MONTHYEARML23165A2342023-03-0303 March 2023 News Release-23-019: NRC Issues Annual Assessments for Nations Nuclear Power Plants ML22273A1282022-09-30030 September 2022 News Release-II-22-025: NRC Monitoring Hurricane Ian Press Release-II-22-015, NRC Schedules Public Meeting to Discuss V.C. Summer Nuclear Power Plant Performance2022-04-28028 April 2022 Press Release-II-22-015: NRC Schedules Public Meeting to Discuss V.C. Summer Nuclear Power Plant Performance Press Release-II-21-007, NRC Hosts Virtual Meeting to Discuss 2020 Safety Performance of V.C. Summer, North Anna and Surry Nuclear Power Plants2021-04-19019 April 2021 Press Release-II-21-007: NRC Hosts Virtual Meeting to Discuss 2020 Safety Performance of V.C. Summer, North Anna and Surry Nuclear Power Plants Press Release-II-20-016, NRC Names New Senior Resident Inspector at Summer Nuclear Power Plant2020-05-26026 May 2020 Press Release-II-20-016: NRC Names New Senior Resident Inspector at Summer Nuclear Power Plant Press Release-II-20-005, NRC Schedules Virtual Meeting to Discuss 2019 Safety Performance of Summer Nuclear Power Plant2020-03-26026 March 2020 Press Release-II-20-005: NRC Schedules Virtual Meeting to Discuss 2019 Safety Performance of Summer Nuclear Power Plant Press Release-II-19-018, NRC Schedules Open House to Discuss Summer Nuclear Power Plant Performance2019-04-17017 April 2019 Press Release-II-19-018: NRC Schedules Open House to Discuss Summer Nuclear Power Plant Performance Press Release-II-18-012, NRC to Hold Open House to Discuss 2017 Performance of Summer Nuclear Power Plant2018-04-17017 April 2018 Press Release-II-18-012: NRC to Hold Open House to Discuss 2017 Performance of Summer Nuclear Power Plant Press Release-II-17-043, NRC Names New Resident Inspector at Summer Nuclear Plant2017-08-31031 August 2017 Press Release-II-17-043: NRC Names New Resident Inspector at Summer Nuclear Plant Press Release-II-17-010, NRC to Discuss 2016 Summer Nuclear Performance and Construction2017-03-22022 March 2017 Press Release-II-17-010: NRC to Discuss 2016 Summer Nuclear Performance and Construction Press Release-II-16-023, NRC Schedules Open House to Discuss 2015 Summer Nuclear Plant Performance and Construction Inspections of New Units2016-04-14014 April 2016 Press Release-II-16-023: NRC Schedules Open House to Discuss 2015 Summer Nuclear Plant Performance and Construction Inspections of New Units Press Release-16-011, NRC Issues Annual Assessments for Nation'S Nuclear Plants2016-03-0404 March 2016 Press Release-16-011: NRC Issues Annual Assessments for Nation'S Nuclear Plants Press Release-15-068, NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors2015-10-27027 October 2015 Press Release-15-068: NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors Press Release-15-025, NRC Issues Violations, Proposed Fine for Actions Related to Reactor Construction Incident at Chicago Bridge & Iron2015-04-21021 April 2015 Press Release-15-025: NRC Issues Violations, Proposed Fine for Actions Related to Reactor Construction Incident at Chicago Bridge & Iron Press Release-II-15-019, NRC Schedules Meetings to Discuss Agency'S Assessment of Summer Nuclear Plant Unit 1 Operation and Units 2 and 3 Construction2015-04-0707 April 2015 Press Release-II-15-019: NRC Schedules Meetings to Discuss Agency'S Assessment of Summer Nuclear Plant Unit 1 Operation and Units 2 and 3 Construction Press Release-II-15-011, NRC Schedules Meeting with Southern and Scana to Discuss Inspections and Testing of New Nuclear Units at the Vogtle and Summer Sites2015-03-17017 March 2015 Press Release-II-15-011: NRC Schedules Meeting with Southern and Scana to Discuss Inspections and Testing of New Nuclear Units at the Vogtle and Summer Sites Press Release-II-15-004, NRC Begins Special Inspection at Summer Nuclear Plant Unit 2 Construction Site2015-02-23023 February 2015 Press Release-II-15-004: NRC Begins Special Inspection at Summer Nuclear Plant Unit 2 Construction Site Press Release-14-058, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2014-09-0404 September 2014 Press Release-14-058: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-II-14-034, NRC Assigns New Resident Inspector for Summer Nuclear Power Plant Construction2014-06-16016 June 2014 Press Release-II-14-034: NRC Assigns New Resident Inspector for Summer Nuclear Power Plant Construction Press Release-II-14-010, NRC Schedules Meetings to Discuss Agency'S Assessment of Summer Nuclear Plant Unit 1 Operation and Units 2 and 3 Construction2014-03-18018 March 2014 Press Release-II-14-010: NRC Schedules Meetings to Discuss Agency'S Assessment of Summer Nuclear Plant Unit 1 Operation and Units 2 and 3 Construction Press Release-II-14-009, NRC Issues Confirmatory Order to Summer Nuclear Power Plant; Prohibits Former Contract Employee from NRC-Licensed Activities for Five Years2014-03-11011 March 2014 Press Release-II-14-009: NRC Issues Confirmatory Order to Summer Nuclear Power Plant; Prohibits Former Contract Employee from NRC-Licensed Activities for Five Years Press Release-13-073, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2013-09-0606 September 2013 Press Release-13-073: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-II-13-025, NRC Schedules Regulatory Conference to Discuss Apparent Construction Violation at New Summer Nuclear Units2013-04-22022 April 2013 Press Release-II-13-025: NRC Schedules Regulatory Conference to Discuss Apparent Construction Violation at New Summer Nuclear Units Press Release-II-13-012, NRC Schedules Meetings to Discuss Performance of Summer Nuclear Plant Oversight of New Unit Construction2013-04-0808 April 2013 Press Release-II-13-012: NRC Schedules Meetings to Discuss Performance of Summer Nuclear Plant Oversight of New Unit Construction Press Release-II-12-068, NRC Schedules Public Meeting to Discuss Oversight of New Summer Nuclear Power Plant Units2012-12-28028 December 2012 Press Release-II-12-068: NRC Schedules Public Meeting to Discuss Oversight of New Summer Nuclear Power Plant Units Press Release-II-12-045, NRC Names Resident Inspectors for Summer Nuclear Plant Construction Activities2012-07-0202 July 2012 Press Release-II-12-045: NRC Names Resident Inspectors for Summer Nuclear Plant Construction Activities Press Release-II-12-033, NRC Schedules Meetings to Discuss 2011 Performance of Summer Nuclear Power Plant and Oversight of Construction at New Units2012-05-10010 May 2012 Press Release-II-12-033: NRC Schedules Meetings to Discuss 2011 Performance of Summer Nuclear Power Plant and Oversight of Construction at New Units Press Release-12-034, NRC Concludes Hearing on Summer New Reactors, Combined Licenses to Be Issued2012-03-30030 March 2012 Press Release-12-034: NRC Concludes Hearing on Summer New Reactors, Combined Licenses to Be Issued Press Release-II-11-062, NRC Names Senior Resident Inspector for Summer Nuclear Plant Construction Activities2011-10-28028 October 2011 Press Release-II-11-062: NRC Names Senior Resident Inspector for Summer Nuclear Plant Construction Activities Press Release-11-197, Opening Remarks of NRC Chairman Gregory B. Jaczko at the Mandatory Hearing for New Reactors at the Virgil C. Summer Site2011-10-12012 October 2011 Press Release-11-197: Opening Remarks of NRC Chairman Gregory B. Jaczko at the Mandatory Hearing for New Reactors at the Virgil C. Summer Site Press Release-11-186, NRC to Hold Mandatory Hearing Regarding Summer New Reactor Application Oct. 12-13 in Rockville, MD2011-10-0303 October 2011 Press Release-11-186: NRC to Hold Mandatory Hearing Regarding Summer New Reactor Application Oct. 12-13 in Rockville, MD Press Release-II-11-051, NRC Names New Senior Resident Inspector at Summer Nuclear Power Plant2011-08-24024 August 2011 Press Release-II-11-051: NRC Names New Senior Resident Inspector at Summer Nuclear Power Plant Press Release-11-150, NRC Issues $15,000 Fine and Confirmatory Order to Professional Service Industries, Inc2011-08-18018 August 2011 Press Release-11-150: NRC Issues $15,000 Fine and Confirmatory Order to Professional Service Industries, Inc Press Release-II-11-036, NRC Schedules Public Meeting for May 26 to Discuss Performance of Summer Nuclear Power Plant2011-05-18018 May 2011 Press Release-II-11-036: NRC Schedules Public Meeting for May 26 to Discuss Performance of Summer Nuclear Power Plant Press Release-11-067, NRC, U.S. Army Corps of Engineers Issue Final Environmental Impact Statement for New Reactors at Virgil C. Summer Site2011-04-19019 April 2011 Press Release-11-067: NRC, U.S. Army Corps of Engineers Issue Final Environmental Impact Statement for New Reactors at Virgil C. Summer Site Press Release-II-10-076, NRC Assigns New Resident Inspector to Summer Nuclear Plant2010-11-0404 November 2010 Press Release-II-10-076: NRC Assigns New Resident Inspector to Summer Nuclear Plant Press Release-II-10-029, NRC Schedules Open House to Discuss 2009 Performance of Summer Nuclear Power Plant2010-04-20020 April 2010 Press Release-II-10-029: NRC Schedules Open House to Discuss 2009 Performance of Summer Nuclear Power Plant Press Release-10-070, NRC Seeks Public Input on Draft Environmental Impact Statement for New Reactors at Virgil C. Summer Site; Meeting May 272010-04-19019 April 2010 Press Release-10-070: NRC Seeks Public Input on Draft Environmental Impact Statement for New Reactors at Virgil C. Summer Site; Meeting May 27 Press Release-II-09-017, NRC Schedules Open House to Answer Questions on 2008 Performance of Summer Nuclear Power Plant2009-04-0303 April 2009 Press Release-II-09-017: NRC Schedules Open House to Answer Questions on 2008 Performance of Summer Nuclear Power Plant Press Release-09-050, NRC Meeting in Blair, S.C., March 28 to Discuss Environmental Review of Summer New Reactor Application2009-03-18018 March 2009 Press Release-09-050: NRC Meeting in Blair, S.C., March 28 to Discuss Environmental Review of Summer New Reactor Application Press Release-09-037, NRC Extends Comment Period to April 6 on Environmental Issues for Summer New Reactor Application2009-02-26026 February 2009 Press Release-09-037: NRC Extends Comment Period to April 6 on Environmental Issues for Summer New Reactor Application Press Release-09-001, NRC Meeting with Public Jan. 27-28 on Environmental Issues for Summer New Reactor Application2009-01-0505 January 2009 Press Release-09-001: NRC Meeting with Public Jan. 27-28 on Environmental Issues for Summer New Reactor Application Press Release-08-186, NRC Announces Opportunity to Participate in Hearing on New Reactor Application for Summer Site2008-10-10010 October 2008 Press Release-08-186: NRC Announces Opportunity to Participate in Hearing on New Reactor Application for Summer Site Press Release-08-146, NRC Accepts Application for New Reactor at Summer2008-08-0606 August 2008 Press Release-08-146: NRC Accepts Application for New Reactor at Summer Press Release-08-120, Summer Application for New Reactors Available on NRCs Website2008-06-26026 June 2008 Press Release-08-120: Summer Application for New Reactors Available on NRCs Website Press Release-II-08-012, NRC to Discuss 2007 Performance of Summer Nuclear Power Plant2008-03-27027 March 2008 Press Release-II-08-012: NRC to Discuss 2007 Performance of Summer Nuclear Power Plant Press Release-II-07-036, - NRC Schedules Conference with Sce&G to Discuss Apparent Violation at Summer Nuclear Station2007-07-0909 July 2007 Press Release-II-07-036 - NRC Schedules Conference with Sce&G to Discuss Apparent Violation at Summer Nuclear Station Press Release-II-07-017, NRC to Discuss 2006 Performance at Summer Nuclear Plant2007-04-11011 April 2007 Press Release-II-07-017: NRC to Discuss 2006 Performance at Summer Nuclear Plant Press Release-II-06-006, NRC to Discuss 2005 Performance at Summer Nuclear Power Plant2006-03-24024 March 2006 Press Release-II-06-006: NRC to Discuss 2005 Performance at Summer Nuclear Power Plant Press Release-II-05-008, NRC to Discuss 2004 Performance at Summer Nuclear Power Plant2005-03-14014 March 2005 Press Release-II-05-008: NRC to Discuss 2004 Performance at Summer Nuclear Power Plant 2023-03-03
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Telephone: 301/415-8200 Washington, D.C. 20555-0001 E-mail: opa.resource@nrc.gov Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No.11-067 April 19, 2011 NRC, U.S. ARMY CORPS OF ENGINEERS ISSUE FINAL ENVIRONMENTAL IMPACT STATEMENT FOR NEW REACTORS AT VIRGIL C. SUMMER SITE The Nuclear Regulatory Commission and the U.S. Army Corps of Engineers (USACE),
Charleston District, have completed the Final Environmental Impact Statement (FEIS) for the Combined Licenses (COL) for the proposed Summer Units 2 and 3 reactors. The NRC concludes in the FEIS that there are no environmental impacts that would preclude issuing the COLs for construction and operation of the proposed reactors at the site, near Jenkinsville, S.C. USACE will use the information in the FEIS in making its federal permit decision in accordance with the Clean Water Act and Rivers and Harbors Act of 1899.
The FEIS will be available on the NRC website at:
http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr1939/. The NRC staff, in cooperation with USACE, began its environmental review with a scoping process that included public meetings near the site in January 2009. The staff issued a draft EIS for the proposed COLs in April 2010 and held public meetings in May 2010 to gather comments on the draft EIS.
The FEIS, with the NRCs conclusions, is also available via the NRCs electronic document database, ADAMS, by entering accession numbers ML11098A044 and ML11098A057 in the ADAMS search engine at: http://wba.nrc.gov:8080/ves. In addition, the Fairfield County Library, at 300 Washington St. in Winnsboro, S.C., will have a hardbound copy of the FEIS available for public inspection.
The NRCs publishing of the FEIS is only part of the overall Summer COL review. The agency staff continues to compile its final safety evaluation report (SER), which will include recommendations from the NRCs Advisory Committee on Reactor Safeguards, an independent group of nuclear safety experts. The NRCs final licensing decision will be based on the FEIS and SER findings, along with a ruling from the five-member Commission that heads the agency.
The applicants, South Carolina Electric & Gas (SCE&G) and Santee Cooper, are applying for licenses to build and operate two Westinghouse AP1000 reactors adjacent to the existing Summer nuclear power plant, approximately 26 miles northwest of Columbia, S.C. The companies submitted the application March 27, 2008, and supplemented the applications environmental report to support their request on Feb. 13, 2009, and July 2, 2010. The AP1000 is a 1,100 MWe pressurized-water reactor design the NRC certified in 2006. The agency is
currently reviewing Westinghouses May 2007 application to amend the certified design. More information regarding the review is available on the NRCs website at:
http://www.nrc.gov/reactors/new-reactors/design-cert/amended-ap1000.html.
News releases are available through a free listserv subscription at the following Web address:
http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRC's website.