November 8, 2007Administrative JudgeAdministrative JudgeRichard F. ColePaul B. Abramson
Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board PanelMail Stop: T-3F23Mail Stop: T-3F23 U.S. Nuclear Regulatory CommissionU.S. Nuclear Regulatory Commission Washington, DC 20555-0001Washington, DC 20555-0001 Administrative Judge Ann Marshall Young, Chair
Atomic Safety and Licensing Board Panel
Mail Stop: T-3 F23
U.S. Nuclear Regulatory Commission
Washington, DC 20555-0001 In the Matter of Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc.(Pilgrim Nuclear Power Station)
Docket No. 50-293-LR; ASLBP No. 06-848-02-LR
Dear Administrative Judges:
The NRC Staff hereby provides its notice that it has updated the hearing file for this proceeding pursuant to 10 C.F.R. § 2.336(d) as modified by the Board's Order
Regarding Schedule for Proceeding and Related Matters (November 29, 2006). An index
containing the ADAMS accession number, date, and title or description of each item in the
hearing file is appended hereto as Attachment 1.
The Staff has no updates to its privilege log required by 10 C.F.R. § 2.336(b)(5) at this time; however, the Staff is continuing to preserve and maintain all privileged documents during the pendency of this proceeding. Also attached R. Cole P. Abramson
A. Young are the Affidavit of Perry Buckberg, as required by 10 C.F.R. § 2.336(c), and the three documents contained in the hearing file, due to technical issues associated with ability of thepublic to access ADAMS.
Sincerely,/RA/Kimberly A. Sexton Counsel for the NRC Staff
Enclosures:
Hearing File Index Affidavit of Perry Buckberg
2007/10/16 Pilgrim Renewal Hearing - Replacement page 3/4.2-17
2007/10/17 Pilgrim Renewal Hearing - Pilgrim License Conditions 2007/10/17 Pilgrim Renewal Hearing - Resolution of discrepancy between NRC and Entergy controlled versions of Pilgrim Tech Specscc:Attached Service List ATTACHMENT 1: PILGRIM LICENSE RENEWAL HEARING FILE AND MANDATORY DISCLOSURES HEARING FILE INDEX Supplement 15- November 8, 2007Accession NumberDocument DateTitle/Description:15-01ML07310022510/16/20072007/10/16 Pilgrim Renewal Hearing - Replacement page 3/4.2-17 15-02ML07310022910/17/20072007/10/17 Pilgrim Renewal Hearing - Pilgrim License Conditions 15-03ML07310022610/17/20072007/10/17 Pilgrim Renewal Hearing - Resolution of discrepancy between NRC and Entergy controlled versions of Pilgrim Tech Specs November 8, 2007 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARDIn the Matter of)
)ENTERGY NUCLEAR GENERATION )Docket No. 50-293-LR COMPANY AND ENTERGY NUCLEAR)
OPERATIONS, INC.)ASLBP No. 06-848-02-LR
)(Pilgrim Nuclear Power Station))
AFFIDAVIT OF PERRY BUCKBERG CONCERNING MANDATORY DISCLOSURE REQUIREMENT OF 10 C.F.R. § 2.336(c)
I, Perry Buckberg, do hereby state as follows:1.I am employed as a Project Manager in the Division of License Renewal in theNuclear Regulatory Commission's ("NRC") Office of Nuclear Reactor Regulation. I serve as a
project manager for the Pilgrim Nuclear Power Station's license renewal application ("LRA"). 2.I hereby certify that all relevant materials required to be disclosed pursuant to10 C.F.R. § 2.336 (b) and (c) in the captioned proceeding have been disclosed, and that the
disclosures are accurate and complete as of the date of this certification.3.I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information and belief./Original Signed By/
______________________
Perry Buckberg Executed in Rockville, MD this 8 th day of November, 2007 From: "Sanchez, Edward" <esanch1@entergy.com>
To: "Perry Buckberg" <PHB1@nrc.gov> Date: 10/16/2007 10:01:26 AM
Subject:
Replacement page 3/4.2-17 Perry, Pilgrim inadvertently issued an in correct page 3/4.2-17 into our controlled Tech Specs when they we re updated for License Amendment 200. I entered the condition into Pilgri m's corrective action program and have already had Document Control co rrect the controlled copy with the correct page which is attached. Please use the attached page for the controlled copy you are working with. I believe you told me the NRC's
version was correct - it was the ve rsion on the CD I sent you that was incorrect.
- Thanks, Ed Sanchez Pilgrim Licensing Hearing Identifier: PilgrimRenewalNonPublic Email Number: 81 Mail Envelope Properties (47304396.HQGWDO01.TWGWPO03.200.2000003.1.12FEF1.1)
Subject:
Replacement page 3/4.2-17 Creation Date: 10/16/2007 10:01:26 AM From: "Sanchez, Edward" <esanch1@entergy.com>
Created By: esanch1@entergy.com
Recipients "Perry Buckberg" <PHB1@nrc.gov>
Post Office Route TWGWPO03.HQGWDO01 nrc.gov
Files Size Date & Time MESSAGE 563 10/16/2007 10:01:26 AM Scan001.PDF 25948 11/6/2007 10:36:06 AM Mime.822 38472 11/6/2007 10:36:06 AM
Options Priority: Standard Reply Requested: No Return Notification: None None
Concealed
Subject:
No Security: Standard
From: Perry Buckberg To: "Steve Bethay" <sbethay@entergy.com> Date: 10/17/2007 8:07:51 AM
Subject:
Pilgrim License Conditions cc: "Edward Sanchez" <esanch1@entergy.com>,"James Kim" <JSK@nrc.gov>,"Louise Lund" <LXL@nrc.gov>,"Susan Uttal" <SLU@nrc.gov>
Steve, Below are the four Pilgrim License Renewal SER (June 28, 2007) license conditions as they will read in renewed Facility Operating License DPR-35. Please contact me if you have any comments on these license conditions.
Thanks, Perry Buckberg Project Manager Nuclear Regulatory Commission Division of License Renewal phone: (301)415-1383 fax: (301)415-3031 phb1@nrc.gov
G. The Updated Safety Analysis Report supplement, as revised, submitted pursuant to 10 CFR 54.21(d), shall be included in the next scheduled update to the Updated Safety Analysis Report required by 10 CFR 50.71(e)(4) following the issuance of this renewed operating license. Until that update is complete, ENO may make changes to the programs and activities described in the supplement without prior Commission approval, provided that ENO evaluates such changes pursuant to the criteria set forth in 10 CFR 50.59 and otherwise complies with the requirements in that section. H. The Updated Final Safety Analysis Report supplement, as revised, describes certain future activities to be completed prior to the period of extended operation. Entergy Nuclear Operations, Inc., shall complete these activities no later than June 8, 2012, and shall notify the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection. I. All capsules in the reactor vessel that are removed and tested must meet the test procedures and reporting requirements of the most recent NRC-approved version of the Boiling Water Reactor Vessels and Internals Project (BWRVIP) Integrated Surveillance Program (ISP) appropriate for the configuration of the specimens in the capsule. All capsules placed in storage must be maintained for future insertion. Any changes to storage requirements must be approved by the NRC, as required by 10 CFR Part 50, Appendix H. J. On or before June 8, 2010, the applicant will submit to the NRC correctly benchmarked RV neutron fluence calculations, consistent with RG 1.190, that will confirm that the neutron fluence for the lower intermediate shell axial welds, at the inner surface of the RV, will not reach the limiting value of 3.37 x 1018 n/cm2 (E > 1.0 MeV) by the end of the period of extended operation (54 EFPY).
Hearing Identifier: PilgrimRenewalNonPublic Email Number: 85 Mail Envelope Properties (47304396.HQGWDO01.TWGWPO03.200.2000009.1.143A99.1)
Subject:
Pilgrim License Conditions Creation Date: 10/17/2007 8:07:51 AM From: Perry Buckberg Created By: PHB1@nrc.gov
Recipients "Edward Sanchez" <esanch1@entergy.com> "James Kim" <JSK@nrc.gov> "Louise Lund" <LXL@nrc.gov>
"Susan Uttal" <SLU@nrc.gov> "Steve Bethay" <sbethay@entergy.com>
Post Office Route TWGWPO03.HQGWDO01 nrc.gov Files Size Date & Time MESSAGE 2345 10/17/2007 8:07:51 AM TEXT.htm 5087 11/6/2007 10:36:06 AM
Options Priority: Standard Reply Requested: No Return Notification: None None
Concealed
Subject:
No Security: Standard Steve, Below are the four Pilgrim License Renewal SER (June 28, 2007) license conditions as they will read in renewed Facility Operating License DPR-35. Please contact me if you have any comments on these license conditions.
Thanks, Perry Buckberg Project Manager Nuclear Regulatory Commission Division of License Renewal phone: (301)415-1383 fax: (301)415-3031 phb1@nrc.gov G. The Updated Safety Analysis Report supplement, as revised, submitted pursuant to 10 CFR 54.21(d), shall be included i n the next scheduled update to the Updated Safety Analysis Report required by 10 CFR 50.71(e)(4) following the issuance of this renewed operating license. Until that update is complete, ENO may make changes to the programs and activities described in the supplement without prio r Commission approval, provided that ENO evaluates such changes pursuant to the criteria set forth in 10 CFR 50.59 and otherwise complies with the requirements in that section.
H. The Updated Final Safety Analysis Report supplement, as revised, describes certain future activities to be completed prior to the period of extended operation. Entergy Nuclear Operations, Inc., shall complete these activities no later than June 8, 2012, and shall notify the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection.
I. All capsules in the reactor vessel that are removed and tested must meet the test procedures and reporting requirements of the most recent NRC-approved version of the Boiling Water Reactor Vessels and Internals Project (BWRVIP) Integrated Surveillance Program (ISP) appropriate for the configuration of the specimens in the capsule. All capsules placed in storage must be maintained for future insertion. Any changes to storage requirements must be approved by the NRC, as required by 10 CFR Part 50, Appendix H.
J. On or before June 8, 2010, the applicant will submit to the NRC correctly benchmarked RV neutron fluence calculations, consistent with RG 1.190, that will confirm that the neutron fluence for the lower intermediate shell axial welds, a t the inner surface of the RV, will not reach the limiting value of 3.37 x 10 18 n/cm 2 (E > 1.0 MeV) by the end of the period of extended operation (54 EFPY).
Pa ge 1of 1 11/6/2007file://c:\EMailCa pture\Pil g rimRenewalNonPub lic\85\attch1.htm From: "Sanchez, Edward" <esanch1@entergy.com>
To: "Perry Buckberg" <PHB1@nrc.gov>,"James Kim" <JSK@nrc.gov> Date: 10/17/2007 10:52:59 AM
Subject:
Resolution of discrepancy between NRC and Entergy controlled versions of Pilgrim Tech Specs
Perry and Jim, Pilgrim TS Section 3/4.4 Standby Liquid Control System was amended by License Amendment 169, which over hauled and consolidated the section resulting in pages 3/4.4-3, 3/4.4-4, and 3/4.4-5 bei ng removed. That is why there are only TS pages 3/4.4-1 and 3/4.4-2 for that section. Also note that License Amendment 170 later made a change to a portion of TS page 3/4.4-1. Therefore last amendment affecti ng page 3/4.4-1 is LA 170 and last amendment affecti ng page 3/4.4-2 is LA 169.
Pilgrim TS Section 3/4.8 and TS Section 7/8 were amended by License Amendmat 177. LA 177 relocated TS pages 3/4.8-3 through 20 and Section 7/8 pages 1-17 to the Pilgrim O ffsite Dose Calculation Manual.
Therefore, with respect to theses sections I am confident that the CD I sent you containing the Pilgrim controlled copy of Tech Specs is
correct.
Please let me know if you need additional information.
Ed Sanchez Pilgrim Licensing
Original Message-----
From: Sanchez, Edward
Sent: Tuesday, October 16, 2007 10:01 AM
To: 'Perry Buckberg'
Subject:
Replacement page 3/4.2-17
- Perry,
Pilgrim inadvertently issued an in correct page 3/4.2-17 into our controlled Tech Specs when they we re updated for License Amendment 200. I entered the condition into Pilgri m's corrective action program and have already had Document Control co rrect the controlled copy with the correct page which is attached. Please use the attached page for the controlled copy you are working with. I believe you told me the NRC's version was correct - it was the ve rsion on the CD I sent you that was incorrect.
- Thanks, Ed Sanchez Pilgrim Licensing Hearing Identifier: PilgrimRenewalNonPublic Email Number: 82 Mail Envelope Properties (47304396.HQGWDO01.TWGWPO03.200.2000002.1.F2037.1)
Subject:
Resolution of discrepancy between NRC and Entergy controlled versions of Pilgrim Tech Specs Creation Date: 10/17/2007 10:52:59 AM From: "Sanchez, Edward" <esanch1@entergy.com>
Created By: esanch1@entergy.com Recipients "Perry Buckberg" <PHB1@nrc.gov> "James Kim" <JSK@nrc.gov>
Post Office Route TWGWPO03.HQGWDO01 nrc.gov
Files Size Date & Time MESSAGE 1679 10/17/2007 10:52:59 AM Mime.822 3962 11/6/2007 10:36:06 AM Options Priority: Standard Reply Requested: No Return Notification: None None Concealed
Subject:
No Security: Standard UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARDIn the Matter of)
)ENTERGY NUCLEAR OPERATIONS, INC. )Docket No. 50-293-LR
)
(Pilgrim Nuclear Power Station) )ASLBP No. 06-848-02-LR
) CERTIFICATE OF SERVICE I hereby certify that copies of the letter notifying the administrative judges and the parties that
the hearing file and affidavit in the above-captioned proceeding have been served on the following by electronic mail and deposit in the U.S. Mail Service or by deposit in the U.S.
Nuclear Regulatory Commission's internal mail system as indicated by a single asterisk(*), or by
deposit in the U.S. mail system, as indicated by a double asterisk (**) this 8 th day of November, 2007.Administrative Judge*
Richard F. Cole
Atomic Safety and Licensing Board Panel
Mail Stop: T-3F23
U.S. Nuclear Regulatory Commission
Washington, DC 20555-0001
E-mail: rfc1@nrc.gov Administrative Judge*
Ann Marshall Young, Chair
Atomic Safety and Licensing Board Panel
Mail Stop: T-3F23
U.S. Nuclear Regulatory Commission
Washington, DC 20555-0001
E-mail: amy@nrc.gov Sheila Slocum Hollis**
Duane Morris LLP
1667 K Street, NW, Suite 700
Washington, DC 20006
E-mail: sshollis@duanemorris.com Administrative Judge*
Paul B. Abramson
Atomic Safety and Licensing Board Panel
Mail Stop: T-3F23
U.S. Nuclear Regulatory Commission
Washington, DC 20555-0001
E-mail: pba@nrc.gov Office of Commission Appellate
- Adjudication
Mail Stop: O-16C1
U.S. Nuclear Regulatory Commission
Washington, DC 20555-0001
E-mail: OCAAMail@nrc.gov Office of the Secretary*
Attn: Rulemaking and Adjudications Staff
Mail Stop: O-16C1
U.S. Nuclear Regulatory Commission
Washington, DC 20555-0001
E-mail: hearingdocket@nrc.gov Atomic Safety and Licensing Board*
Mail Stop: T-3 F23
U.S. Nuclear Regulatory Commission
Washington, DC 20555-0001 Mary Lampert**
148 Washington Street
Duxbury, MA 02332
E-mail: mary.lampert@comcast.net Chief Kevin M. Nord**
Fire Chief & Director Duxbury Emergency
Management Agency
668 Tremont Street
Duxbury, MA 02332
E-mail: nord@town.duxbury.ma.us Fax: 781-934-6530 Terence A. Burke, Esq.**
Entergy Nuclear
1340 Echelon Parkway
Mail Stop: M-ECH-62
Jackson, MS 39213 David R. Lewis, Esq.**
Paul A. Gaukler, Esq.
Pillsbury, Winthrop, Shaw, Pittman, LLP
2300 N Street, NW
Washington, DC 20037-1137
E-mail: david.lewis@pillsburylaw.com paul.gaukler@pillsburylaw.com Town Manager**
Town of Plymouth
11 Lincoln St.
Plymouth, MA 02360
E-mail: msylvia@townhall.plymouth.ma.us
/RA/
Kimberly A. Sexton Counsel for the NRC Staff