MONTHYEARML1013401882010-06-0808 June 2010 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant, Unit 1, Areva Fuel Transition, Areva Fuel Mechanical Design Report Project stage: Withholding Request Acceptance ML1013802442010-06-0808 June 2010 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant, Unit 1, Areva Fuel Transition, Thermal-Hydraulic Design Report Project stage: Withholding Request Acceptance ML1025202302010-09-24024 September 2010 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant, Unit 1, Areva Fuel Transition, GE14 Fuel Thermal Mechanical Information Project stage: Withholding Request Acceptance ML1025203012010-11-0404 November 2010 Letter Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant, Unit 1, Areva Fuel Transition, Unit 1 Cycle 9 Reload Safety Analysis for 105% Original Licensed Thermal Power Project stage: Withholding Request Acceptance ML1101805852011-01-24024 January 2011 Request for Additonal Information Regarding Amendment Request to Transition to Areva Fuel Project stage: Other ML1105900542011-02-23023 February 2011 Response to NRC Request for Additional Information Regarding Amendment Request to Transition to Areva Fuel Project stage: Response to RAI ML11095A0732011-03-28028 March 2011 Request for Additional Information Regarding a Request to Transition to Areva Fuel Project stage: RAI ML11136A1872011-04-26026 April 2011 NRR E-mail Capture - Audit Results Summary Report Supporting TAC ME3775 - BF1 Areva Fuel Transition and Related BF2/3 Request Project stage: Other ML11137A1992011-05-12012 May 2011 Response to NRC Request for Additional Information Regarding to Transition to Areva Fuel Project stage: Response to RAI ML11159A0412011-06-0707 June 2011 NRR E-mail Capture - Audit Results Summary Report Supporting TAC ME3775 - BF1 Areva Fuel Transition and Related BF2/3 Request Project stage: Other ML11234A0042011-08-23023 August 2011 Request for Additional Information Regarding Technical Specification TS-473, Areva Fuel Transition Project stage: RAI ML11286A1072011-10-0707 October 2011 Response to NRC Request for Additional Information Regarding Amendment Request to Transition to Areva Fuel Project stage: Response to RAI ML12018A3762012-01-23023 January 2012 Request for Withholding Information from Public Disclosure for Areva Fuel Transition Documents (TAC No. ME3775)(TS-473) Project stage: Withholding Request Acceptance ML12083A0012012-04-0404 April 2012 Request for Withholding Information from Public Disclosure for Areva Fuel Transition Documents (TAC No. ME3775)(TS-473) Project stage: Withholding Request Acceptance ML1208300592012-04-0404 April 2012 Request for Withholding Information from Public Disclosure for Areva Fuel Transition Documents (TAC No. ME3775) (TS-473) Project stage: Withholding Request Acceptance ML12083A0032012-04-0404 April 2012 Request for Withholding Information from Public Disclosure for Areva Fuel Transition Documents (TAC No. ME3775)(TS-473) Project stage: Withholding Request Acceptance ML12083A0142012-04-0404 April 2012 Request for Withholding Information from Public Disclosure for Areva Fuel Transition Documents (GEH-Harrison) (TAC No. ME3775) (TS-473) Project stage: Withholding Request Acceptance ML12100A1032012-04-11011 April 2012 Audit Report Regarding Tennessee Valley Authority Browns Ferry, Unit 1 Areva Fuel Transition Emergency Core Cooling System Evaluation Model Application (TAC No. ME3775) (Np) Project stage: Other ML12108A2482012-04-17017 April 2012 Request for Withholding Information from Public Disclosure for Areva Fuel Transition Documents (TAC No. ME3775)(TS-473) Project stage: Withholding Request Acceptance ML12114A0042012-04-18018 April 2012 Supplement to License Amendment Request to Transition to Areva Fuel Project stage: Supplement ML12129A1492012-07-0303 July 2012 Issuance of Amendment Regarding the Transition to Areva Fuel (TAC No. ME3775) (TS-473) Project stage: Approval ML13010A0162013-01-0404 January 2013 CFR 50.46 30-Day Report Project stage: Other 2011-05-12
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000259/20240102024-11-12012 November 2024 Design Basis Assurance Inspection Program Inspection Report 05000259/2024010 and 05000260/2024010 and 05000296/2024010 IR 05000259/20240032024-11-0404 November 2024 Integrated Inspection Report 05000259/2024003 and 05000260/2024003 and 05000296/2024003 CNL-24-043, Application for Subsequent Renewed Operating Licenses, Second Safety Supplement2024-11-0101 November 2024 Application for Subsequent Renewed Operating Licenses, Second Safety Supplement ML24305A1692024-10-31031 October 2024 Site Emergency Plan Implementing Procedure Revision 05000259/LER-2024-003, Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators2024-10-29029 October 2024 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators 05000259/LER-2024-001-02, Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure2024-10-28028 October 2024 Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure ML24299A2632024-10-25025 October 2024 Response to Apparent Violation in NRC Inspection Report 05000260/2024090, EA-24-075 ML24289A1232024-10-24024 October 2024 Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24308A0042024-10-16016 October 2024 Ahc 24-1578 Environmental Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Subsequent License Renewal Application Limestone County CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter ML24239A3332024-09-0303 September 2024 Full Audit Plan IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request ML24219A0272024-08-0606 August 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000259/20244022024-08-0606 August 2024 Security Baseline Inspection Report 05000259/2024402 and 05000260/2024402 and 05000296/2024402 IR 05000259/20240022024-08-0202 August 2024 Brown Ferry Nuclear Plant – Integrated Inspection Report05000259/2024002 and 05000260/2024002 and 05000296/2024002 ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24183A4142024-07-10010 July 2024 – License Renewal Regulatory Limited Scope Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-SLE-0000) (Docket Numbers: 50-259, 50-260, and 50-296) 05000296/LER-2024-003, Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints2024-07-0808 July 2024 Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints 05000259/LER-2024-001-01, Inoperability of Unit 3 Diesel Generator Due to Relay Failure2024-07-0303 July 2024 Inoperability of Unit 3 Diesel Generator Due to Relay Failure ML24184A1142024-07-0202 July 2024 Site Emergency Plan Implementing Procedure Revision ML24183A3842024-07-0101 July 2024 Registration of Use of Cask to Store Spent Fuel (MPC-364, -365) ML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) 05000259/LER-2024-002, Reactor Scram Due to Generator Step-Up Transformer Failure2024-06-24024 June 2024 Reactor Scram Due to Generator Step-Up Transformer Failure ML24175A0042024-06-23023 June 2024 Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System ML24176A1132024-06-23023 June 2024 American Society of Mechanical Engineers, Section XI, Fourth 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owner’S Activity Report Cycle 21 Oper ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24155A0042024-06-18018 June 2024 Proposed Alternative to the Requirements of the ASME Code (Revised Alternative Request 0-ISI-47) ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24071A0292024-06-0505 June 2024 Subsequent License Renewal Application Enclosure 3 - Proprietary Determination Letter ML24068A2612024-06-0505 June 2024 SLRA Fluence Methodology Report - Proprietary Determination Letter ML24151A6322024-05-30030 May 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report IR 05000259/20244032024-05-22022 May 2024 – Security Baseline Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 05000260/LER-2024-002, High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation2024-05-20020 May 2024 High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A0702024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000259/20240012024-05-14014 May 2024 Integrated Inspection Report 05000259/2024001, 05000260/2024001, and 05000296/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 2024-09-03
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24255A5822024-09-10010 September 2024 SLRA - Requests for Additional Information - Set 1 ML24255A5802024-09-10010 September 2024 SLRA - Requests for Additional Information - Set 1 - Email from Jessica Hammock to James Barstow ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A0272024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23332A0042023-11-27027 November 2023 NRR E-mail Capture - Request for Additional Information Related to Proposed Revised Alternative 0-ISI-47 ML23243A9892023-08-29029 August 2023 Inspection Information Request ML23124A0082023-05-0303 May 2023 NRR E-mail Capture - Request for Additional Information Related to Proposed Alternative Requests for the 5th 10-Year Inservice Testing Interval for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML23041A0022023-02-0909 February 2023 NRR E-mail Capture - Request for Additional Information Related to TVA Alternative Request BFN-0-ISI-32 (CNL-22-025) ML22299A0292022-10-26026 October 2022 NRR E-mail Capture - Request for Additional Information for Relief Request BFN-2-ISI-003 Re Weld Examination Coverage ML22292A2722022-10-19019 October 2022 NRR E-mail Capture - Request for Additional Information Related to TVAs Request to Adopt TSTF-505 and TSTF-439 for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML22208A2172022-07-15015 July 2022 NRR E-mail Capture - Request for Additional Information Related to TVA Relief Request BFN-21-ISI-02 (CNL-21-081) ML22174A2722022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22168A0802022-06-17017 June 2022 NRR E-mail Capture - Request for Confirmation of Information and Additional Information Related to TVAs Request to Use Control Bay Chiller Cross-Tie ML22160A4742022-06-0303 June 2022 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Re LAR to Use Advanced Framatome Methodologies in Support of Atrium 11 Fuel ML22168A0392022-05-13013 May 2022 NRR E-mail Capture - Draft Request for Confirmation of Information and Additional Information Related to TVAs Request to Use Control Bay Chiller Cross-Tie ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to TVAs Request to Revised the TVA Plants Radiological Emergency Plans ML22047A1612022-02-16016 February 2022 NRR E-mail Capture - Request for Additional Information Regarding TVAs Request to Expand the SFP Criticality Safety Analysis for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML22025A4132022-01-25025 January 2022 RP Inspection Doc Request ML21343A4232021-12-0909 December 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000259/2022010, 05000260/2022010, and 05000296/2022010) and Request for Information (RFI) ML21173A1042021-06-21021 June 2021 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to TS 3.8.6 ML21041A5422021-02-10010 February 2021 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to Adopt 10 CFR 50.69 ML21041A5432021-02-0505 February 2021 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Draft Request for Additional Information Regarding 10 CFR 50.69 LAR ML21026A1652021-01-26026 January 2021 Document Request for Browns Ferry Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-02 ML20297A3012020-10-22022 October 2020 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to Adopt TSTF-425 ML20296A3782020-10-22022 October 2020 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to Incorporate TMRE ML20294A3762020-09-23023 September 2020 NRR E-mail Capture - Draft Request for Additional Information - Browns Ferry Nuclear Plant, Units 1, 2, and 3, Request to Adopt TSTF-425 ML20266G4472020-09-22022 September 2020 Notification of Inspection and Request for Information ML20224A4732020-08-11011 August 2020 Requalification Program Inspection Browns Ferry Nuclear ML20195B1302020-07-13013 July 2020 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Alternative Request No. 0-ISI-47 ML20149K3212020-05-27027 May 2020 RP Inspection Document Request, Browns Ferry 2020-003 ML20254A3032020-05-13013 May 2020 Request for Supporting Information for the Browns Ferry, Units 1, 2, and 3 Seismic Probabilistic Risk Assessment Audit Review ML20054B8592020-02-20020 February 2020 Emergency Preparedness Program Inspection Request for Information ML20014E6552020-01-14014 January 2020 01 RP Inspection Document Request ML19196A0752019-07-12012 July 2019 NRR E-mail Capture - Final RAIs Browns Ferry Nuclear, Units 1, 2, 3 - Application to Revise Technical Specifications to Adopt TSTF-542 Revision 2, Reactor Pressure Vessel Water Inventory Control ML19116A0712019-06-0303 June 2019 Request for Additional Information Related Resubmittal of Proposed Alternative Request No. 1-ISI-27 for the Period of Extended Operation ML18331A5442018-12-0606 December 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - (Non-Proprietary) ML18317A1642018-11-20020 November 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - Non-Proprietary ML18263A1412018-09-11011 September 2018 NRR E-mail Capture - Browns Ferry Unit 1: RAI Associated with Relief Request 1-ISI-28 ML18138A1102018-05-17017 May 2018 Enclosurequest for Additional Information (Letter to E. D. Schrull Request for Additional Information Regarding Tennessee Valley Authority'S Decommissioning Funding Plan Update for Browns Ferry and Sequoyah Isfsis) ML18108A1872018-04-18018 April 2018 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000259/2018411, 05000260/2018411, and 05000296/2018411 ML18057A6372018-02-23023 February 2018 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet Topical Report TVA-NPG-AWA16 - EPIC: L-2016-TOP-0011) ML17216A0062017-08-18018 August 2017 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Related to LAR to Revise Modifications and Implementations Related to NFPA 805 for Fire Protection for Light Water Reactor Generating Plants (CAC Nos. MF9814-MF9816) ML17163A0502017-06-0808 June 2017 NRR E-mail Capture - RAI for Browns Ferry RR 3-ISI-28 CAC No. MF9257 ML17150A0792017-05-23023 May 2017 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet LAR for EAL Change to Adopt NEI-99-01 Rev.6 (CAC Nos. MF9054 - MF9060) ML16288A0182016-10-27027 October 2016 Browns Ferry Nuclear Plant, Units 2 and 3 - RAI Related to Relief Request for the Use of Alternatives to Certain American Society of Mechanical Engineers, Boiler and Pressure Vessel Code, Section XI Requirements (CAC Nos. MF7795 and MF7796) ML16236A0732016-08-31031 August 2016 Request for Additional Information Related to License Amendment Request to Add New Technical Specification 3.3.8.3 ML16203A0272016-07-25025 July 2016 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Related to License Amendment Request for Adding New Specifications to Technical Specification 3.3.8.3 (CAC Nos. MF6738, MF6739, and MF6740) ML16194A2292016-07-21021 July 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate ML16187A2932016-07-21021 July 2016 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate (CAC Nos. MF6741, MF6742, and MF6743) ML16154A5442016-06-21021 June 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate 2024-09-10
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 24, 2011 Mr. R. M. Krich Vice President, Nuclear Licensing Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 SUB~IECT: BROWNS FERRY NUCLEAR PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING AMENDMENT REQUEST TO TRANSITION TO AREVA FUEL (TAC NO. ME3775)
Dear Mr. Krich:
By letter dated April 16, 2010 (Agencywide Document Access and Management System Accession No. ML101160156), Tennessee Valley Authority (TVA) submitted a request to amend the technical specifications (TSs) for Browns Ferry Nuclear Plant (BFN), Unit 1. The amendment would revise the Operating License to allow the use of AREVA fuel and analytical methodologies for BFN, Unit 1. This information request supports the transition to AREVA fuel for non-Extended Power Uprate power conditions (i.e., 105 percent of Original Licensed Thermal Power level).
Based on our review of your submittal, the U. S. Nuclear Regulatory Commission (NRC) staff finds that a response to the enclosed request for additional information is needed before we can complete the review. The NRC staff forwarded a draft of the enclosure to this request to TVA on January 10, 2011.
The NRC staff held a call with members of your staff on January 14, 2011, to clarify, as necessary, any questions on the draft information request, and it was agreed that a response would be provided by TVA within 30 days of this letter. As a result of the call, the NRC staff agreed that the information requested in Question 8(a) is not needed at this time, therefore the question has been removed.
-2 If you have any questions, please contact me at (301) 415-1055.
s~~
Christopher Gratton, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-259
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv
REQUEST FOR ADDITIONAL INFORMATION PROPOSED LICENSE AMENDMENT REQUEST FOR TECHNICAL SPECIFICATION CHANGE TS-473 -AREVA FUEL TRANSITION TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT, UNIT 1 DOCKET NO. 50-259 By letter dated April 16, 2010, Tennessee Valley Authority (TVA) submitted a request for amendment to the Technical Specifications (TS) for Browns Ferry Nuclear Plant (BFN), Unit 1.
The amendment request proposed to add the AREVA NP analysis methodologies to the list of approved methods to be used in determining the core operating limits in the Core Operating Limits Report (COLR). The scope of this application focuses on BFN Unit 1 transition to AREVA fuel, addition of AREVA NP analyses methodologies to the list of approved methods to be used in determining the core operating limits in the COLR, and additional TS changes to reflect the AREVA NP specific methods for monitoring and enforcing the thermal limits. TVA is also requesting approval for transition to AREVA fuel for BFN Unit 1 for non-extended power uprate conditions (105 percent Original Licensed Thermal Power Level).
The Nuclear Regulatory Commission (NRC) staff has reviewed the license amendment request, and has determined that additional information is needed in order to complete our evaluation.
- 1. ANP-2877P, Section 1.0 Explain what "chamfered pellet design" is and describe how this design reduces the occurrence of pellet chipping during manufacturing, and then reducing the pellet-clad-interaction failure due to missing pellet surface.
- 2. ANP-2877P, Section 2.1.4 Explain the "Harmonized Advanced Load Chain" modifications that improved the upper tie plate (UTP) connection by making it simpler and more robust,
- 3. ANP-2877P, Section 2.1.5, ANP-2859(P) Appendix B (a) Provide details of the distribution of Gadolinia (U02 +Gd 2 0 3) rods in the BFN Unit 1 core for the upcoming cycle, with respect to the number of Gadolinia rods and respective Gadolium (Gd) enrichment.
(b) With degraded thermal conductivity, and lower melting point of the U02+Gd 2 0 3 mixture, describe what adjustments are made in the Gadolinia rods to prevent failure of the Gadolinia rod melting. Is there any restriction on linear heat Enclosure
-2 generation rate (LHGR) limit for the Gadolinia rods during normal operation and anticipated operational occurrences (ADOs)?
(c) Section 3.2.4 of At\lP-2877 indicates that "for ADOs, the fuel temperatures are calculated using the same power history (as for normal operating temperatures),
except that additional calculations are performed at elevated power levels as a function of exposure corresponding with the Protection Against Power Transients (PAPT) LHGR limit." Describe this process with example calculations.
(d) Describe the adjustments, and how the adjustments are applied to the fuel melt temperature, for exposure and Gadolinia content, as stated in Section 3.2.4 of ANP-2877. Show a typical calculation.
- 4. ANP-2877P, Section 3.2 Section 3.2, under bullet "Cladding Collapse," states that "The pellet/clad gap is evaluateq [up to a proprietary rod exposure] to ensure the cladding does not [proprietary end state].
Section 3.2.2 "Cladding Collapse" states that gap conditions are evaluated after the first
[proprietary rod exposure stating a different end state than Section 3.2 above].
After reviewing the proprietary information contained in ANP-2877, Section 3.2, please explain why there is discrepancy between the above two statements and correct the error, if needed.
- 5. ANP-2877P, Section 3.2.6 Section 3.2.6 of ANP-2877 states that "the evaluation (for cladding rupture) is covered separate from this report." Identify the location of this report if it is part of the license amendment request or is contained in other docketed material. Otherwise, please provide a copy of this report.
- 6. ANP-2877P, Sections 3.2.8, and 3.3.7 Discuss the impact of Gd content in Gadolinia rods (UO z+Gd z0 3 ) on fuel densification, swelling and fission gas release in fuel rods.
- 7. ANP-2877P, Section 3.3.8 Section 3.3.8 states that "Mixed core conditions for liftoff are considered on a specific basis as determined by the plant and other fuel types. Analyses to date indicate a large margin to liftoff under normal operating conditions." Justify this claim by providing a summary of the analysis and calculations.
- 8. ANP-2877P, Sections 3.4.1 through 3.4.3, Table 3.3 Item 3.4.2 (a) [deleted]
(b) Item 3.4.2 of Table 3.3 indicates that violent expulsion of fuel criteria for fuel is less than 280 calories per gram (cal/g) for coolability, and is less than 170 cal/g for rod failure. Standard Review Plan (SRP, NUREG-0800) Section 4.2, Appendix B, Section C (Core coolability criteria) stipulates that for fuel rod
-3 thermal-mechanical calculations, employed to demonstrate compliance with Criteria 1 (peak radial average fuel enthalpy must remain below 230 cal/g) and Criteria 2 (peal fuel temperature must remain below incipient fuel melting conditions), must be based upon design-specific information accounting for manufacturing tolerances and modeling using the NRC-approved methods, including burnup-enhanced effects on pellet power distribution, fuel thermal conductivity, and fuel melting temperature. Provide justification for the items in 3.4.2 of Table 3.3 in support of the Standard Review Plan acceptance criteria, specifically, the difference between the SRP value for coolability (less than 230 cal/g) and the value in Table 3.3, item 3.4.2.
- 9. ANP-2821 (P) Thermal- Hydraulic (T-H) Design Report, Section 3.1 Provide a summary of detailed calculations for thermal-hydraulic characterization for the ATRIUM 10 reload fuel for BFN Unit 1. These calculations should show how the licensee obtained the loss coefficients and friction factors listed in Table 3.3 of ANP-2821; for example, the upper tie plate (UTP) loss coefficient, spacer loss coefficients, lower tie plate (LTP) grid loss coefficients, orifice, and LTP loss coefficients.
- 10. ANP-2821 (P), Section 3.2 Provide detailed calculations that demonstrate thermal-hydraulic compatibility of ATRIUM 10 with the co-resident GE14 fuel in BFN Unit 1. These calculations should show the following:
(a) Calculations should demonstrate that during the entire transition from a full core GE14 to a full core ATRIUM 10 fuel, there will be no major impacts on thermal-hydraulic operation of BFN Unit 1 and should demonstrate compliance over the entire licensing range of the power/flow map.
(b) Justify your selection of bottom-peaked axial power distribution as a basis for the hydraulic compatibility results, compared to the results for top- and middle peaked axial power distributions.
- 11. Thermal margin performance (a) Discuss the impact of part length rods and Gadolinia (UO z+Gd z0 3 ) on the application of SPCB critical power correlation.
(b) Will any of these part length rods undergo boiling transition/dryout during normal operating conditions or during transients and accident conditions?
- 12. Mixed core and Critical Power Ratio (CPR) calculations The proposed BFN Unit 1 core with AREVA Atrium 10 and GE14 fuel designs will constitute a "mixed core."
Provide details of the impact of the mixed core on the CPR calculations, accounting for the differences in mechanical, thermal and hydraulic characteristics of the two fuel designs in the transition core at BFN Unit 1.
-4
- 13. ANP-2821 P, Section 3.6 Stability General Design Criterion 12 of Title 10 of the Code of Federal Regulations, Part 50 Appendix A requires suppression of reactor power oscillations so that the Specified Acceptable Fuel Design Limits are not exceeded. Demonstrate, with supporting analyses and calculations, how thermal hydraulic and neutronic stability of the mixed core will be maintained at the BFN Unit 1 throughout the upcoming and following cycles of operation.
- 14. ANP-2859P Section 2.0 Provide a reference or summarize the methodology by which BFN Unit 1 is designed to achieve 71 Gigawatt-days of additional energy via final feedwater temperature reduction operation, beyond the full power capability.
- 15. Shutdown Margin Describe the analysis procedure used to ensure that the shutdown margin is within the TS limit throughout the transition cycles. Specifically, address how the eigenvalue biases and uncertainties are determined and accounted for during the transition cycles.
- 16. EMF-2158 Licensee has used EMF-2158 methodology to perform fuel cycle design and fuel management calculations for the Cycle 10 operation of BFN Unit 1 to generate nuclear data including cross sections, local power peaking factors, and associated uncertainties.
Section 5 of XN-NF-80-19(P)(A), Volume 1, Supplement 3, and Section 9 of EMF-2158(P)(A) together provide very detailed description of the analyses and calculations to determine the traversing in-core probe detector (TIP) uncertainty components for boiling-water reactors.
Sections 9.4 and 9.5 provide combined uncertainties for TIP distribution calculations, TIP distribution measurement, net calculated TIP distribution and synthesized TIP distribution uncertainty. Provide details of the calculations and uncertainties listed in Chapter 9 of EMF-2158 applicable to the D-Iattice BFN Unit 1 plant. Show that the BFN Unit 1 uncertainties documented in EMF-2158 for D-Iattice plants remain conservative.
-2 If you have any questions, please contact me at (301) 415-1055.
Sincerely, IRA!
Christopher Gratton, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-259
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION PUBLIC LPLlI-2 RlF RidsNrrDorlLpl2-2 RidsNrrDssSnpb RidsNrrPMBrownsFerry RidsNrrLABClaylon RidsOgcRp RidsRgn2MailCenter RidsNrrAcrsAcnwMailCtr RidsNrrDorlDpr ADAMS Accession No* ML110180585 OFFICE LPL2-2/PM LPL2-2/LA DSS/SNPB LPL2-2/BC LPL2-2/PM NAME CGratton BClaylon AMendiola DBroaddus CGratton DATE 01/21/11 01/21/11 01/24/11 01/21/11 01/24/11 OFFICIAL RECORD COpy