthew Sherman (July 24, 2019) (Exhibit NER004) (SGH Testimony); NRC Staff Testimony of Angela Buford, Bryce Lehman, and George Thomas (July 24, 2019) (Exhibit NRC001) (NRC Staff Testimony); NRC Staff Testimony of Jacob Phillip (July 24, 2019) (Exhibit NRC005) (Phillip Testimony).

3 II. EVALUATING COMPLIANCE WITH REASONABLE ASSURANCE STANDARD the Commission takes a case-by-case approach, exercising sound technical judgment and verifying circumstances. NextEra SOP at 5 (citing Amergen Energy Company, LLC, (Oyster Creek Nuclear Generating Station), CLI-09-7, 69 NRC 235, 262, n.143 (2009); Entergy Nuclear Generation Co. (Pilgrim Nuclear Power Station), CLI-10-14, 71 NRC 449, 465-66 (2010)). Here, where the NRC has no regulatory standard for ASR, and industry codes even lack standard for ASR, the ASLB must evaluate all of the evidence presented, relying on the testimony of qualified experts to determine whether the reasonable assurance standard has been met. The record demonstrates that Dr. Saouma is the only expert witness to testify in this proceeding who has extensive scientific and engineering experience in the study of ASR. ependent peer review by qualified scientists, other than a very limited peer review of a single issue. See testimony should be given great weight in comparison to the testimony by expert witnesses for NextEra and the Staff, who are all engineers lacking any particular experience with the measurement or evaluation of ASR. Carolina Power & Light Co. (Shearon Harris Nuclear Power Plant), LBP-01-09, 53 NRC 239, 251 (2001) expertise). Dr. Saouma has presented two thorough and well-documented pieces of testimony that abrook for its lack of 4 sophistication or effectiveness in diagnosing ASR at Seabrook or establishing an effective monitoring program. As he summarized on rebuttal: [T]he work done by NextEra is insufficient to characterize the current condition of ASR at Seabrook or to support a monitoring plan that can identify and assess ASR progression during the 30 years of future operation for which Seabrook has been licensed. As I have repeatedly testified, the simplistic methods used by NextEra to gather data and assess the condition of ASR at Seabrook are fundamentally inadequate to address such a complex problem with such significant safety implications. NextEra effectively put on blinders to a wide range of available techniques and sources of outside expertise, choosing instead to take a code-based engineering approach that could only scratch at the problem. As a result, the basic safety of the population living within 10 miles of Seabrook cannot be reasonably assured. Saouma Rebuttal Testimony, B.1 at 8. Dr. Saouma a set of more modern and effective alternative methods for gathering and analyzing data about ASR (i.e., accelerated expansion tests, periodic damage rating index (DRI) measurements, detailed petrographic studies, and modern computational methods).Id. In offering these alternatives, Dr. Saouma has not made a bid for perfection; and See NextEra SOP at 5, NRC Staff SOP at 31. Instead, as Dr. Saouma explained, way to do the job, or even just a better way. It is demonstrably effective (for example, Hydro-Quebec), in contrast to the demonstrably ineffective measures used by NextEra. Saouma Rebuttal Testimony, B.1 at 8. Given these extremely serious and fundamental inadequacies, the LAR must be rejected and NextEra must be sent back to the drawing board to conceive a new program for assessing and monitoring ASR. III.

SUMMARY

OF KEY POINTS IN REBUTTAL TESTIMONY Question E.1 as follows:

5 1. -based engineering approach rather than a combination of scientific and engineering approaches as is required for a problem with the complexity of ASR in the concrete enclosure of a nuclear reactor. The contrast can be seen by comparing the Seabrook ASR project to Hydro-the Gentilly-2 nuclear plant, a much more sophisticated and effective investigation. 2. lack of sufficient expertise in the field of ASR assessment and analysis. This lack of expertise was compounded by a failure to obtain indepework. 3. -based-engineering approach may comply with the 1971 ACI code. However, the corresponding margin of error has not been quantified and is likely to be unacceptable. This makes it too risky to be adopted. 4. ACI 318-71, is not an adequate tool because it stipulates linear elastic analysis rather than inelastic (i.e., nonlinear) analysis. Use of nonlinear analysis is common and widely performed in the 21st century for complex structures such as Seabrook (as in the post-mortem investigation of Crystal-River). It should have been employed at Seabrook. 5. The finite element simulation used by NextEra is very rudimentary, completely inappropriate modeling of the ASR and the possible in-plane degradation. NextEra has failed to recognize some of the key characteristics of ASR, namely the driving force of relative humdity, the relationship between the characteristics of aggregates to both the nature of cracks and the timing of their development, the kinetics of the ASR reaction, the degradation of concrete mechanical properties in the SEM, and the lack of uniformity in the location and progression of ASR. NextEra also fails to acknowledge that the 6 progression of ASR over time follows a sigmoid curve and is not lto account for all these factors plays a significant role in undermining the reliability of its assessment of ASR. 6. Dr. Saouma does not give much credence to the shear tests for the purpose of assessing the impact of ASR and the ultimate strength of the beam. Those results could have been easily anticipated and confirmed by proper finite element studies (i.e., they were un-necessary). On the other hand, a by-product was the development of the inspection methodology. 7. The environmental conditions under which the CI and through crack extension were measured in the laboratory do not correspond to the conditions at the Seabrook Plant. As a result, the extent of internal expansion will most certainly be misleading. Furthermore, NextEra failed to recognize the impact of the reinforcement close to the surface of the wall that would inhibit crack opening. 8. Due to the confinement, the expansion will be radial, hence the cracking will be internal and propagate vertically (along the lines of compression). Furthermore, it will seldom daylight to be captured by CI. Hence, the walls of the CEB could very well delaminate internally, and this delamination will either not be captured by the instrumentation, or not captured in a timely way. 9. The ten-year effort to understand ASR at Seabrook and establish a program to adequately current license term and a 20-year renewal term) has fallen far short of providing a reasonable assurance that NRC seismic design requirements are satisfied and that the public will be protected in the event of an earthquake. Yet, some progress has been made, especially in the program to install extensometers for more accurate monitoring.

7 10. In expert opinion, NextEra should return to the drawing board, applying greater expertise, collecting more meaningful data, and using more appropriate and commensurate scientific and engineering approaches. Some of the work that has been done will still be useful and should be expanded on, such as the use of extensometers. But overall, the investigation should take a new approach that is more scientific, rigorous and sophisticated and subject it to a panel of independent expert reviewers in various related disciplines. IV. CONCLUSION Opening Testimony and Rebuttal Testimony, NextEra has failed to satisfy its burden of providing that its LAR contains an adequate assessment of the condition of ASR at the Seabrook nuclear power plant, or that it can be monitored in an effective way. As a result, affected members of the public lack a reasonable assurance that their safety will be protected during the next 30 years of operation. In particular, NextEra has failed to demonstrate that the CEB will not crack or otherwise fail during a design-basis earthquake at the plant. For these reasons, C-10 requests the ASLB to:  ; and b) notify the Commission that the reversal of the LAR should have the effect of nullifying the license renewal decision.

8 Respectfully submitted, ___/signed electronically by/__ Diane Curran Harmon, Curran, Spielberg, & Eisenberg, L.L.P. 1725 DeSales Street N.W., Suite 500 Washington, D.C. 20036 240-393-9285 dcurran@harmoncurran.com August 23, 2019