| | {{#Wiki_filter:PRELIMINARY NOTIFICATION October 3, 2011 |
| | |
| | PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE PNO-III-11-011-A This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. Some of the information may not yet be fully verified or evaluated by the Region III staff. |
| | Facility Palisades Nuclear Plant Entergy Nuclear Operations, Inc. Covert, Michigan Docket No: 50-255 License No: DPR-20 Licensee Emergency Classification Notification of Unusual Event Alert Site Area Emergency General Emergency x Not Applicable |
| | |
| | ==SUBJECT:== |
| | PALISADES REACTOR TRIP (UPDATE) |
| | |
| | == Description:== |
| | |
| | On October 2, 2011, Palisades restarted following a forced outage. Palisades entered the forced outage on September 25, 2011, following an automatic reactor trip due to the loss of one of two trains of direct current (DC) power. The loss of the DC bus took place due to an electric fault that occurred in a DC distribution panel while plant workers were performing troubleshooting activities. |
| | |
| | The NRC resident inspectors, augmented by a Special Inspection Team, monitored operator actions following the reactor trip, as well as, the repair activities. Before the reactor start-up, the NRC inspectors reviewed the evaluations and tests performed to assure the adequacy of the plant repairs. In addition, the inspectors were present in the control room to monitor the subsequent restart. The Special Inspection Team continues to evaluate this event and will issue a report after completion of the inspection. |
| | This preliminary notification is issued for information only. The state of Michigan has been informed. The NRC issued a press release on September 28, 2011, describing the event and the start of a Special Inspection Team to review the event. |
| | |
| | The information presented herein has been discussed with the licensee, and is current as of 10:30 a.m. (CST), on October 3, 2011. |
| | ADAMS Accession Number: ML112760722. |
| | |
| | CONTACTS: John Ellegood John Giessner 269/764-8971 630/829-9619 |
| | |
| | John.Ellegood@nrc.gov John.Giessner@nrc.gov}} |
Revision as of 23:43, 2 August 2018
|
---|
Category:NRC Preliminary Notification of Event/Occurrence
MONTHYEARPNO-III-19-002, Palisades, Through-Wall Leak Identified on a Reactor Vessel Head Nozzle2018-11-14014 November 2018 PNO-III-19-002: Palisades, Through-Wall Leak Identified on a Reactor Vessel Head Nozzle PNO-III-19-001, Maintenance Outage to Repair Control Rod Drive and Failed Transformer2018-10-18018 October 2018 PNO-III-19-001: Maintenance Outage to Repair Control Rod Drive and Failed Transformer PNO-III-14-002, A: Update, Palisades Control Rod Drive Mechanism Housing Flaws2014-03-14014 March 2014 PNO-III-14-002A: Update, Palisades Control Rod Drive Mechanism Housing Flaws ML14030A1902014-01-30030 January 2014 PNO-III-14-002: Palisades Control Rod Drive Mechanism Housing Flaws PNO-III-13-004, B, Update - Palisades Shutdown Due to Safety Injection Refueling Water Tank (SIRWT) Leakage2013-06-17017 June 2013 PNO-III-13-004B, Update - Palisades Shutdown Due to Safety Injection Refueling Water Tank (SIRWT) Leakage ML13129A4382013-05-0909 May 2013 PNO-III-13-004A - Update: Palisades Shutdown Due to Safety Injection Refueling Water Storage Tank (SIRWT) Leakage ML13126A2702013-05-0606 May 2013 PNO-III-13-004 - Palisades Shutdown Due to Safety Injections Refueling Water Storage Tank Leakage PNO-III-13-002, A - Update - Palisades Shutdown Due to Leakage from the Component Cooling Water (CCW) System2013-02-22022 February 2013 PNO-III-13-002A - Update - Palisades Shutdown Due to Leakage from the Component Cooling Water (CCW) System ML13046A4042013-02-15015 February 2013 PNO-III-13-002, Palisades Shutdown Due to Leakage from the Component Cooling Water (CCW) System ML12314A2712012-11-0909 November 2012 PNO-lll-12-015A (Update) Palisades Shutdown Due to Leakage from the Main Steam System ML12310A5052012-11-0505 November 2012 PNO-lll-12-015, Palisades Shutdown Due to Leakage from the Main Steam System PNO-III-12-012, Palisades Leakage from the Service Water System2012-09-25025 September 2012 PNO-III-12-012: Palisades Leakage from the Service Water System PNO-III-12-007, A, Update, Palisades Shutdown Due to Increase in Unidentified Reactor Coolant System Leakage2012-08-30030 August 2012 PNO-III-12-007A, Update, Palisades Shutdown Due to Increase in Unidentified Reactor Coolant System Leakage PNO-III-12-004, A: Update - Palisades Shutdown Due to Safety Injection Refueling Water Storage Tank Leakage2012-07-11011 July 2012 PNO-III-12-004A: Update - Palisades Shutdown Due to Safety Injection Refueling Water Storage Tank Leakage ML12166A2612012-06-14014 June 2012 PNO-III-12-004 - Palisades Shutdown Due to Safety Injection Refueling Water Storage Tank Leakage PNO-III-11-011, A - Palisades Reactor Trip (Update)2011-10-0303 October 2011 PNO-III-11-011-A - Palisades Reactor Trip (Update) ML11269A2302011-09-26026 September 2011 PNO-III-11-011 Palisades Nuclear Plant Reactor Trip PNO-III-11-010, Palisades - Unplanned Shutdown Greater than 72 Hours and Notification of Unusual Event2011-09-19019 September 2011 PNO-III-11-010 - Palisades - Unplanned Shutdown Greater than 72 Hours and Notification of Unusual Event ML1123601032011-08-23023 August 2011 PNO-II-11-005: North Anna, Emergency Declarations Due to Seismic Event PNO-III-11-003, Palisades Shutdown Due to Loss of Main Generator Electrical Load2011-01-24024 January 2011 PNO-III-11-003, Palisades Shutdown Due to Loss of Main Generator Electrical Load PNO-III-11-001, ; Palisades, Unusual Event and 72-Hour Limiting Condition for Operation Due to 4160 V Ground Fault2011-01-11011 January 2011 PNO-III-11-001; Palisades, Unusual Event and 72-Hour Limiting Condition for Operation Due to 4160 V Ground Fault PNO-III-10-010, A: Update - Palisades Forced Shutdown for Greater than 72 Hours to Replace Leaking Control Rod Drive Seal2010-07-0606 July 2010 PNO-III-10-010A: Update - Palisades Forced Shutdown for Greater than 72 Hours to Replace Leaking Control Rod Drive Seal ML1017605222010-06-25025 June 2010 PNO-III-10-010 - Palisades - Forced Shutdown for Greater than 72 Hours to Replace Leaking Control Rod Drive Seal PNO-III-09-001, A - Palisades Forced Shutdown for Greater than 72 Hours to Replace Leaking Control Rob Drive Seal (Update)2009-02-23023 February 2009 PNO-III-09-001A - Palisades Forced Shutdown for Greater than 72 Hours to Replace Leaking Control Rob Drive Seal (Update) ML0904905272009-02-18018 February 2009 PNO-III-09-001, Palisades Forced Shutdown for Greater than 72 Hours to Replace Leaking Control Rod Drive Seals PNO-III-08-008, A - Palisades - Forced Shutdown to Replace Leaking Control Rod Drive (CRD) Seal Packages (Update)2008-08-11011 August 2008 PNO-III-08-008A - Palisades - Forced Shutdown to Replace Leaking Control Rod Drive (CRD) Seal Packages (Update) ML0822003472008-08-0707 August 2008 PNO-III-08-008 - Palisades Forced Shutdown to Replace Leaking Control Rod Drive Seals PNO-III-08-004, A, Cook and Palisades, Update - Unusual Events Declared Due to Earthquake2008-04-18018 April 2008 PNO-III-08-004A, Cook and Palisades, Update - Unusual Events Declared Due to Earthquake ML0810903102008-04-18018 April 2008 PNO-III-08-004: Cook & Palisades, Unusual Events Declared Due to Earthquake PNO-III-07-006, A: Palisades, Shutdown Due to Low Steam Generator Level (Update)2007-05-14014 May 2007 PNO-III-07-006A: Palisades, Shutdown Due to Low Steam Generator Level (Update) ML0712905812007-05-0909 May 2007 PNO-III-07-006: Palisades Shutdown Due to Low Steam Generator Level PNO-III-07-003, A - Palisades: Shutdown to Replace Heat Damaged Cables (Update)2007-03-0505 March 2007 PNO-III-07-003A - Palisades: Shutdown to Replace Heat Damaged Cables (Update) ML0705805222007-02-27027 February 2007 PNO-III-07-003: Palisades - Palisades Shutdown to Replace Heat-Damaged Cables PNO-III-06-013, Palisades Shutdown to Investigate Control Rod Withdrawal Problem2006-05-11011 May 2006 PNO-III-06-013: Palisades Shutdown to Investigate Control Rod Withdrawal Problem PNO-III-04-010, Palisades Shut Down to Repair Control Rod Drive Mechanism Leakage2004-08-11011 August 2004 PNO-III-04-010: Palisades Shut Down to Repair Control Rod Drive Mechanism Leakage PNO-III-03-040, Fire Adjacent to Palisades Nuclear Generating Station2003-09-22022 September 2003 PNO-III-03-040 - Fire Adjacent to Palisades Nuclear Generating Station PNO-III-03-014, B: Palisades Loss of Shutdown Cooling Caused by Loss of Offsite Power (Second Update)2003-03-28028 March 2003 PNO-III-03-014B: Palisades Loss of Shutdown Cooling Caused by Loss of Offsite Power (Second Update) ML0308605932003-03-27027 March 2003 PNO-III-03-14A: Palisades Loss of Shutdown Cooling Caused by Loss of Offsite Power (Update) PNO-III-03-013, Alert Declared Due to Fire with Potential to Affect Safety Systems2003-03-19019 March 2003 PNO-III-03-013: Alert Declared Due to Fire with Potential to Affect Safety Systems 2018-11-14
[Table view] |
Text
PRELIMINARY NOTIFICATION October 3, 2011
PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE PNO-III-11-011-A This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. Some of the information may not yet be fully verified or evaluated by the Region III staff.
Facility Palisades Nuclear Plant Entergy Nuclear Operations, Inc. Covert, Michigan Docket No: 50-255 License No: DPR-20 Licensee Emergency Classification Notification of Unusual Event Alert Site Area Emergency General Emergency x Not Applicable
SUBJECT:
PALISADES REACTOR TRIP (UPDATE)
Description:
On October 2, 2011, Palisades restarted following a forced outage. Palisades entered the forced outage on September 25, 2011, following an automatic reactor trip due to the loss of one of two trains of direct current (DC) power. The loss of the DC bus took place due to an electric fault that occurred in a DC distribution panel while plant workers were performing troubleshooting activities.
The NRC resident inspectors, augmented by a Special Inspection Team, monitored operator actions following the reactor trip, as well as, the repair activities. Before the reactor start-up, the NRC inspectors reviewed the evaluations and tests performed to assure the adequacy of the plant repairs. In addition, the inspectors were present in the control room to monitor the subsequent restart. The Special Inspection Team continues to evaluate this event and will issue a report after completion of the inspection.
This preliminary notification is issued for information only. The state of Michigan has been informed. The NRC issued a press release on September 28, 2011, describing the event and the start of a Special Inspection Team to review the event.
The information presented herein has been discussed with the licensee, and is current as of 10:30 a.m. (CST), on October 3, 2011.
ADAMS Accession Number: ML112760722.
CONTACTS: John Ellegood John Giessner 269/764-8971 630/829-9619